Question

Question 2 If cumulative PV 100, cumulative EV 98 and cumulative AC 104, the project is likely to be: Item EV 10,000 7,000 8,

1 0
Add a comment Improve this question Transcribed image text
Answer #1

SPI= EV/PV.

SPI of the items are as follows:

Item 1= 10000/10000= 1

Item 2= 7000/9000= 7/9= 0.778

Item 3= 8000/8000= 1

Item 4= 5000/7000= 5/7= 0.71

Option b. Thus Item 4 has the lowest SPI.

Add a comment
Know the answer?
Add Answer to:
Question 2 If cumulative PV 100, cumulative EV 98 and cumulative AC 104, the project is likely to be: Item EV 10,000 7,000 8,000 5,000 PV 10,000 9,000 8,000 7,000 AC 1,000 8,000 8,000 7,000 Which ite...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Activity PV (in $) EV (in $) AC A 9,200 10,000 9,700 B 23,000 20,000 18,000...

    Activity PV (in $) EV (in $) AC A 9,200 10,000 9,700 B 23,000 20,000 18,000 C 12,000 13,000 11,000 D 8,000 10,000 12,000 E 10,000 12,000 13,000 F 7,000 9,000 10,000 G 8,000 9,000 10,000 A project to develop a country park has an actual cost in month 17 of $350,000, a planned cost of $475,000, and a value completed of $300,000. Find the cost and schedule variances, and CPI and SPI. What meaning do you derive from the...

  • QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an...

    QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the...

  • Activity PV (in $) EV (in $) AC A 9,200 10,000 9,700 B 23,000 20,000 18,000...

    Activity PV (in $) EV (in $) AC A 9,200 10,000 9,700 B 23,000 20,000 18,000 C 12,000 13,000 11,000 D 8,000 10,000 12,000 E 10,000 12,000 13,000 F 7,000 9,000 10,000 G 8,000 9,000 10,000 Find the schedule and cost variances for a project that has an actual cost at month 22 of $540,000, a scheduled cost of $523,000, and an earned value of $535,000.

  • 3) You are in charge of the Aurora Project. Given the following project network, baseline, and...

    3) You are in charge of the Aurora Project. Given the following project network, baseline, and status information, (40 Points) B DI OA E • Develop status reports for periods 7 and complete the performance indices table. . Calculate the EAC, and VAC. Based on your data, what is the current status of the project? At completion? Rule 1 0% complete 2-50/50 3 - 0/100 ID LF SL Schedule information Total 0 1 2 PV 3 4 30 5 6...

  • Senior management asks you to recommend a decision on which project(s) to accept based on the...

    Senior management asks you to recommend a decision on which project(s) to accept based on the cash flow forecasts provided.The firm uses a 3-year cutoff when using the payback method. The hurdle rate used to evaluate capital budgeting projects is 15%. Assume the projects are mutually exclusive and answer the following: Which project(s) would you accept based on the payback criterion? Which projects would you accept based on the IRR criterion? Which projects would you accept based on the NPV...

  • I need help with the attached assignment. I attached the question and completed assigment. I just...

    I need help with the attached assignment. I attached the question and completed assigment. I just need help with answering one more question which is which is: Discuss a strategy that you would use to communicate the status of the project to stakeholders? Project Monitoring and Control Assignment Complete the following items for this assignment: 1. Read through the Case 13.1 Tree Trimming Project Case in Larson and Gray. Respond to Questions 1 and 2 of the case. Use Microsoft...

  • Question 15 The following information about a project was provided: • Indirect costs per day: $233...

    Question 15 The following information about a project was provided: • Indirect costs per day: $233 • Late completion penalty of $84 per day beyond day 19 • The current Critical Path duration is 26 Acitvity А B с D E F G Immed Normal Normal Pred(s) Time (days) Cost ($) 3 7,000 1 3,000 A 4 12,000 B 2 12,000 1 8,000 DE 4 5,000 E 2 9,000 Crash Time Crash Cost (days) 2 10,000 1 3,000 2 40,000...

  • QUESTION 7 Consider the following cash flows: Year Cash Flow 0 -$10,000 1 $1,000 2 $2,000...

    QUESTION 7 Consider the following cash flows: Year Cash Flow 0 -$10,000 1 $1,000 2 $2,000 3 $3,000 4 $4,000 5 $5,000 Which equation would you use to compute the IRR? 1. -$10000 + $1000(P/G, i, 5) = 0 2. -$10,000 + $1,000 * (P/A, i, 5) + $1,000 * (P/G, i, 5) = 0 3. -$10,000 + $1,000 + $1,000 * (P/G,i,5) = 0 4. None of the above

  • Software Installation: You are the project manager of the software installation project (see figure & table)...

    Software Installation: You are the project manager of the software installation project (see figure & table) below. You would like to find the minimum-cost schedule for your project. There is a $1,000-per-week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,500 per week. Oo un D FINISH START START I Normal Normal Crash Crash Max reduction $ per Week Activity Time Cost Time Cost AI 5...

  • 1. Suppose a company has two mutually exclusive projects, both of which are three years in...

    1. Suppose a company has two mutually exclusive projects, both of which are three years in length. Project A has an initial outlay of $7,000 and has expected cash flows of $3,000 in year 1, $4,000 in year 2, and $4,000 in year 3. Project B has an initial outlay of $10,000 and has expected cash flows of $2,000 in year 1, $4,000 in year 2, and $5,000 in year 3. The required rate of return is 12% for projects...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT