Question

You work in the Finance Division of a medium size company that is considering a project...

You work in the Finance Division of a medium size company that is considering a project to supply a customer with 50,000 widgets annually. You will need an initial investment of $4,000,000 in new equipment to get the project started and you estimate that this project will remain active for five years.

The Accounting Department estimated $1,000,000 in annual fixed costs and a variable costs of $200 per unit. Additionally, they told you they will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. Additionally, they are expecting a salvage value of $500,000 after dismantling costs.

The Marketing Department is confident that they will be able to negotiate a contract with the customer to pay $300 per unit. Finally, the Engineering Department informed that they will need an initial net working capital investment of $350,000.

You require a return of 15 percent and face a marginal tax rate of 40 percent on this project.

DOL = 1 + [FC × (1 − T) − T × D]/OCF

1) Suppose you’re confident about your own projections, but you’re not sure if your customer really needs the 50,000 widgets annually.

A) What is the sensitivity of the project OCF to changes in the quantity supplied?

B) What about the sensitivity of NPV to changes in quantity supplied?

C) Given the sensitivity number you calculated, is there some minimum level of output below which you wouldn’t want to operate? Why?

*Please No Handwritten explanations. Also, please provide explanation on how to asses and answer these types of questions.*

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a) Calculation of Operating Profit and Operating Cash Flows:

Description

Quantity

Rate/Unit

Value

Sales

50,000 Widgets

$300

$15,000,000

Variable Cost

50,000 Widgets

$200

$10,000,000

Operating Margin

$5,000,000

Fixed Cost

$1,000,000

EBITDA

$4,000,000

Depreciation ($4,000,000-$500,000 (Salvage Value)/5)

$700,000

Earning before interest and Tax (EBIT)

$3,300,000

Tax @ 40%

$13,20,000

Net Profit

$19,80,000

Capital Employed (Initial Investment- $4,000,000 + Working Capital Investment $350,000= $4,350,000)

$4,350,000

Return on Investment (1,980,000/4,350,000)

45.55%

b) Degree of Operating Leverage

Sales-$15,000,000

Fixed Cost (Including Depreciation)-1,700,000

Variable Cost-10,000,000

Degree of Operating Leverage= (Sales-Variable Cost)/(Sales-Variable Cost-Fixed Cost)

=5,000,000/3,300,00

=1.515

c) Break Even Point=Fixed Cost/(Operating margin / unit)

=1,700,000/(5,000,000/50,000)

=17,000 Units

d) Units to be Sold to Earn ROI of 15%

Capital Employed: $4,350,000

After Tax Return ($4,350,000 * 15%) =$652,500

EBIT=$652,500 /(1-40% (tax rate)= 1,087,500

Add Fixed Cost = 1,087,500 + 1,700,000=27,87,500

No. of Units to be Sold= 2,787,500/100= 27875

1) The minimum no. of units required to be sold to achieve 15% ROI is 27875 based on the projections above.

2) Sensitivity of the Project OCF:

OCF=Net Profit + Depreciation

=19,80,000 + 700,000

= 26,80,000

Sensitivity of OCF to Change in Quantity Sold:

Let us consider the case of Units sold of 40,000

OCF= Operating Margin= $100 * 40,000= $ 4,000,000

Tax= (Operating Margin- Fixed Cost-Depreciation)*40%

=($4,000,000-1,000,000-7,00,000)*40%

=920,000

Net Profit=2,300,000-920,000=13,80,000

OCF=Net Profit + Depreciation=1,380,000+ 700,000=2,080,000

The sensitivity of Changes in quantity sold is

(26,80,000-20,80,000)/(50,000-40,000)

600,000/10,000=60

3) I would not want to operate sales below 27,875 units as the return below this level would be less than 15%

Add a comment
Know the answer?
Add Answer to:
You work in the Finance Division of a medium size company that is considering a project...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You work in the Finance Division of a medium size company that is considering a project...

    You work in the Finance Division of a medium size company that is considering a project to supply a customer with 50,000 widgets annually. You will need an initial investment of $4,000,000 in new equipment to get the project started and you estimate that this project will remain active for five years. The Accounting Department estimated $1,000,000 in annual fixed costs and a variable costs of $200 per unit. Additionally, they told you they will depreciate the initial fixed asset...

  • Consider a project to supply Tacoma with 40,000 tons of machine screws annually for automobile production....

    Consider a project to supply Tacoma with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,600,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $600,000 and that variable costs should be $250 per ton. Further, the accounting department will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life and estimate a...

  • QUESTION 2 – SENSITIVITY ANALYSIS (25 POINTS) Consider a project to supply Detroit with 40,000 tons...

    QUESTION 2 – SENSITIVITY ANALYSIS (25 POINTS) Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,600,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $600,000 and that variable costs should be $250 per ton. Further, the accounting department will depreciate the initial fixed asset investment straight-line to zero over...

  • Consider a project to supply Detroit with 28,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 28,000 tons of machine screws annually for automobile production. You will need an initial $5,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,250,000 and that variable costs should be $235 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $4,500,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,075,000 and that variable costs should be $200 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $4,600,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,100,000 and that variable costs should be $205 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $4,600,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,100,000 and that variable costs should be $205 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $6,000,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,450,000 and that variable costs should be $275 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 26,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 26,000 tons of machine screws annually for automobile production. You will need an initial $5,900,000 investment in threading equipment to get the project started, the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,425,000 and that variable costs should be $270 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. - Initial investment of $5,600,000 in threading equipment - the project will last for 6 years. -The accounting department estimates that annual fixed costs will be $600,000 -variable costs should be $250 per ton. - depreciate initial investment straight-line to 0 over 6 years with salvage value of $450,000 -contract at selling price of $340 per ton - the engineering department estimates you will...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT