Review each of the following scenarios and
identify the risk events, the probability of those risks, and the
impact of the risk events. Some scenarios may have more risks than
others.
Scenario Two
A construction company has been awarded the contract to build a pipeline in Alaska. The project timeline is of the highest priority because work can only be completed during summer months due to adverse weather conditions. One of the suppliers of a key component has longer lead time than is required to complete the pipeline, but may be able to deliver if the construction company will pay fees to expedite. There are other suppliers, but these suppliers are not on the construction company’s approved supplier list and it would take time to get them approved. There is a huge penalty in the contract if the project is not completed on time.
Risk event |
Probability of risk event (1=high; 3=medium; 5=low) |
Impact of risk event (1=high; 3=medium; 5=low) |
Various kinds of risks that are associated with the construction projects in Alaska to build a pipeline are as follows.
Review each of the following scenarios and identify the risk events, the probability of those risks,...
Qualitative risks are typically categorized by a group of experts to determine the probability and the impact to project objectives. In the example below, consider the next steps that should be taken as project manager to assemble a group of experts to participate. Who would you select and why? Project Management Body of Knowledge (PMBOK) defines risks as “an uncertain event or condition, that if it occurs, has a positive or negative effect on one or more project objectives” (ProjectRiskCoach,...
Dear Sir/Madam, could you answer all the question below. I appreciate if u can answer all. Thank You :) A (Bad?) Day in the Life of a Project Manager Frank Mills is a Site Agent for McMurray Concrete Ltd which specialises in building concrete structures on industrial sites. His present site is a large chemical plant, Agrochem Ltd that manufactures farm fertilisers. The project he is currently working on is part of a large contract being managed by Design Solutions...
Which of the six risks should be considered a significant risk? Explain why they represent a significant risk. For each risk that you identified as a significant risk, describe how you might address the risk to give it special audit consideration. For example, a valuation risk might be addressed by engaging a valuation specialist. Begin by determining which of the six risks should be considered a significant risk. Then, for each risk that has been identified as a significant risk,...
Q: Complete the following "Reason column" for your software engineering risk analysis project. Please Note that there is a sample for filling the reason column please see it. Risk Probability Effects Reason Organizational financial problems force reductions in the project budget (7). Low Catastrophic It is impossible to recruit staff with the skills required for the project (3). High Catastrophic Key staff are ill at critical times in the project (4). Moderate Serious Faults in reusable software components have to...
Orleans Construction Company Case (adapted from Meredith and Mantel) The Orleans Construction Company, a small construction company in North Carolina, has been awarded a contract for the construction of a new 25,000 soccer stadium at Greensboro. The City is hoping to use this facility to attract a new soccer franchise. The construction cannot start earlier than March 2, 2020 (because of the availability of bond funds) and must be completed within 1 year (52 weeks). A penalty clause of $13,000...
You roll a six-sided die. Find the probability of each of the following scenarios. (a) Rolling a 6 or a number greater than 3 (b) Rolling a number less than 4 or an even number (c) Rolling a 4 or an odd number (a) P(6 or number> 3)- (Round to three decimal places as needed) (b) P/1 or 2 or 3 or 4 or 6)-( Round to three decimal places as needed.) (c) P(4 or 1 or 3 or 5)...
1) Discuss the company's top risks? 2) Discuss whether the company treats risk reactively or proactively? 3) Do you observe a lack of understanding of potential exposures? 4) Does the company focus on internal risks or external risks? 5) Do you think the company is well prepared to respond to potential risks? Orange County he t die Following the debocie Orange County o dmorych of control procedures and financial gove nonce and d e setof o n policies December 1994...
Assess whether from a utilitarian, rights, justice and caring perspective, Unocal did the right thing in deciding to invest in the pipeline and then in conducting the project as it did. In your view, and using your utilitarian, rights, justice and caring assessments, did Unocal do the right thing? CASE: Unocal in Burma Union Oil Company of California, or Unocal, was founded in 1890 to develop oil fields around Los Angeles and other parts of California. By 1990, Unocal had...
RADICO’S CHALLENGE The executive staff at Radico Corporation was quite pleased with the one-day training program they attended on the benefits of using agile and Scrum on some of their projects. Radico provided products and services to both public and private sector clients, almost all of it through competitive bidding. IT was not required for any of the products and services Radico provided. Agile and Scrum had proven to be successful on internal IT projects, but there were some concerns...
Use the answer sheet provided for the project to identify which (if any) of the events or sitautions described happened in each cases. Use our report template to create a report for the medical staff review committee. Under conclusion discuss one process change that can be implemented to reduce risk exposure and provide at least two ways in which change can be managed smoothly when implementing the new process. Presume you are a data analyst in the hospital health information...