You work in the Finance Division of a medium size company that is considering a project to supply a customer with 50,000 widgets annually. You will need an initial investment of $4,000,000 in new equipment to get the project started and you estimate that this project will remain active for five years.
The Accounting Department estimated $1,000,000 in annual fixed costs and a variable costs of $200 per unit. Additionally, they told you they will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. Additionally, they are expecting a salvage value of $500,000 after dismantling costs.
The Marketing Department is confident that they will be able to negotiate a contract with the customer to pay $300 per unit. Finally, the Engineering Department informed that they will need an initial net working capital investment of $350,000.
You require a return of 15 percent and face a marginal tax rate of 40 percent on this project.
DOL = 1 + [FC × (1 − T) − T × D]/OCF
1) Suppose you’re confident about your own projections, but you’re not sure if your customer really needs the 50,000 widgets annually.
A) What is the sensitivity of the project OCF to changes in the quantity supplied?
B) What about the sensitivity of NPV to changes in quantity supplied?
C) Given the sensitivity number you calculated, is there some minimum level of output below which you wouldn’t want to operate? Why?
*Please No Handwritten explanations. Also, please provide explanation on how to asses and answer these types of questions.*
a) Calculation of Operating Profit and Operating Cash Flows:
Description |
Quantity |
Rate/Unit |
Value |
Sales |
50,000 Widgets |
$300 |
$15,000,000 |
Variable Cost |
50,000 Widgets |
$200 |
$10,000,000 |
Operating Margin |
$5,000,000 |
||
Fixed Cost |
$1,000,000 |
||
EBITDA |
$4,000,000 |
||
Depreciation ($4,000,000-$500,000 (Salvage Value)/5) |
$700,000 |
||
Earning before interest and Tax (EBIT) |
$3,300,000 |
||
Tax @ 40% |
$13,20,000 |
||
Net Profit |
$19,80,000 |
||
Capital Employed (Initial Investment- $4,000,000 + Working Capital Investment $350,000= $4,350,000) |
$4,350,000 |
||
Return on Investment (1,980,000/4,350,000) |
45.55% |
b) Degree of Operating Leverage
Sales-$15,000,000
Fixed Cost (Including Depreciation)-1,700,000
Variable Cost-10,000,000
Degree of Operating Leverage= (Sales-Variable Cost)/(Sales-Variable Cost-Fixed Cost)
=5,000,000/3,300,00
=1.515
c) Break Even Point=Fixed Cost/(Operating margin / unit)
=1,700,000/(5,000,000/50,000)
=17,000 Units
d) Units to be Sold to Earn ROI of 15%
Capital Employed: $4,350,000
After Tax Return ($4,350,000 * 15%) =$652,500
EBIT=$652,500 /(1-40% (tax rate)= 1,087,500
Add Fixed Cost = 1,087,500 + 1,700,000=27,87,500
No. of Units to be Sold= 2,787,500/100= 27875
1) The minimum no. of units required to be sold to achieve 15% ROI is 27875 based on the projections above.
2) Sensitivity of the Project OCF:
OCF=Net Profit + Depreciation
=19,80,000 + 700,000
= 26,80,000
Sensitivity of OCF to Change in Quantity Sold:
Let us consider the case of Units sold of 40,000
OCF= Operating Margin= $100 * 40,000= $ 4,000,000
Tax= (Operating Margin- Fixed Cost-Depreciation)*40%
=($4,000,000-1,000,000-7,00,000)*40%
=920,000
Net Profit=2,300,000-920,000=13,80,000
OCF=Net Profit + Depreciation=1,380,000+ 700,000=2,080,000
The sensitivity of Changes in quantity sold is
(26,80,000-20,80,000)/(50,000-40,000)
600,000/10,000=60
3) I would not want to operate sales below 27,875 units as the return below this level would be less than 15%
You work in the Finance Division of a medium size company that is considering a project...
You work in the Finance Division of a medium size company that is considering a project to supply a customer with 50,000 widgets annually. You will need an initial investment of $4,000,000 in new equipment to get the project started and you estimate that this project will remain active for five years. The Accounting Department estimated $1,000,000 in annual fixed costs and a variable costs of $200 per unit. Additionally, they told you they will depreciate the initial fixed asset...
Consider a project to supply Tacoma with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,600,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $600,000 and that variable costs should be $250 per ton. Further, the accounting department will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life and estimate a...
QUESTION 2 – SENSITIVITY ANALYSIS (25 POINTS) Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,600,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $600,000 and that variable costs should be $250 per ton. Further, the accounting department will depreciate the initial fixed asset investment straight-line to zero over...
Consider a project to supply Detroit with 28,000 tons of machine screws annually for automobile production. You will need an initial $5,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,250,000 and that variable costs should be $235 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $4,500,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,075,000 and that variable costs should be $200 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $4,600,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,100,000 and that variable costs should be $205 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $4,600,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,100,000 and that variable costs should be $205 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $6,000,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,450,000 and that variable costs should be $275 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 26,000 tons of machine screws annually for automobile production. You will need an initial $5,900,000 investment in threading equipment to get the project started, the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,425,000 and that variable costs should be $270 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. - Initial investment of $5,600,000 in threading equipment - the project will last for 6 years. -The accounting department estimates that annual fixed costs will be $600,000 -variable costs should be $250 per ton. - depreciate initial investment straight-line to 0 over 6 years with salvage value of $450,000 -contract at selling price of $340 per ton - the engineering department estimates you will...