Question

Given a list of activities for a small project as shown in the following table: Astivity Duration Earlyate Late Tota (days) Start | Finish ! Start | Finish Float 13 19 20 19 It is required to: . Complete the missing data in the table; and . Draw the resource profile based on early times in case of Resource -4D-3 units/day Draw the resource profile based on late times of Resource- 2D-1 units/day; and Draw best resource leveling profile of previous cases
0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Given a list of activities for a small project as shown in the following table: Astivity...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 13 The following table provides a list of activities in a project, along with their...

    Question 13 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 B 3 с 2 D A,B 5 E CD F D 4 G E 2 1 Determine the duration of the project. a. 13 weeks b. 12 weeks OC. 11 weeks d. 10 weeks e. 9 weeks Question 14 Assume that activity F has the following times: Early start time (ES) =...

  • A Question 11 The following table provides a list of activities in a project, along with...

    A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...

  • Question on resource leveling 1. Use the following data in order to make a manpower loading chart, a cash-flow char...

    Question on resource leveling 1. Use the following data in order to make a manpower loading chart, a cash-flow chart, and a progress S (banana curve) of practice problem #3 (show a loaded bar chart, with float, and a histogram for both costs and men). The banana curve should show both early start/finish and late start/finish costs. The cash and manpower charts are to show early start and finish information. It is not necessary to produce the late start/finish charts....

  • I request the answer for this question please; Their are similar questions but I need specifically...

    I request the answer for this question please; Their are similar questions but I need specifically the answer of the question I posted Thank you 4. Compute the early start, early finish, late start, and late finish dates and floats (total float and free float) for the activities of the project shown below. Identify the critical activities on the AON diagram. Draw an early bar chart for the project and show critical activities. TF= TF = TF= FS= -2 TF...

  • Management Information Systems Assume you have a project with 11 activities labeled A - K (below)....

    Management Information Systems Assume you have a project with 11 activities labeled A - K (below). (5 points) Activity Preceding Activities Duration (Days) Early Finish (Days) Late Finish (Days) Free Slack (Days) A -- 4                   B A 2                   C B 6                   D B 21                   E B 12                   F C, D 2                   G D, E 15                   H F, G 8...

  • The following table illustrates the activities of a small project Duration Days) Activity Depends orn 7 7 9 2 419 A...

    The following table illustrates the activities of a small project Duration Days) Activity Depends orn 7 7 9 2 419 A a. Calculate the mean Project duration; b. Write and Highlight the Critical Path; c. Find the probability to finish this project at 15 days; d. Find the probability to finish this project at 19 days; e. Find the project duration that satisfies probability equal to 8 %; f. Find the project duration that satisfies probability equal to 92 %.

  • The table below shows a number of tasks required for the successful completion of a project....

    The table below shows a number of tasks required for the successful completion of a project. Activity Days Immediate Predecessor(s) A 4 B 2 A C 5 A D 7 A E 2 B F 5 B,C G 6 D,E,F Draw the network diagram for this project highlighting Early Start, Early Finish, Late Start and Late Finish and slack. Please show your answer by using the format shown below.                                                                                                                                  Table template: Activity A B C D E F G Early...

  • Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity...

    Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity on Node (AON) diagram to reflect the flow of these activities. Calculate the Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity. Calculate the slack for each activity. Identify all activities on the Critical Path. Use the data to calculate the probability the project will finish in 20 weeks (Hint: z-score). Activity A 8 с D E...

  • Please help with 1-2!! Network diagram: Exercise # 4 Based on Excercise 3 from Module 6: 1. Perform a Forward...

    Please help with 1-2!! Network diagram: Exercise # 4 Based on Excercise 3 from Module 6: 1. Perform a Forward Pass and a Backward Pass of the network diagram above 2. Which Activities has the same Early Finish as they have Late Finish? Note: The project starts on Day "O" Early Start Duration Early Finsh Task Name Late Start Late Finish Slack A 2. 2 6 4 H Exercise # 4 Based on Excercise 3 from Module 6: 1. Perform...

  • 9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activit...

    9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activity. (20 points) Predecessor Duration (Days) Activity A, B C, D F,G 9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activity. (20...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT