UMUC hospital has decided to implement a new EHR and appointed you as the EHR Project Manager. The EHR needs to be implemented in one year. Which Project Management tool (hint: Gantt Chart, Microsoft Office Project) would you use to keep track of the schedule and how? How would you avoid the Scope Creep that usually results in project implementation delays?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

EHR project managers can effectively use a Gantt chart as an effective project management tool. It is also known as an activity chart, milestones chart or project bar chart.

In order to outline the plan for and show the progress of a project, the Gantt chart can be used. It also possesses the format of a bar chart. It can depict the various subdivided phases or tasks that must be completed for a project to be finished in accordance with the project timeline and the phases or tasks need to occur. It can be useful in showing the progress on which tasks have been completed by the help of shades. It can also demonstrate the teams or individuals responsible for completing every task. Gantt chart allows the project team to make realistic timelines and goals for the project. It can direct the attention to the most crucial aspects of the project. The chart is extremely useful for monitoring the progress of a project due to the ability to demonstrate tasks on the project timeline.

The advantages:

Gantt chart helps in understanding how tasks or phases of a project overlap and sequence in which they need to occur.

Aids to identify critical tasks or phases of a project.

Helps to monitor the project's progress and deadlines if the project is lagging behind its schedule.

Useful in project scheduling.

Gives a visual representation of start times, durations, and overlap of tasks within a project for easy understanding.

Easy to create, interpret, or monitor.

Supports resource allocation for the project.

Allows setting realistic expectations and attainable timetables.

Disadvantages:

The main disadvantage of the Gantt chart is the little room for uncertainty.

Steps to use the Gantt chart in an EHR

1. IDENTIFICATION OF THE TASKS THAT COMPRISE THE PROJECT AND IDENTIFY PRIMARY GOALS.

Methods like brainstorming, constructing a flowchart or storyboard, or creating an arrow diagram helps in accomplishing this.

Determine the time required to complete each task followed by the sequence to follow. This will also contain information about which tasks must be completed before the next can start or which tasks can be overlapped or occurred simultaneously. Before reaching each milestone in the project, identify the task that needs to be finished.

2. CREAT OR DRAW A HORIZONTAL TIME AXIS AT THE TOP OR BOTTOM OF A PAGE.

The time axis can be marked with an appropriate timescale for the length of the project and its tasks like days or weeks.

3. EACH TASK AND MILESTONE OF THE PROJECT MUST BE WRITTEN IN ORDER, VERTICALLY ALONG THE LEFT SIDE OF THE PAGE.

A diamond can be drawn (solely its outline) further down the time of the event.

An unfilled bar can be used under the corresponding times on the timeline to denote, if there is an event that needs to happen at a specific date and time or if an activity occurs over a period of time. The beginning of the activity starts at the leftmost point of the bar and ends at the rightmost point.

4. INCLUDE EVERY TASK OF THE PROJECT ON THE CHART.

5. DENOTE THE COMPLETION OF EVENTS AND ACTIVITIES BY FILLING IN THE DIAMONDS AND BARS ON THE CHART.

Ongoing tasks can be marked as per their progress by estimating their percentage of completion and filling that much of the bar.

6. THE CURRENT TIME ON THE TIMELINE CAN BE MARKED BY PLACING A VERTICAL MARKER.

This can be achieved by simple techniques like string and/ or two thumbtacks.

SCOPE CREEP

Scope creep occurs when changes are made to the scope of a project without any control, beyond the normally expected changes. It usually arises when new requirements added to the project are uncontrollable and without proper review. The resources of the project team and the time is not expending. The project may not end in such a situation.

The scope creep can be minimized or managed by the following measure:

1. Proper documentation of the requirements

The best and most important thing to avoid scope creeps the project is to document the requirements. Manage conflicts and use arbitrate to compromise between the stakeholders. Finish the requirements based on their priority. Make sure to communicate the documents with the stakeholders.

2. Set guidelines for the Change Control Processes

A change control process can be used to review the suggested changes and only the approved changes are incorporated in the project.

3. Develop a Clear Project Schedule

Schedule all the tasks and activities of the project and stick on to it to the possible extend.

4. Verify the Scope of the project with the Stakeholders

Share the requirements documentation with the stakeholders to ensure all the elements they expected to see are represented in the task list.

Discussions with the sponsor and stakeholders about the change control process are also useful.

5. Project Team engagement

Inform and engage the project team in the change control process.

Add a comment
Know the answer?
Add Answer to:
UMUC hospital has decided to implement a new EHR and appointed you as the EHR Project Manager. The EHR needs to be imple...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • UMUC hospital is going to implement a new EHR and has appointed you as the EHR...

    UMUC hospital is going to implement a new EHR and has appointed you as the EHR Project Manager. During the vendor selection process, the project team recognized that five vendors could be potential suppliers. However, three of these five are well-known while the other two are relatively less known. List and discuss five criteria that you would use for the final EHR vendor selection.

  • ou have been appointed as lead project manager for the implementation of a new EHR system...

    ou have been appointed as lead project manager for the implementation of a new EHR system in a large multi- campus hospital system. The CEO and Board of Directors have asked you to provide information regarding the methods by which you will ensure successful adoption of the new information system. Please follow the instructions below in completion of this assignment. Part 1: Instructions: Discuss the relationship between health care regulation compliance and quality management. Demonstrate the quality management tools that...

  • WRITE 50 WORDS Your organization has decided to implement the EHR system, and you have been...

    WRITE 50 WORDS Your organization has decided to implement the EHR system, and you have been appointed as a member of steering committee. Discuss the role of the steering committee in EHR implementation.

  • The activity An EHR was implemented at the General Hospital one year ago, before you were...

    The activity An EHR was implemented at the General Hospital one year ago, before you were hired. The implementation process did not go smoothly and now there are strong EHR advocates and strong EHR-dissenters on the team. The CEO wants to move forward with an implementation of the bar-coded medication administration feature of the EHR, but the director of nursing does not. You have been asked to manage the implementation and see that it is successful. You will first need...

  • !!!Only Project 2 need to be answered!!! Project Report 1 Once the business case has been approved, you need to make a...

    !!!Only Project 2 need to be answered!!! Project Report 1 Once the business case has been approved, you need to make a project plan showing each task. Assume you are a project manager to lead your team to acquire an additional delivery van for the company. Please find the details below. The current month is January. Activity (What is to be done?) Objective (Why will we do it?) Resources (Where will it be done?) Procedures (How will it be done?)...

  • Part 2: Project Scope Management Congratulations! You have been selected as the project manager for the...

    Part 2: Project Scope Management Congratulations! You have been selected as the project manager for the Green Computing Research Project. The company’s CIO, Ben, is the project sponsor, and Ito is the program manager for the larger Environmental Technologies Program that this project is part of. Now you need to put together your project team and get to work on this high-visibility project. You will work with Ben to handpick your team. Ben had already worked with the HR department...

  • 2. A) We require you to describe how you would use project management tools to develop and implement a project plan. Dis...

    2. A) We require you to describe how you would use project management tools to develop and implement a project plan. Discuss at least 3 tools from below: Activity (What is to be done?) Objective (Why will we do it?) Resources (Where will it be done?) Procedures (How will it be done?) Responsible person (Who will do it?) When? Budget Acquire additional resources – delivery van. To provide a delivery service and provide brand recognition Purchase a new van for...

  • CASE 17: WATSON’S AMBULATORY EHR TRANSITION Major theme: System acquisition Primary care physicians play a key...

    CASE 17: WATSON’S AMBULATORY EHR TRANSITION Major theme: System acquisition Primary care physicians play a key role in the U.S. health care delivery system. These providers integrate internal and external information with their clinical knowledge to determine the patient’s treatment options. An effective ambulatory electronic health record (EHR) is critical to supply physicians with the information they need to provide quality care and maximize their efficiency. This case involves the decision-making process to replace an inadequate EHR system in a...

  • Project 1: You work at a health care facility (General Hospital) that has experienced an increase...

    Project 1: You work at a health care facility (General Hospital) that has experienced an increase in patient falls on the Med/Surg ward over the last year. Put together a PI team and create the following: List of team members, their work area, and why they have been selected for the team (How are they a part of this issue?). Write a concise Mission Statement and Vision Statement for your team - These should relate directly to the purpose of...

  • Your team of consultants has been hired to create a database for MD Employment Agency (MDEA)....

    Your team of consultants has been hired to create a database for MD Employment Agency (MDEA). MDEA is an employment agency that contracts with the city of Miami, FL to assist displaced workers in finding new career opportunities and to help workers currently collecting unemployment benefits. Up to this point MDEA has been using standalone PCs to handle data entry of new clients and to update their status. The company also has relationships with local government agencies that have openings...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT