Question

QUESTION 5 Not yet answered Marked out of 1.00 Flag question Percentage-of-Completion and Completed Contract Methods Philbric2. Percentage-of-completion method, where percentage-of-completion is determined by the costs incurred. Revenue Expense Gross

QUESTION 5 Not yet answered Marked out of 1.00 Flag question Percentage-of-Completion and Completed Contract Methods Philbrick Company signed a three-year contract to provide sales training to the employees of Elliot Company. The contract price is $1,200 per employee and the estimated number of employees to be trained is 400. The expected number to be trained in each year and the expected training costs follow Number of Training Costs Employees Incurred 2016 125 $60,000 2017 200 75,000 40,000 75 2018 400 175,000 Total Required For each year, compute the revenue, expense, and gross profit reported assuming revenue is recognized using the following method (Do not round until your final answers. Round your answers to two decimal places.) 1. Percentage-of-completion method, where percentage-of-completion is determined by the number of employees trained Expense Gross Profit Revenue 2016 S 2017 $ 2018 S Total
2. Percentage-of-completion method, where percentage-of-completion is determined by the costs incurred. Revenue Expense Gross Profit 2016 2017 $ 2018 Total 3. Completed contract method. Revenue Expense Gross Profit 2016 $ 2017 $ 2018 $ Total $
0 0
Add a comment Improve this question Transcribed image text
Answer #1


Solution: Part 1: Gross profit Revenue Expense 2016 95,312.50 150,000.0054,687.50 2017 152,500.00 240,000.00 87,500.00 2018 5

Add a comment
Know the answer?
Add Answer to:
QUESTION 5 Not yet answered Marked out of 1.00 Flag question Percentage-of-Completion and Completed Contract Methods Philbrick Company signed a three-year contract to provide sales training to the em...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 5 Partially correct Mark 1.00 out of 15.00 P Flag question Computing Percentage-of-Completion Revenues Bartov...

    Question 5 Partially correct Mark 1.00 out of 15.00 P Flag question Computing Percentage-of-Completion Revenues Bartov Corporation agreed to build a warehouse for $3,000,000. Expected and actual) costs for the warehouse follow: 2016, $500,000 2017, $1,400,000 and 2018, $600,000. The company completed the warehouse in 2018. Compute revenues, expenses, and income for each year 2016 through 2018 using the percentage-of-completion method. Round percentages to the nearest whole percent. Use rounded percentages to calculate subsequent answers. Year Costs incurred % of...

  • Question6. Long-term contract based on percentage of completion method (32 (4) Prepare journal entry to record...

    Question6. Long-term contract based on percentage of completion method (32 (4) Prepare journal entry to record gross profit for 2017(6 points) (5) Show at end of 2017 and 2018, what are the balance af CIP ( points) points) lim's Construction Co. has a $85,000,000 contract to build a new football stadium The project began on January 1, 2016 with an expected completion date of October 31, 2018. The following table provides infomation gathered during the construction period. Jim uses the...

  • Google Fiber signed a contract and hired Patrick Wirelines to build a new data center in...

    Google Fiber signed a contract and hired Patrick Wirelines to build a new data center in Aksarben. They signed a fixed price contract for 80,000. Additional information about the contract is included in the schedule with the problem worksheets. Required 1. Using the Percentage of Completion Method for each year report the amount of Revenue and Gross Profit or Loss that should be recognized 2. Using the Completed Contract Method for each year report the amount of Revenue and Gross...

  • The contract price for a 3-year construction contract is $100 The actual cost and estimated costs...

    The contract price for a 3-year construction contract is $100 The actual cost and estimated costs for each vear are given below: Items 2016 2017 2018 Actual cost incurred each year $10 Estimated cost to complete $40 Under Percentage of Completion method (You first prepare the table I showed you in the class to make your calculations easier) S20 $30 1. Compute Actual cost incurred to date 2. Compute total estimated cost for each year 3. Compute estimated gross profit...

  • Constructing and Assessing Income Statements Using Percentage of Completion On March 15, 2017, Frankel Construction is...

    Constructing and Assessing Income Statements Using Percentage of Completion On March 15, 2017, Frankel Construction is contracted to build a shopping center at a contract price of $120 million. The schedule of expected (equals actual) cash collections and contract costs follows Year Cash Collections Cost Incurred 2017 2018 2019 $30 million 15 million 50 million40 mlion 40 million 30 million Total $120 million 85 million Calculate the amount of revenue, expense, and income for each of the three years 2017...

  • Ex. 18-127-Percentage-of-completion and completed-contract methods. On February 1, 2012, Marsh Contractors agreed to construct a building...

    Ex. 18-127-Percentage-of-completion and completed-contract methods. On February 1, 2012, Marsh Contractors agreed to construct a building at a contract price of $5,400,000. Marsh estimated total construction costs would be $4,000,000 and the project would be finished in 2014. Information relating to the costs and billings for this contract is as follows: 2014 2012 $1,500,000 2,500,000 2,200,000 2,000,000 2013 $4,600,000 $2,640,000 1,760,000 4,000,000 3,500,000 Total costs incurred to date Estimated costs to complete Customer billings to date Collections to date -0-...

  • Tamarisk Construction Company uses the percentage-of-completion method of accounting. In 2017, Tamarisk began work under contract...

    Tamarisk Construction Company uses the percentage-of-completion method of accounting. In 2017, Tamarisk began work under contract #E2-D2, which provided for a contract price of $2,227,000. Other details follow: 2017 2018 Cost incurred during the year $660240 $1422000 Estimated costs to complete, as of December 31 911760 0 Billings to date 425000 2227000 Collections during the year 347000 1523000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017 $______________ Revenue...

  • On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2016, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2017, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2017 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2018 after additional costs of...

  • Question: Question:1.    When the percentage-of-completion method of accounting for long-term contracts, the percentage of completion used to...

    Question: Question:1.    When the percentage-of-completion method of accounting for long-term contracts, the percentage of completion used to recognize gross profit in the first year usually is determined by measuring: a. costs incurred in the first year, divided by estimated remaining costs to complete the project. b. costs incurred in the first year, divided by estimated total cost of the completed project. c. costs incurred in the first year, divided by estimated gross profit. d. none of the above.    2.As of...

  • Fender period. Construction Company receives a contract to construct a building over a 3 year Information...

    Fender period. Construction Company receives a contract to construct a building over a 3 year Information relating to the performance of the contract is summarized as follows: 2015 2016 2017 S 16,000,000 Cumulative construction costs incurred to date Estimated costs to complete Billings during the year Cash collected during the year 6,000,000 8,000,000 6,000,000 3,000,000 8,000,000 7,000,000 4,000,000 5,000,000 Required: 1. How much is Fender Construction charging to build this athletic stadium? In other words, what is the contract price...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT