1. A construction company has total revenues of $650,000, total construction costs of $509,000, and general overhead costs of $65,000 for the year. Determine the profit and overhead mark-up for a company that wants to maintain a 8% gross profit margin.
Gross profit = 8% or 0.08
Profit and overhead markup = Gross profit / ( 1 - Gross profit)
= 0.08 / (1 - 0.08)
= 0.0870 or 8.70%
1. A construction company has total revenues of $650,000, total construction costs of $509,000, and general...
A construction company has total revenues of $250,000, total construction costs of $175,000, variable general overhead of $5,000, and fixed general overhead of $45,000 for the year. What are the contribution margin and the contribution margin ratio for the company?
Given that the company’s revenues are $3,698,945, the construction costs are $3,186,457, and the overhead costs are $422,562. a) Calculate the company’s profit from operations for the year and the percentage of the construction revenues that become profit. b) What are the contribution margin and the contribution margin ratio if $45,000 of the overhead is considered variable overhead?
Markup on Cost, Cost-Based Pricing Arthur Quillen Construction Company is a general contractor that specializes in custom residential housing. Each job requires a bid that includes Quillen’s direct costs and subcontractor costs as well as an amount referred to as “overhead and profit.” Quillen’s bidding policy is to estimate the costs of direct materials, direct labor, and subcontractors’ costs. These are totaled, and a markup is applied to cover overhead and profit. In the coming year, the company believes it...
countitled Construction Overhead The mated direct labor cost for the year, it estimated $1,150,000 and total direct labor costs of $5.750.000 T during Augusti .. Purchased materiale on account, $400.000 Requisitioned direct material and directe the materiale regioned head. The company applies mated construction 0.000. The following events direct labor in construction. Recorded Direct Labor 3. Hou 402 House 403 House 404 House 405 Direct Materials $50,000 62,000 61,000 86,000 $ 44,000 32.000 S8,000 57.000 c. The company incurred total...
1.) Both total revenues (TR) and total costs (TC) are likely to be affected by changes in the output. True or False 2.) Profit is the unit contribution margin multiplied by the number of units minus the fixed component of the total costs (TC). True or False 3.) The average selling price is $.60 per unit, the average variable cost is $.36 per unit, and the total fixed costs are $1,500. If operating profits of $900 are desired, what is...
Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It is estimated that the complex will take 3 years to construct. Additional information follows. Estimated cost of complex Contract price AA 600,000 900,000 The following data pertain to the construction period. 2019 610,000 $ 6100 A 2017 270,000 330,000 270,000 240,000 2018 450,000 150,000 550,000 500,000 Costs to date Estimated costs to complete Progress billings to date Cash collected to date $...
Sandhill Construction Company has entered into a non-cancellable contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $650,000 and will take three years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2022 $660,000 Costs to date Estimated costs to complete Progress billings to date (non-refundable) Cash collected to date 2020 $292,500 357,500 292,500 262,500 2021 $487,500 162,500...
Determine the profit and overhead markup for a company who wants to maintain a 13.2% gross profit margin.
Bramble Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $272,700 $466,620 $618,000 Estimated costs to complete 333,300 139,380 –0– Progress billings to date 273,000 546,000 902,000 Cash collected to date...
Cheyenne Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $895,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $268,200 $482,760 $605,000 Estimated costs to complete 327,800 113,240 –0– Progress billings to date 267,000 552,000 895,000 Cash collected to date...