Question

Consider the following tasks, times, and predecessors for an assembly of set top cable converter boxes:...

Consider the following tasks, times, and predecessors for an assembly of set top cable converter boxes:

TASK ELEMENT TIME
(MINUTES)
ELEMENT
PREDECESSOR
A 3
B 3 A
C 2 B
D 2 B
E 1 C, D
F 1 A
G 3 F
H 3 G
I 1 E, H

Given a cycle time of six minutes, what is the efficiency of your layout? Use the longest task time as primary criterion with largest number of following tasks as secondary criterion.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The assignment of tasks in the stations as per the LPT rule is as follows:

Station Remaining time Eligibles Was Fit Assigned time Remaining time Idle time
I 6 A A 3 3 0
3 B, F B 3 0
0 C, D, F - - 0
II 6 C, D, F C 2 4 0
4 D, F D 2 2
2 E, F F 1 1
1 E, G E 1 0
0 G - - 0
III 6 G G 3 3 0
3 H H 3 0
0 I - - 0
IV 6 I I 1 5 5

Efficiency = Sum of task times / (No. of stations * Cycle time)

= 19 / (4*6)

= 0.7917 or 79.17%

Add a comment
Know the answer?
Add Answer to:
Consider the following tasks, times, and predecessors for an assembly of set top cable converter boxes:...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider the following tasks, times, and predecessors for an assembly of set top cable converter boxes:...

    Consider the following tasks, times, and predecessors for an assembly of set top cable converter boxes: TASK ELEMENT TIME (MINUTES) ELEMENT PREDECESSOR A 2 — B 1 A C 5 B D 4 B E 3 C, D F 3 A G 2 F H 1 G I 4 E, H Given a cycle time of seven minutes, what is the efficiency of your layout? Use the longest task time as primary criterion with largest number of following tasks as...

  • Consider the following tasks, times, and predecessors for an assembly of set-top cable converter boxes ELEMENT...

    Consider the following tasks, times, and predecessors for an assembly of set-top cable converter boxes ELEMENT TASK ELEMENT (MINUTES) PREDECESSOR TIME C, D E. H Given a cycle time of four minutes, develop an assembly line layout. Use the longest task time rule and the largest number of following tasks as a secondary criterion. What is the efficiency of your layout, assuming the 4-minute cycle time? (Round your answer to the nearest whole percent.) Efficiency

  • The desired daily output for an assembly line is 540 units. This assembly line will operate...

    The desired daily output for an assembly line is 540 units. This assembly line will operate 729 minutes per day. The following table contains information on this product's task times and precedence relationships: TASK TASK TIME (SECONDS) IMMEDIATE PREDECESSOR A 30 — B 28 A C 18 B D 69 B E 34 A F 36 E G 42 C, D H 24 F, G b. What is the workstation cycle time? Cycle time seconds c. Balance this line using...

  • 2. Show all the steps for the question to be worth any marks. The following table...

    2. Show all the steps for the question to be worth any marks. The following table presentss the tasks, durations, and immediate predecessors necessary to produce a particular Rroduct The required daily output is 320 units, and the working day is 8.0 hours on an assembly line. Immediate Predecessor Duration (in minutes) Activity A 0.9 B 0.7 C 0.8 Г E 0.4 В, с А, D E 0.5 0.4 G E 0.6 Н F, G 0.5 T 1.1 a. Draw...

  • Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been...

    Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been told that the firm needs to assemble 1400 agents per day. There are 420 minutes of productive time in each working day. The assembly line activities are given below: Task Time (seconds) Predecessor A 13 - B 4 A C 10 B D 10 - E 6 D F 12 E G 5 E H 6 F, G I 7 H J 5 H...

  • 3. A manager wants to assign tasks to workstations in order to achieve an hourly output...

    3. A manager wants to assign tasks to workstations in order to achieve an hourly output rate of four units. The depart- working time of 56 minutes per hour. ment uses a Assign the tasks shown in the following precedence network (times are on the nodes and are in minutes) to workstations using the following heuristic rules: (i) Assign the task with the largest positional weight. (ii) Tiebreaker: "Assign the task with the longest time." If a tie still exists,...

  • The following tasks are to be performed on an assembly line: TASK SECONDS TASKS THAT MUST...

    The following tasks are to be performed on an assembly line: TASK SECONDS TASKS THAT MUST PRECEDE A 18 — B 10 A C 25 B D 15 B E 14 C F 17 D G 12 E, F H 20 G The workday is 6.25 hours long. Demand for completed product is 750 per day. a. Find the cycle time required to meet the desired output rate. (Round your answer to 1 decimal place.) b. What is the theoretical...

  • EXAMPLE 8.2: Assembly-Line Balancing The Model J Wagon is to be assembled on a conveyor belt....

    EXAMPLE 8.2: Assembly-Line Balancing The Model J Wagon is to be assembled on a conveyor belt. Five hundred wagons are required per day. Production time per day is 420 minutes, and the assembly steps and times for the wagon are given in Exhibit 8.9A. Assignment: Find the balance that minimizes the number of workstations, subject to cycle time and precedence constraints SOLUTION I. Draw a precedence diagram. Exhibit 8.9B illustrates the sequential relationships identi- fied in Exhibit 8.9A. (The length...

  • You have been asked to balance a flow shop assembly operation to achieve an output rate...

    You have been asked to balance a flow shop assembly operation to achieve an output rate of 80 units over two eight-hour shifts - 16 hours. Task times and precedence relationships are shown in the table below: Task Predecessor Time (minutes) A -- 2 B A 4 C 7 D A, B 11 E C 9 F D 10 G E, F 7 H D, G 4 What is the cycle time in minutes? What is the theoretical number of...

  • For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A...

    For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A 45 - B 11 A C 9 B D 50 - E 26 D F 11 E G 12 C H 10 C I 9 F, G, H J 10 I 193 b. Determine the minimum and maximum cycle times in seconds for a desired output of 500 units in a seven-hour day. (Round your answers to 1 decimal place.)    The minimum cycle...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT