Question

If a work cell had the following data, what is their OEE or overall equipment effectiveness?...

If a work cell had the following data, what is their OEE or overall equipment effectiveness?

2 – 8 hour shifts

30 minute break per shift

2 hours planned downtime per shift

1 - 30 minute meeting per shift

Cycle time = .025 hours/unit

350 units were produced

325 were good parts

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The Overall Equipment Effectiveness is given by following formula:

OEE = Availability (A) x Performance (P) x Quality (Q)

1.

Availability = Run Time/Planned Production time

Run time = Planned Production time – Losses – Breaks

Planned Production time = Shift length – Breaks = (2 shifts x 8 hours per shift) – (2 shifts x 30 minutes breaks/shift) = 16 hours – 1 hour = 15 hours

Planned Production time (in minutes) = 15 hours per day

Run time = 960 mins – (time loss due to (downtime + meeting))

2 hours planned downtime per shift

1 - 30 minute meeting per shift

Run time = 15 – (2*2 + 2*0.5) = 10 hours

Availability = Run Time/Planned Production time = 10/15 = 0.6667

2.

Performance = (Ideal cycle time x total count)/Run time

Cycle time = 0.025 hours/unit

Total count = 350 units were produced

Performance = (0.025 hrs/unit x 350)/10 = 8.75/10 = 0.875

3.

Quality = Good Count/Total Count

Good count of parts = 325 units

Total count = 350 units

Quality = 325/350 = 0.9285

OEE = A x P x Q = 0.6667 x 0.875 x 0.9285 = 0.5416

OEE = 54.6%

Add a comment
Answer #2

To calculate the Overall Equipment Effectiveness (OEE), we'll use the formula:

=××

where:

  • Availability = (Total Operating Time - Planned Downtime) / Total Operating Time

  • Performance = (Total Count \times Ideal Cycle Time) / Total Operating Time

  • Quality = Good Count / Total Count

Given the following data:

  • Total Operating Time = 2 shifts × 8 hours/shift = 16 hours

  • Planned Downtime = 2 hours/shift × 2 shifts = 4 hours

  • Total Count = 350 units

  • Good Count = 325 units

  • Cycle Time = 0.025 hours/unit

Now, let's calculate the components of OEE:

  1. Availability: Availability = (Total Operating Time - Planned Downtime) / Total Operating Time Availability = (16 hours - 4 hours) / 16 hours Availability = 12 hours / 16 hours Availability ≈ 0.75

  2. Performance: Performance = (Total Count × Ideal Cycle Time) / Total Operating Time Performance = (350 units × 0.025 hours/unit) / 16 hours Performance = 8.75 hours / 16 hours Performance ≈ 0.547

  3. Quality: Quality = Good Count / Total Count Quality = 325 units / 350 units Quality ≈ 0.929

Now, let's calculate the OEE:

OEE = Availability × Performance × Quality OEE ≈ 0.75 × 0.547 × 0.929 OEE ≈ 0.37

The Overall Equipment Effectiveness (OEE) for the work cell is approximately 0.37, which represents 37%.

answered by: Hydra Master
Add a comment
Answer #3

To calculate the Overall Equipment Effectiveness (OEE), we need to consider three main factors: Availability, Performance, and Quality. OEE is the product of these three factors and provides a measure of how effectively the equipment is being utilized.

  1. Availability: Availability measures the percentage of time the equipment is available for production. It is calculated as the ratio of operating time to planned production time.

Operating Time = Total shift time - Breaks - Planned downtime - Meeting time Operating Time = 2 shifts * (8 hours/shift) - 2 * (0.5 hours) - 2 * (2 hours) - 2 * (0.5 hours) Operating Time = 16 hours - 1 hour - 4 hours - 1 hour Operating Time = 10 hours

Planned Production Time = Total shift time - Breaks Planned Production Time = 2 shifts * (8 hours/shift) - 2 * (0.5 hours) Planned Production Time = 16 hours - 1 hour Planned Production Time = 15 hours

Availability = (Operating Time / Planned Production Time) * 100 Availability = (10 hours / 15 hours) * 100 Availability = 66.67%

  1. Performance: Performance measures the actual production rate compared to the ideal production rate. It takes into account any speed losses or inefficiencies during production.

Ideal Production Rate = 1 / Cycle time Ideal Production Rate = 1 / 0.025 hours/unit Ideal Production Rate = 40 units/hour

Actual Production Rate = Total units produced / Operating Time Actual Production Rate = 350 units / 10 hours Actual Production Rate = 35 units/hour

Performance = (Actual Production Rate / Ideal Production Rate) * 100 Performance = (35 units/hour / 40 units/hour) * 100 Performance = 87.5%

  1. Quality: Quality measures the percentage of good parts produced compared to the total parts produced.

Quality = (Good Parts / Total Parts Produced) * 100 Quality = (325 units / 350 units) * 100 Quality = 92.86%

Now, we can calculate the Overall Equipment Effectiveness (OEE):

OEE = Availability * Performance * Quality OEE = 0.6667 * 0.875 * 0.9286 OEE ≈ 0.5614 or 56.14%

The Overall Equipment Effectiveness (OEE) for the work cell is approximately 56.14%. This indicates that the equipment is operating at about 56.14% of its full potential efficiency, considering factors such as availability, performance, and quality.


answered by: Mayre Yıldırım
Add a comment
Know the answer?
Add Answer to:
If a work cell had the following data, what is their OEE or overall equipment effectiveness?...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT