Question
Calculate payback periods. Please show calculations so I can duplicate it in excel.
7 Your division is considering two projects. Its wACC is 10%, and the projects, after-tax cash flows (in millions 8 of dollar
31 Project A Parback Period Time period: Cash flow: 0 34 Cumulative cash flow 35 36 Paybacka: 37 38 Project B Payback Period:
7 Your division is considering two projects. Its wACC is 10%, and the projects, after-tax cash flows (in millions 8 of dollars) would be as follows: Expected Cash Flows Project A Project B 10 Time (S30) S5 s10 S15 S20 (S30) S20 S10 S8 S6 12 13 14 15 16 17 18 a. Calculate the projects' NPVs, IRRs, MIRRs, regular paybacks, and discounted payback Use Excel's NPV function as explained in 11model.xlsx. Note that the range does not include the initial costs, which are added separately. 10% $7.74 S6.55 19 WACC = 20 NPVA- 21 NPVB 23 We find the Internal rath of return with Exel's IRR functions 24 IRRA 19.19% 22.52% 25 IRR 26 7 we find the Inodified internal rate of return with Excel's MIRR function using the 10% WACC 28 MIRR 29 MIRR 30 31 Project A Payback Period 32 16.50% 15.57% Time period:
31 Project A Parback Period Time period: Cash flow: 0 34 Cumulative cash flow 35 36 Paybacka: 37 38 Project B Payback Period: Time period: 0 39 40 41 Cumulative cash flow: 42 43 Paybackg: Cash flow: 45 Project A Discounted Payback Period 46 47 48 49 Disc. cum. cash flow 50 51 Discounted PaybackA Time period: 0 Cash flow: Disc. cash flow Project B Discounted Payback Period: 54 Time period: 0 Cash flow: Disc. cash flow: 57 Disc. cum. cash flow: 59 Discounted Paybackg 61-b.lrthetw。proyects areindependent,whichprotect(s) shouldbechosen?
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Payback Period = A +B/C

Where,

A = Last period with a negative cumulative cash flow

B = Absolute value of cumulative cash flow at the end of the period A

C = Total cash flow during the period after A

Computation of payback period for project A:

Period

Cash flow

‘Cumulative cash flow

0

($30)

($30)

1

$5

($25)

2

$10

($15)

3

$15

$0

4

$20

$20

Payback period for Project A = 2 + $ 15/$15 = 2 + 1 = 3 years

Computation of payback period for project B:

Period

Cash flow

Cumulative cash flow

0

($30)

($30)

1

$20

($10)

2

$10

$0

3

$8

$8

4

$6

$14

Payback period for Project B = 1 + $ 10/$10 = 1 + 1 = 2 years

---------------------------------------------------

Discounted Payback Period = A +B/C

Where,

A = Last period with a discounted negative cumulative cash flow

B = Absolute value of discounted cumulative cash flow at the end of the period A

C = Total discounted cash flow during the period after A

Computation of discounted payback period for Project A:

Period

Cash flow(CA)

Computation of PV Factor

PV Factor @ 10 % (F)

Discounted cash Flow(CA x F)

Discounted ‘Cumulative cash flow

0

($30)

1/(1+0.1)^0

1

($30)

($30)

1

$5

1/(1+0.1)^1

0.909090909090909

$4.55

($25.45)

2

$10

1/(1+0.1)^2

0.826446280991735

$8.26

($17.19)

3

$15

1/(1+0.1)^3

0.751314800901578

$11.27

($5.92)

4

$20

1/(1+0.1)^4

0.683013455365071

$13.66

$7.74

Discounted Payback period for Project A = 3 + $ 5.92/$ 13.66 = 3 + 0.433382 = 3.433382 or 3.43 years

Computation of discounted payback period for Project B:

Period

Cash flow (CB)

Computation of PV Factor

PV Factor @ 10 % (F)

Discounted cash Flow (CB x F)

Discounted ‘Cumulative cash flow

0

($30)

1/(1+0.1)^0

1

($30)

($30)

1

$20

1/(1+0.1)^1

0.909090909090909

$18.18

($11.82)

2

$10

1/(1+0.1)^2

0.826446280991735

$8.26

($3.55)

3

$8

1/(1+0.1)^3

0.751314800901578

$6.01

$2.46

4

$6

1/(1+0.1)^4

0.683013455365071

$4.10

$6.55

Discounted Payback period for Project B = 2 + $ 3.55/$ 6.01 = 2 + 0.590682 = 2.590682 or 2.59 years

---------------------------------------------------------------------------------

PV factor for period n = 1/ (1+r) n

Where r is rate of interest and n is the number of period

Multiply PV factor with the cash flow of respective year to get discounted cash flow. Discounted Cumulative cash flow in year 0 is the discounted cash flow or initial layout of the project. Add the discounted cash flow of year 1 with discounted cash flow year 0 to get discounted cumulative cash flow in year 1. With this discounted cumulative cash flow of year 1, add discounted cash flow of year 2 and get the discounted cumulative cash flow of year 2 and so on.

Project A Discounted Payback Period:                                          

If excel sheet is like below table, insert formulas as:

A

B

C

D

E

F

1

Time period

0

1

2

3

4

2

Cash Flow

($30)

$5

$10

$15

$20

3

Disc. Cash Flow

=B2*(1/(1.1)^0)

=C2*(1/(1.1)^1)

=D2*(1/(1.1)^2)

=E2*(1/(1.1)^3)

=F2*(1/(1.1)^4)

4

Disc. Cum. Cash Flow

=B3

=B4+C3

=C4+D3

=D4+E3

=E4+F3

5

6

Discounted payback period A

=E1 + (-E4/F3)

This will display as:

A

B

C

D

E

F

1

Time period

0

1

2

3

4

2

Cash Flow

($30)

$5

$10

$15

$20

3

Disc. Cash Flow

-30

$4.55

$8.26

$11.27

$13.66

4

Disc. Cum. Cash Flow

-30

$(25.45)

$(17.19)

$(5.92)

$7.74

5

6

Discounted payback period A

                            3.43

Add a comment
Know the answer?
Add Answer to:
Calculate payback periods. Please show calculations so I can duplicate it in excel. 7 Your division is considering two projects. Its wACC is 10%, and the projects, after-tax cash flows (in millio...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Case Study 3--Capital Budgeting (Comprehensive Spreadsheet Problem 11-23, page 408) Your division is considering two projects....

    Case Study 3--Capital Budgeting (Comprehensive Spreadsheet Problem 11-23, page 408) Your division is considering two projects. Its WACC is 10%, and the projects' after-tax cash flows (in millions of dollars) would be as follows: Expected Cash Flows Time Project A Project B 0 ($30) ($30) 1 $5 $20 2 $10 $10 3 $15 $8 4 $20 $6 a.   Calculate the projects' NPVs, IRRs, MIRRs, regular paybacks, and discounted paybacks. WACC = 10% Use Excel's NPV function as explained in NPVA...

  • Problem 10-21 Payback, NPV, and MIRR Your division is considering two investment projects, each of which...

    Problem 10-21 Payback, NPV, and MIRR Your division is considering two investment projects, each of which requires an up-front expenditure of $27 million. You estimate that the cost of capital is 8% and that the investments will produce the following after-tax cash flows (in millions of dollars): Year Project A Project B 1 5 20 2 10 10 3 15 8 4 20 6 What is the regular payback period for each of the projects? Round your answers to two...

  • Problem 10-21 Payback, NPV, and MIRR Your division is considering two investment projects, each of which...

    Problem 10-21 Payback, NPV, and MIRR Your division is considering two investment projects, each of which requires an up-front expenditure of $22 million. You estimate that the cost of capital is 12% and that the investments will produce the following after-tax cash flows (in millions of dollars): Year Project A Project B 1 5 20 2 10 10 3 15 8 4 20 6 What is the regular payback period for each of the projects? Round your answers to two...

  • 6 Instructions Your manager wants you to evaluate two mutually exclusive projects. The cash flows of...

    6 Instructions Your manager wants you to evaluate two mutually exclusive projects. The cash flows of the project is given in the flowing tables. 8 Project 1 $ uomi Cash flow (30,000) 8,000 10,000 11,000 17,000 12,000 + Onm Project 2 Cash flow $ (15,000) 2,000 5,000 7,000 2,000 25,000 20 The required rate of return is 15%. The first step is too evaluate the project using NPV, IRR, payback rule 21 You will do so in each tab named...

  • A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M Project N - $12,000 $4,000 $4,000 $4,000 $4,000 $4,000 -$36,000 $11,200 $11,200 $11,200 $11,200 $11,200 a. Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M: $ Project N: $ Calculate IRR for each project. Do not round intermediate calculations....

  • A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two decimal places. Do...

  • A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$21,000 $7,000 $7,000 $7,000 $7,000 $7,000 Project N -$63,000 $19,600 $19,600 $19,600 $19,600 $19,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two decimal places. Do...

  • A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M $(21,000) $7,000 $7,000 $7,000 $7,000 $7,000 Project N $(63,000) $19,600 $19,600 $19,600 $19,600 $19,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two decimal places. Do...

  • The IRR evaluation method assumes that cash flows from the project are reinvested at the same...

    The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation: Celestial Crane Cosmetics is analyzing a project that requires an initial investment of $2,750,000. The project's expected cash flows are: Year Year 1...

  • A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 23 5 Project M Project N - $30,000 $10,000 $10,000 $10,000 $10,000 $10,000 - $90,000 $28,000 $28,000 $28,000 $28,000 $28,000 a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to two...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT