Question

A7-3 (Algo) The expected times and variances... The expected times and variances for the project activities are given below. Complete the table showing which activities are critical ID 1 Pilot production 2 Select channels of distrib 3Develop mktg. program 4Test market 5 Patent 6 Full production 7 Ad promotion 8Release Description Predecessor None None None Variance Critical? te 6 40 18 4 15 4 16 2,5,6,7 What is the probability of completing the project in 29 periods? (Do not round intermediate calculations. Round the final answer to 3 decimal places, i.e., 0.750.) The probability of completing the project in 29 periods

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The precedence diagram of activities as follows :

                                                         1

2

3

4

5

7

6

                                                                                                            8

The possible paths and their corresponding expected durations as follows :

1-4-6-8 = 6 + 4 + 16 + 2 = 28

1-5-8 = 6 + 15 + 2 = 23

2-8 = 40 + 2 = 42

3-7-8 = 18 + 9 + 2 = 29

Since , 2-8 has the longest duration, it forms the critical path. The expected project duration ( which is same as expected duration of critical path ) will be 42 periods

Variance of the duration of critical path = Variance of activity 2 + Variance of activity 8 = 4 + 1 = 5

Therefore, Standard deviation of duration of activities on critical path = Square root ( Variance ) = Square root ( 5 ) = 2.236

Let z value corresponding to the probability of completing the project within 29 periods = Z1

Accordingly,

Expected project duration + Z1 x standard deviation of expected project duration = 29

Or, 40 + 2.236.Z1 = 29

Or, 2.236.Z1 = 29 – 40 = - 11

Or, Z1 = - 11/2.236 = - 4.919 ( - 4.9 rounded to 2 decimal places )

Corresponding value of probability for Z =- 4.9 as derived from standard normal distribution table is 0.0000005

PROBABILITY OF COMPLETING THE PROJECT IN 29 PERIODS = 0.0000009

Add a comment
Know the answer?
Add Answer to:
A7-3 (Algo) The expected times and variances... The expected times and variances for the project activities...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT