Question

One path on a project has 3 tasks, A, B, and C. The expected times for...

One path on a project has 3 tasks, A, B, and C. The expected times for these tasks are 31, 34, and 20 respectively. Their standard deviations are 3, 4 and 2 respectively. The expected time for this path is                             [ Select ]                       ["65", "95", "75", "85"]       and standard deviation of this path is                             [ Select ]                       ["9", "9.7", "5.4", "29"]         .

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The expected time for the path = Sum of each Activity = ( 31 + 34 + 20) = 85

Hence, the correct option is 85.

Stabdard deviation = Sum of all standard deviation = 3 + 4 + 2 = 9.

Hence, the correct option is 9.

Do give a positive rating if you think this answer helped

Add a comment
Know the answer?
Add Answer to:
One path on a project has 3 tasks, A, B, and C. The expected times for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Tasks A, B, C and D are in the critical path of a project, all the...

    Tasks A, B, C and D are in the critical path of a project, all the tasks are estimated To require similar effort of 5 days each and cost $ 5,000 per task What is the Question 42 5 A 10 B 15 C 20 11 16 earned value (EV)? $5,000 $5,000 $5,000 $5,000 $ 5,000 Choice 1 complete: Task C is 50% complete At the end of day 11, Task A and Task B are and $13,000 has already...

  • For the following project with times to complete activities in weeks: ActivityDepend on a m b...

    For the following project with times to complete activities in weeks: ActivityDepend on a m b 1 3 6 2 3 6 3 79 2 23 34 5 B,C (a) Calculate the expected time and variance for each activity. Draw the project network (AOA). Determine the critical path, expected completion time and variance. (b) Determine the probability of finishing the project in 14 weeks or less. (c) You want to tell the client you are 95% sure the project will...

  • 4. A project has the following tasks and duration estimates given. These three tasks are done...

    4. A project has the following tasks and duration estimates given. These three tasks are done in succession on a project. Task Optimistic Estimate Most Likely Estimate Pessimistic Estimate Alpha 30 days 40 days 50 days Beta 20 days 25 days 28 days Charlie 4 days 10 days 12 days Delta 25 days 30 days 50 days a. What is the expected duration for the project? (3 points) b. What is the variance for the project? (3 points) . c....

  • 5. A project has critical path activities A, B, and C. A is the predecessor of B. B is the predec...

    5. A project has critical path activities A, B, and C. A is the predecessor of B. B is the predecessor of C. The duration estimate for activity A, B and C is shown in the following table. Fill the table with mean duration, standard deviation, and variance for activities and the whole project (critical path). Determine what is the probability of completing this project within 80 days? (10 points) Activity Optimistic Pessimistic Most likely Mean Standard Variance deviation duration...

  • The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning...

    The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning Company are given in the following table. Assume that the activity times are independent. Activity Immediate Predecessor a (time weeks) m (time weeks) b (time weeks) A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 Calculate the expected time (mean) and variance for each activity, then answer the following: a. What is the...

  • A7-3 (Algo) The expected times and variances... The expected times and variances for the project activities...

    A7-3 (Algo) The expected times and variances... The expected times and variances for the project activities are given below. Complete the table showing which activities are critical ID 1 Pilot production 2 Select channels of distrib 3Develop mktg. program 4Test market 5 Patent 6 Full production 7 Ad promotion 8Release Description Predecessor None None None Variance Critical? te 6 40 18 4 15 4 16 2,5,6,7 What is the probability of completing the project in 29 periods? (Do not round...

  • The customer has seen the Technology Refresh (Version B) project schedule and the expected project finish...

    The customer has seen the Technology Refresh (Version B) project schedule and the expected project finish time. However, the customer is concerned about the schedule risk of the project. Therefore, he wishes to know the following (i.e., determine the following): 1. The probability of finishing the project in 287 days. 2. The probability of finishing the project in 273 days. Hints: 1. If you wish to solve part 3 using the Z-value approach, refer to the Standard Normal Cumulative Probability...

  • What is the critical path and how long is the project expected to take?

    (a) Develop a network diagram for the project. What is the critical path and how long is the project expected to take? (6 m) (b) Which activities have a slack time of 8 weeks or more? (2 m) (c) Discuss five challenges a project manager faces in events such as this one. (12 m) (d) Why is a work breakdown structure useful in a project such as this? Take the 26 activities and break them into what you think should be level-2, level-3,...

  • tPacuity 9. (15 pts) What proportion of project completion times fall within two standard deviations of...

    tPacuity 9. (15 pts) What proportion of project completion times fall within two standard deviations of the mean? 10. (15 pts) What proportion of project completion times fall beyond one standard deviation of the mean? 11. (10 pts) 12% of arrivals occur in less than how many days. aschool system to complete major building repair projects is assumed The time it takes for to be normally distributed with a population mean value of MU 32 davs standard deviation value of...

  • Answer next 3 questions using following information: A project has three activities A, B, and C that must be carried out sequentially. The probability distributions of the times required to complete e...

    Answer next 3 questions using following information: A project has three activities A, B, and C that must be carried out sequentially. The probability distributions of the times required to complete each of the activities A, B, and C have uniform probability distribution in the following ranges:. Activity     Completion Time A                   1 to 5 B                   2 to 3 C                    3 to 6 Find the total project completion time and run 500 simulation trials in Excel. 1/ The “project completion time”...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT