Required Return from the project as per CAPM = Risk free rate + beta*(Market Return - Risk Free Rate) | ||||
Project | Risk free rate | Beta | Market Risk premium | CAPM Return |
A | 3% | 0.6 | 8% | 7.80% |
B | 3% | 1.3 | 8% | 13.40% |
C | 3% | 1.5 | 8% | 15.00% |
D | 3% | 1.7 | 8% | 16.60% |
Acceptable projects are those whose expected return is higher than CAPM return | ||||
i.e. Projects A, B and D | ||||
Project C will be incorrectly accepted |
An all-equity firm is considering the projects shown below. The T-bill rate is 3 percent and...
An all-equity firm is considering the projects shown below. The T-bill rate is 6 percent and the market risk premium is 8 percent. Project - Expected - Return Beta A 9 % 0.3 B 21 % 1.1 C 15 % 1.3 D 19 % 1.5 Calculate the project-specific benchmarks for each project. (Round your answers to 2 decimal places.)
3. (Ch 10] An all-equity firm is considering the projects shown in the table below. The T-bill rate is 2% and the market risk premium is 5.5%. If the firm uses its current (composite) WACC of 7% (which it should NOT do because the WACC ignores risk) to evaluate these projects, which project(s), if any, will be INCORRECTLY rejected, and which projects, if any, will be INCORRECTLY accepted? [HINT: A picture might help you.] Project Beta 0.15 A Expected Return...
SML and WACC. An all-equity firm is considering the following projects: The T-bill rate is 4 percent, and the expected return on the market is 12 percent. a. Which projects have a higher expected return than the firm’s 12 percent cost of capital? b. Which projects should be accepted? c. Which projects will be incorrectly accepted or rejected if the firm’s overall cost of capital were used as a hurdle rate?
17. SML and WACC [LO1] An all-equity firm is considering the following projects: Project Beta IRR W 8.9% X .85 .92 1.09 1.35 10.8 12.8 < 13.3 N The T-bill rate is 4 percent, and the expected return on the market is 11 percent. a. Which projects have a higher expected return than the firm's 11 percent cost of capital? b. Which projects should be accepted? c. Which projects would be incorrectly accepted or rejected if the firm's overall cost...
(5 points) An all equity firm is considering the following projects: 2. Project Beta 0.8 1.2 IRR 10% 12% The risk-free rate is 3% and the expected market rate premium is 8%. The firm has a beta equal to 1 (1 point) What is the firm's cost of capital? a. b. (2 points) Which projects should be accepted? Explain (2 point) Which projects will be incorrectly accepted or rejected if the firm's overall cost of capital were used to as...
An all-equity firm is considering the following projects: Project Beta IRR W .64 9.5 % X .75 10.6 Y 1.31 14.1 Z 1.42 17.2 The T-bill rate is 5.2 percent, and the expected return on the market is 12.2 percent. a. Which projects have a higher/lower expected return than the firm’s 12.2 percent cost of capital? b. Which projects should be accepted? c. Which projects will be incorrectly accepted/rejected or correctly accepted/rejected if the firm's overall cost of capital were...
An all-equity firm is considering the following projects: Project Beta .89 76 141 IRR 10.3% 108 143 173 1.52 The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. a. Which projects have a higher/lower expected return than the firm's 12.3 percent cost of capital? expected return, Project X has a expected return, Project Y has a Project W has a expected return, and Project Z has a expected return b. Which projects should...
An all-equity firm is considering the following projects: Project Beta 80 90 1.10 1.35 IRR 9.3% 11.4 12.1 15.1 The T-bill rate is 4 percent, and the expected return on the market is 12 percent. a. Which projects have a higher expected return than the firm's 12 percent cost of capital? expected retum, Project X has a Project W has a expected return, and Project Z has a expected return, Project Y has a expected return. b. Which projects should...
An all-equity firm is considering the following projects: Project Beta IRR W .58 9% X .87 9.7% Y 1.13 12.1% Z 1.47 15.2% The T-bill rate is 4.2 percent, and the expected return on the market is 11.2 percent. Compared with the firm's 11.2 percent cost of capital, Project W has a _____(answer 1) (lower or Higher)____ expected return, Project X has a _____(answer 2) (lower or Higher)____ expected return, Project Y has a _____(answer 3) (lower or Higher)____ expected...
An all-equity firm is considering the following projects: Project Beta IRR W .65 10.0 % X .90 10.5 Y 1.20 14.0 Z 1.80 17.0 The T-bill rate is 5 percent, and the expected return on the market is 12 percent. Required: (a) Which projects have a higher expected return than the firm’s 12 percent cost of capital? Project W has a (Click to select)lowerhigher expected return, Project X has a (Click to select)lowerhigher expected return, Project...