If a work cell had the following data, what is their OEE or overall equipment effectiveness?
2 – 8 hour shifts
30 minute break per shift
2 hours planned downtime per shift
1 - 30 minute meeting per shift
Cycle time = .025 hours/unit
350 units were produced
325 were good parts
The Overall Equipment Effectiveness is given by following formula:
OEE = Availability (A) x Performance (P) x Quality (Q)
1.
Availability = Run Time/Planned Production time
Run time = Planned Production time – Losses – Breaks
Planned Production time = Shift length – Breaks = (2 shifts x 8 hours per shift) – (2 shifts x 30 minutes breaks/shift) = 16 hours – 1 hour = 15 hours
Planned Production time (in minutes) = 15 hours per day
Run time = 960 mins – (time loss due to (downtime + meeting))
2 hours planned downtime per shift
1 - 30 minute meeting per shift
Run time = 15 – (2*2 + 2*0.5) = 10 hours
Availability = Run Time/Planned Production time = 10/15 = 0.6667
2.
Performance = (Ideal cycle time x total count)/Run time
Cycle time = 0.025 hours/unit
Total count = 350 units were produced
Performance = (0.025 hrs/unit x 350)/10 = 8.75/10 = 0.875
3.
Quality = Good Count/Total Count
Good count of parts = 325 units
Total count = 350 units
Quality = 325/350 = 0.9285
OEE = A x P x Q = 0.6667 x 0.875 x 0.9285 = 0.5416
OEE = 54.6%
To calculate the Overall Equipment Effectiveness (OEE), we'll use the formula:
where:
Availability = (Total Operating Time - Planned Downtime) / Total Operating Time
Performance = (Total Count \times Ideal Cycle Time) / Total Operating Time
Quality = Good Count / Total Count
Given the following data:
Total Operating Time = 2 shifts × 8 hours/shift = 16 hours
Planned Downtime = 2 hours/shift × 2 shifts = 4 hours
Total Count = 350 units
Good Count = 325 units
Cycle Time = 0.025 hours/unit
Now, let's calculate the components of OEE:
Availability: Availability = (Total Operating Time - Planned Downtime) / Total Operating Time Availability = (16 hours - 4 hours) / 16 hours Availability = 12 hours / 16 hours Availability ≈ 0.75
Performance: Performance = (Total Count × Ideal Cycle Time) / Total Operating Time Performance = (350 units × 0.025 hours/unit) / 16 hours Performance = 8.75 hours / 16 hours Performance ≈ 0.547
Quality: Quality = Good Count / Total Count Quality = 325 units / 350 units Quality ≈ 0.929
Now, let's calculate the OEE:
OEE = Availability × Performance × Quality OEE ≈ 0.75 × 0.547 × 0.929 OEE ≈ 0.37
The Overall Equipment Effectiveness (OEE) for the work cell is approximately 0.37, which represents 37%.
To calculate the Overall Equipment Effectiveness (OEE), we need to consider three main factors: Availability, Performance, and Quality. OEE is the product of these three factors and provides a measure of how effectively the equipment is being utilized.
Availability: Availability measures the percentage of time the equipment is available for production. It is calculated as the ratio of operating time to planned production time.
Operating Time = Total shift time - Breaks - Planned downtime - Meeting time Operating Time = 2 shifts * (8 hours/shift) - 2 * (0.5 hours) - 2 * (2 hours) - 2 * (0.5 hours) Operating Time = 16 hours - 1 hour - 4 hours - 1 hour Operating Time = 10 hours
Planned Production Time = Total shift time - Breaks Planned Production Time = 2 shifts * (8 hours/shift) - 2 * (0.5 hours) Planned Production Time = 16 hours - 1 hour Planned Production Time = 15 hours
Availability = (Operating Time / Planned Production Time) * 100 Availability = (10 hours / 15 hours) * 100 Availability = 66.67%
Performance: Performance measures the actual production rate compared to the ideal production rate. It takes into account any speed losses or inefficiencies during production.
Ideal Production Rate = 1 / Cycle time Ideal Production Rate = 1 / 0.025 hours/unit Ideal Production Rate = 40 units/hour
Actual Production Rate = Total units produced / Operating Time Actual Production Rate = 350 units / 10 hours Actual Production Rate = 35 units/hour
Performance = (Actual Production Rate / Ideal Production Rate) * 100 Performance = (35 units/hour / 40 units/hour) * 100 Performance = 87.5%
Quality: Quality measures the percentage of good parts produced compared to the total parts produced.
Quality = (Good Parts / Total Parts Produced) * 100 Quality = (325 units / 350 units) * 100 Quality = 92.86%
Now, we can calculate the Overall Equipment Effectiveness (OEE):
OEE = Availability * Performance * Quality OEE = 0.6667 * 0.875 * 0.9286 OEE ≈ 0.5614 or 56.14%
The Overall Equipment Effectiveness (OEE) for the work cell is approximately 56.14%. This indicates that the equipment is operating at about 56.14% of its full potential efficiency, considering factors such as availability, performance, and quality.
If a work cell had the following data, what is their OEE or overall equipment effectiveness?...
Overall Equipment Effectiveness Exercise for Case Study E Directions: Using your Overall Equipment Effectiveness Calculation Worksheet and th information provided below, determine the Overall Equipment a typical Assembly plant for Availability Assumptions: At a typical plant, the constraint in the Widget production process is the machining line. The following information applies to the line for the week of June 5 through June 11. The line was schedulėd to run two &-bour shifts Monday through Friday, and one 9-hour shift on...
The production facility run on one 7.5 hour shift. There is a 15 minute meeting planned at the beginning of the shift and 30 total minutes of setup time each day. 15 minutes of unscheduled equipment failure usually occurs. 380 good parts and 20 defective parts were produced with a standard cycle time of 60 parts per hour. What is the Overall Equipment Effectiveness (OEE)? A) 93.51% B) 78.56% C) 85.17% D) 72.34%
Question 33 Which dominant production paradigm represents the Overall Equipment Effectiveness (OEE) metric? OEE= (Good Count x Ideal Cycle Time)/Planned Production Time Where: Good Count = Parts manufactured without defects Ideal Cycle Time = Theoretical fastest time possible to manufacture a part Planned Production Time = Total time scheduled for production a) Industry 4.0 b) Craftsmanship c) Mass production d) Lean manufacturing e) Industry 3.0 [1 mark] Question 34 Identify the defining factor for your answer in Question 33 and...
QUESTION 21 (10 points) ‐ Overall Equipment Effectiveness (OEE) QUESTION 21 (10 points) Overall Equipment Effectiveness (OEE) A copy machine is available 20 hours a day. On a typical day, the machine needs to process 360 jobs. Each job takes about 1.5 minutes on the machine, 0.5 minute of which is processing time and 1 minute is setup time (logging in, defining the job). About 30% of the jobs need to be reworked, in which the set-up time and the...
To determine efficiency metrics, engineers collected data for a full shift of production run on machine A. During this time: » Production was stopped for 20 minutes due to a machine failure, 10 minutes for a biın change, and 30 minutes for a quality concern requiring a tool repair . A total of 1200 parts were produced. Note that he ideal cycle time established by engineering or the equipment manufacturer is 4 parts /minute 6 parts were scrapped during the...
A pipe bending machine used to produce ship system components was operated as follows: The period of operation was 25 days @ 10 hrs per day. It produced 800 total pipe details, of which 40 were rejected by quality inspectors. The total setup time for the machine during the 25 days was 22 hours. The machine had 3 unplanned breakdown events 1.5 hours for a power failure 0.5 hours for computer network failure 2.2 hours for lubricant pump failure The...
OVERALL EQUIPMENT EFFICIENCY A CNC machine tool is used for single shift working, the machine tool is operated for 8 hours per shift for 5 days per week. The CNC machine fool produces terminal blocks at a planned production rate of 60 units per hour Using the Availability, Performance and Quality losses given in the table below, (all values are in minutes per week) Calculate the average Overall Equipment Efficiency (OEE) for the machine tool over the three week period...
just #3 Part I A full shift of production was scheduled to run on machine X. Production was stopped for 20 minutes due to a machine failure, 10 minutes for a bin change, 30 minutes for a quality concern requiring a tool repair. Assumptions: A) A day- 8 hours with 20 minutes break time B) A total of 1200 parts is processed per day and only 6 is rejected/scraped C)- The ideal cycle time established by engineering or the equipment...
A pipe bending machine used to produce ship system components was operated as follows: The period of operation was 25 days @ 10 hrs per day. It produced 800 total pipe details, of which 40 were rejected by quality inspectors. The total setup time for the machine during the 25 days was 22 hours. The machine had 3 unplanned breakdown events 1.5 hours for a power failure 0.5 hours for computer network failure 2.2 hours for lubricant pump failure The...
Help with question b. please! The manager at Ormonde Inc. collected the value stream mapping data from the plant's most problematic manufacturing cell that fabricates parts for washing machines. This data is shown in Table 1. Using this data, calculate the current state performance of the cell and answer the following questions. Click the icon to view Table 1. a. What is the cell's current inventory level? The cell's current inventory level is 2050 parts. (Enter your response as a...