Hello, could you help me solve this question, please?
Thank you very much!
Question:
(a) A project has EIGHT (8) activities listed in the following table:
Activity |
Immediate Predecessor (s) |
Time (Weeks) |
Activity |
Immediate Predecessor (s) |
Time (Weeks) |
A |
- |
2 |
E |
C |
3 |
B |
A |
5 |
F |
C |
7 |
C |
A |
3 |
G |
D, E |
2 |
D |
B |
4 |
H |
F |
3 |
(i) Use the GRAPH PAPER provided to construct a Gantt chart for the above project. [Note: You are to attach the graph paper to the page where this question is answered].
(ii) What is the expected project duration in weeks?
(b) Explain the following TWO (2) terms in lean operations:
(i) Kanban.
(ii) Toyota production system (TPS)
Answer
Part a)
As per problem statement
Activity | Immediate predecessors | Time (Weeks) |
A | 2 | |
B | A | 5 |
C | A | 3 |
D | B | 4 |
E | C | 3 |
F | C | 7 |
G | D,E | 2 |
H | F | 3 |
Duration | |||||||||||||||
Steps | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 |
Activities | A | C | B | D | G | ||||||||||
C | E | ||||||||||||||
C | F | H |
Part b)
Explain the following TWO (2) terms in lean operations:
a. Kanban –
Kanban is a visual system for work management as it moves through system processes i.e.
b. Toyota production system (TPS)
If you liked my answer , thumbs up pls.
Hello, could you help me solve this question, please? Thank you very much! Question: (a) A...
QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are shown follow. Time Immediate Activity (weeks) Predecessor 2 5 В 4 C 5 В 6 В.С D,E F What are the slack times of Activities D and E? 0 and 0, respectively 1 and 1, respectively 2 and 0, respectively 0 and 1, respectively 1 and 0, respectively shown follow. A firm is planning a project for the...
PLEASE ANSWER IN 30 MINUTES PM.53 Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations: Activity Duration (weeks) Immediate Predecessor(s) A 20 - B 12 - C 15 A D 5 B E 6 D F 14 A,E G 5 F H 3 C,G What is the duration of the project? weeks What is the latest start week for activity C? What is the slack time for...
Can someone please help me with this Operations Management
Question?
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) MO OWO 10ம் ONNON b. What is the critical path? O O O O A-C-D-E-G A-B-E-G A-B-D-F-G A-C-D-F-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
Question 13 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 B 3 с 2 D A,B 5 E CD F D 4 G E 2 1 Determine the duration of the project. a. 13 weeks b. 12 weeks OC. 11 weeks d. 10 weeks e. 9 weeks Question 14 Assume that activity F has the following times: Early start time (ES) =...
3. (20 points) A landscaping upgrade project consists of following activities. Times are given in weeks. Activity | Immediate Predecessor Activity Time A А ထင်ထ F B, DC D D 3 3 a. Draw the network diagram and find the ES, EF, LS, LF, and slack for each activity b. Construct an early-start-date Gantt chart for the project. C. As a project manager, where would you focus your attention, given your analysis?
Activity12345678910Activity time (weeks)2542758431Immediate predecessor-1122, 33455, 67, 8, 9Please build the GANTT chart for the given question above (note: you may use excel if that is easier for you)
can you help me wirh this question please
Question 7 1 pts 5- Draw the activity-on-node project network associated with the following activities for a construction project. How long should it take the team to complete this project? What are the critical path activities? Provide your answers in the blank fields below. Immediate Predecessor(s) Time (Days) Activity IA 3 B A 4 IC с A 6 D B 6 E B 4 IF c с 4 G D 6 H...
A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...
The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 3 2 B с D E F 4 A B B с DE E 1 3 G 2 Determine the amount of slack time for Activity E Ola. O weeks b. 1 week c. 2 weeks d. 3 weeks
Please help me find the critical path and the slack. I've been
struggling on this for awhile
Screen Shot 2020-04-20 at 3.45.19 PM Z o @ Q Search A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) <MOOW LUI b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Slack (weeks) Yes No Yes Yes | <mo...