Question

Question 2 Assume that Beta Inc. entered into an agreement to build a ship for $1,000 million and a reliable estimate of the

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Case A: Calculation of Net Income for Each Year Using Percentage of Completion Method:

Net revenue = Revenue - cost

Under this method revenue is recognized based on the percentage of completion of the contract.

Percentage complete = (cost incurred till date / estimated total cost)

Percentage complete for year 1 = ($400 million / $800 million) * 100 = 50%

Percentage complete for year 2 = ( ($400 million + $300 million) / $800 million) * 100 = 87.5%

Percentage complete for year 3 = ( ($400 million + $300 million + $100 million) / $800 million) * 100 = 100%

Revenue = ( Percentage complete * Contract price ) - ( revenue preciously recognized )

Revenue for year 1 = ( 50% * $1,000 million ) - ( 0 ) = $500 million

Revenue for year 2 = ( 87.5% * $1,000 million ) - ( $500 million) = $875 million - $500 million = $375 million

Revenue for year 3 = ( 100% * $1,000 million ) - ( $500 million + $375 million ) = $1,000 million - $875 million = $125 million

Calculation of net income:

Net income for year 1 = Revenue for year 1 - cost incurred in year 1 = $500 million - $400 million = $100 million

Net income for year 2 = Revenue for year 2 - cost incurred in year 2 = $375 million - $300 million = $75 million

Net income for year 3 = Revenue for year 3 - cost incurred in year 3 = $125 million - $100 million = $25 million

Therefore net income for the year 1 is $100 million, for the year 2 is $75 million and for the year 3 is $25 million.

Case B: Calculation of Net Income for Each Year Using Completed Contracts Method:

The completed contract method refers to a method in which all of the revenue and profit associated with the project is recognized only after the completion of the project.

Hence, net income for the year 1 and year 2 will be Nil. And the total net income from the project will be recognized in the year 3 i.e. $200 million (Contract price - total cost = $1,000 million - $800 million).

Therefore, net income for the year 1 = Nil

net income for the year 2 = Nil

net income for the year 3 = $200 million

Add a comment
Know the answer?
Add Answer to:
Question 2 Assume that Beta Inc. entered into an agreement to build a ship for $1,000 million and a reliable estimate o...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Rangers Corp. entered into a contract to construct a factory building. The contract price is $10,000,000....

    Rangers Corp. entered into a contract to construct a factory building. The contract price is $10,000,000. Cost information over the life of the contract is as follows: Year 2014 2015 2016 Cost Incurred During Year $2,000,000 3,500,000 1.100.000 Estimated Cost to Complete $5,000,000 1,250,000 0 Rangers uses cost-to-cost to estimate the percentage complete on the contract. Provide the amount of gross profit recognized each year using two alternative revenue recognition methods. Year Completed Contract Method Percentage of Completion Method 2014...

  • A construction company entered into a fixed-price contract to build an office building for $20 million....

    A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • A construction company entered into a fixed-price contract to build an office building for $44 million....

    A construction company entered into a fixed-price contract to build an office building for $44 million. Construction costs incurred during the first year were $14 million and estimated costs to complete at the end of the year were $21 million. The building was completed during the second year. Construction costs incurred during the second year were $22 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • Ranger's Corp. entered into a contract to construct a factory building. The contract price is $10M....

    Ranger's Corp. entered into a contract to construct a factory building. The contract price is $10M. cost information over life of the contract is as follows 5.16 Rangers Corp. entered into a contract to construct a factory building. The contract price is $10,000,000. Cost information over the life of the contract is as follows: Year 2014 2015 2016 Cost Incurred During Year $2,000,000 3,500,000 1,100,000 Estimated Cost to Complete $5,000,000 1.250.000 Rangers uses cost-to-cost to estimate the percentage complete on...

  • During 20x5, the Ibti Construction Company obtained a $15 million contract to build a bridge. The...

    During 20x5, the Ibti Construction Company obtained a $15 million contract to build a bridge. The costs incurred, estimated costs to complete and the billings made on the contract for the period 20x5 – 20x6 are as follows: 20x5 20x6 Costs incurred during the year $3,000,000 $5,000,000 Expected costs to complete 9,000,000 6,000,000 Billings 7,500,000 - Ibti uses the percentage of completion method. Costs incurred relative to total project costs are used to measure the percentage of completion at the...

  • A construction company entered into a fixed-price contract to build an office building for $12 million....

    A construction company entered into a fixed-price contract to build an office building for $12 million. Construction costs incurred during the first year were $4 million and estimated costs to complete at the end of the year were $6 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.) Revenue

  • A construction company entered into a fixed-price contract to build an office building for $46 million....

    A construction company entered into a fixed-price contract to build an office building for $46 million. Construction costs incurred during the first year were $12 million and estimated costs to complete at the end of the year were $28 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.) Revenue

  • A construction company entered into a fixed-price contract to build an office building for $48 million....

    A construction company entered into a fixed-price contract to build an office building for $48 million. Construction costs incurred during the first year were $18 million and estimated costs to complete at the end of the year were $27 million. The building was completed during the second year. Construction costs incurred during the second year were $28 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • A construction company entered into a fixed-price contract to build an office building for $10 million....

    A construction company entered into a fixed-price contract to build an office building for $10 million. Construction costs incurred during the first year were $2 million and estimated costs to complete at the end of the year were $3 million. The building was completed during the second year. Construction costs incurred during the second year were $4 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • A company has a contract to build a bridge for $100,000 with an estimated time to...

    A company has a contract to build a bridge for $100,000 with an estimated time to completion of three years. A reliable total cost estimate for the project would be $60,000. In the first year of the project, the company incurred a cost of $24,000. (a) Assume that the contractor bases the degree of completion on the percentage of total costs incurred to date. Under the percentage-of-completion method, what amount of gross profit the company will report in the first...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT