Question

As part of a time study a particular job was analyzed. The study included 20 job...

As part of a time study a particular job was analyzed. The study included 20 job cycles and the following cumulative times and performance rating factors for each element were reported:

Element

Σt (min)

RF

1

12.22

1.10

2

9.55

1.05

3

14.5

0.90

4

11.21

0.95


Assuming an allowance factor of 15% the standard time for this job would be

Select one:

A. 2.712 minutes

B. 3.67 minutes

C. 4.35 minutes

D. 2.358 minutes

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Given that 20 job cycles were included, given t sum and RF with element grades. Asked that 15% of standard time would be:

ANSWER: Option A(2.712 minutes)

Add a comment
Know the answer?
Add Answer to:
As part of a time study a particular job was analyzed. The study included 20 job...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • What is a Therblig? Please specify and give exampie. 3) A time study was conducted on a job that ...

    What is a Therblig? Please specify and give exampie. 3) A time study was conducted on a job that contains four elements. The observed times and performance ratings for six cycles are shown in the following table. Note that all units are in minutes 15 Element Performance 1 13 4 6 rating 85% 100% 110% 95% 0.5 258* 0.89 1.14 0.46 1.52 0.8 0.44 1.5 0.84 1.1 0.43 1.47 0.48 1.49 0.85 0.45 1.51 0.83 1.081.21.161.26 4 * Machine broke...

  • A time study was conducted on a job that contains four elements. The observed times and...

    A time study was conducted on a job that contains four elements. The observed times and performance ratings for six cycles are shown in the following table. OBSERVATIONS (minutes per cycle) Element Performance Rating 1 2 3 4 5 6 1 80 % 0.51 0.56 0.46 0.46 0.46 0.46 2 75 1.51 1.51 1.46 1.46 1.46 1.51 3 120 0.86 0.86 0.76 0.81 0.86 0.81 4 105 1.11 1.16 1.11 1.16 1.16 1.21 a. Determine the average cycle time for...

  • A worker-machine operation was found to involve 40 minutes of machine time per cycle in the...

    A worker-machine operation was found to involve 40 minutes of machine time per cycle in the course of 40 cycles of stopwatch study The worker's time averaged 25 minutes per cycle, and the worker was given a rating of 115 percent machine rating is 100 percent). Midway through the study, the worker took a 10-minute rest break. Assuming an allowance factor of 15 percent of work time which is applied only to the worker element not the machine element), determine...

  • A worker-machine operation was found to involve 3.6 minutes of machine time per cycle in the...

    A worker-machine operation was found to involve 3.6 minutes of machine time per cycle in the course of 40 cycles of stopwatch study. The worker’s time averaged 2.1 minutes per cycle, and the worker was given a rating of 111 percent (machine rating is 100 percent). Midway through the study, the worker took a 10-minute rest break. Assuming an allowance factor of 11 percent of work time which is applied only to the worker element (not the machine element), determine...

  • (20 points) A direct time study is performed to obtain average time and performance rating values...

    (20 points) A direct time study is performed to obtain average time and performance rating values for the work elements in a certain repetitive task. The values are given in the table below. Elements a, b, and c are worker-controlled. Element d is a machine-controlled element and its time is the same each cycle (N.A.means performance rating is not applicable). Element c is performed while the machine is performing its cycle (element d). Element e is a worker- controlled irregular...

  • Time Study: Consider the recorded observations of 10 cycles of the cup packaging operation in seconds,...

    Time Study: Consider the recorded observations of 10 cycles of the cup packaging operation in seconds, shown in the figure below. Notice that the data reflects the continuous method in timing the elements. Determine the select times for each work element, the normal time for the cycle, and the standard time per package. Suppose we want a sample size that gives an average within + 2 percent of the true average 95 percent of the time. Did we make enough...

  • The owner of Bubba’s Barbeque is trying to determine a standard time for assembling each kind...

    The owner of Bubba’s Barbeque is trying to determine a standard time for assembling each kind of sandwiches he sells. During a time study for assembling Bubba’s Famous Pulled Pork Sandwiches you recorded the following data in seconds. Work Element Cycles Performance Rating 1 2 3 4 5 Prepare hoagie roll, move to prep area, open roll. 31 26 33 34 31 105% Get pork from smoker. 26 19 25 26 19 95% Shred pork for sandwich 149 148 145...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT