Question

Problem 15-03 (Algorithmic) Consider the following time series data. Week 1 2 3 4 5 6...

Problem 15-03 (Algorithmic)

Consider the following time series data.

Week 1 2 3 4 5 6
Value 18 14 16 11 17 13

Using the naïve method (most recent value) as the forecast for the next week, compute the following measures of forecast accuracy:

  1. Mean absolute error (MAE)
  2. Mean squared error (MSE)
  3. Mean absolute percentage error (MAPE)

Round your answers to two decimal places.

MAE =

MSE =

MAPE =

Using the average of all the historical data as a forecast for the next period, compute the same three values. Round your answers to two decimal places.

MAE =

MSE =

MAPE =

Which method appears to provide the more accurate forecasts for the historical data?

Explain.

The input in the box below will not be graded, but may be reviewed and considered by your instructor.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

As per Chegg's guidelines, we are required to do only the first full part of a question so do not downvote for the same reason.

Add a comment
Know the answer?
Add Answer to:
Problem 15-03 (Algorithmic) Consider the following time series data. Week 1 2 3 4 5 6...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Please help Consider the following time series data. 3 4 5 6 Week 12 18 14...

    Please help Consider the following time series data. 3 4 5 6 Week 12 18 14 Value 17 1018 15 Using the average of all the historical data as a forecast for the next period, compute the following measures of forecast accuracy. (Round your answers to two decimal places.) (a) mean absolute error MAE - (b) mean squared error MSE - (c) mean absolute percentage error MAPE 96 (d) What is the forecast for week 7?

  • Problem 15-01 (Algorithmic) Consider the following time series data. Week 1 2 3 4 5 6...

    Problem 15-01 (Algorithmic) Consider the following time series data. Week 1 2 3 4 5 6 Value 18 14 15 11 19 14 Using the naïve method (most recent value) as the forecast for the next week, compute the following measures of forecast accuracy. Mean absolute error. Round your answer to one decimal place. Mean squared error. Round your answer to one decimal place. Mean absolute percentage error. Round your answer to two decimal places. What is the forecast for...

  • PLEASE ONLY ANSWER IF YOU CAN DO WHAT IS BLANK, I DON'T NEED HELP WITH WHAT...

    PLEASE ONLY ANSWER IF YOU CAN DO WHAT IS BLANK, I DON'T NEED HELP WITH WHAT IS FILLED OUT ALREADY. THANK YOU! Problem 15-03 (Algorithmic) Consider the following time series data. Week 1 2 3 4 5 6 Value 1914 16 10 17 15 Using the naive method (most recent value) as the forecast for the next week, compute the following measures of forecast accuracy: a. Mean absolute error (MAE) b. Mean squared error (MSE) c. Mean absolute percentage error...

  • Problem 15-01 (Algorithmic) Consider the following time series data. Week 1 2 3 4 6 Value...

    Problem 15-01 (Algorithmic) Consider the following time series data. Week 1 2 3 4 6 Value 20 14 16 10 18 14 Using the naiïve method (most recent value) as the forecast for the next week, compute the following measures of forecast accuracy a. Mean absolute error. Round your answer to one decimal place. b. Mean squared error. Round your answer to one decimal place. c. Mean absolute percent error. Round you answer to two decimal places. d. What is...

  • Consider the following time series data. Week 1 2 3 4 5 6 Value 1914 16...

    Consider the following time series data. Week 1 2 3 4 5 6 Value 1914 16 10 19 13 Using the naïve method (most recent value) as the forecast for the next week, compute the following measures of forecast accuracy. a. Mean absolute error. Round your answer to one decimal place. b. Mean squared error. Round your answer to one decimal place. c. Mean absolute percentage error. Round your answer to two decimal places. d. What is the forecast for...

  • Consider the following time series data. Week 1 2 3 45 6 Value 19 12 15...

    Consider the following time series data. Week 1 2 3 45 6 Value 19 12 15 10 19 15 Using the naïve method (most recent value) as the forecast for the next week, compute the following measures of forecast accuracy. (a) Mean absolute error If required, round your answer to one decimal place. (b) Mean squared error If required, round your answer to one decimal place. (c) Mean absolute percentage error If required, round your intermediate calculations and final answer...

  • Problem 8-1 Consider the following time series data. Week Value 1 18 2 12 3 16...

    Problem 8-1 Consider the following time series data. Week Value 1 18 2 12 3 16 4 5 6 11 1914 Using the naïve method (most recent value) as the forecast for the next week, compute the following measures of forecast accuracy. (a) Mean absolute error If required, round your answer to one decimal place. (b) Mean squared error If required, round your answer to one decimal place. (c) Mean absolute percentage error If required, round your intermediate calculations and...

  • Consider the following time series data. Week 1 2 3 45 6 Value 20 12 15...

    Consider the following time series data. Week 1 2 3 45 6 Value 20 12 15 11 18 13 Using the naive method (most recent value) as the forecast for the next week, compute the following measures of forecast accuracy. (a) Mean absolute error If required, round your answer to one decimal place. (b) Mean squared error If required, round your answer to one decimal place. (c) Mean absolute percentage error If required, round your intermediate calculations and final answer...

  • Consider the following time series data. Month Value 1 21 2 3 4 14 2014 5...

    Consider the following time series data. Month Value 1 21 2 3 4 14 2014 5 18 6 21 7 15 Round your answers to two decimal places. a. Compute MSE using the most recent value as the forecast for the next period. Mean squared error is What is the forecast for month 8? b. Compute MSE using the average of all data available as the forecast for the next period Mean squared error is What is the forecast for...

  • Consider the following time series data. Week 1 2 3 4 5 6 Value 17 13...

    Consider the following time series data. Week 1 2 3 4 5 6 Value 17 13 15 11 15 13 (a) Choose the correct time series plot. (i) (ii) (iii) (iv) - Select your answer -Graph (i)Graph (ii)Graph (iii)Graph (iv)Item 1 What type of pattern exists in the data? - Select your answer -Horizontal PatternTrend PatternItem 2 (b) Develop a three-week moving average for this time series. Compute MSE and a forecast for week 7. If required, round your answers...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT