SALES DATA Use the data provided to answer questions 1 through 4. Month Sales 8552 7759...
a) The correct precedence relationship with one of the possible assignment of tasks to workstations is shown in ? b) What is the operating efficiency of the assembly line, using your answer to (a)? c) What is the theoretical minimum number of workstations? d) What is the idle time per boat produced? IOIIGWufk. Cny Score: 0 of 1 pt Problem 9.18 Assembly Line Balancing 10 of 11 (6 complete) HW Score: 54.55%, 6 of 11 Question Holp The final assembly...
3. Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 48 chairs. the eight tasks required to produce the chair and the precedence diagram are shown below TASK PERFORMANCE TIME (min) ULUI Precedence diagram a. What is the cycle time for...
Use the following sales data to answer the questions. Month Sales January $250,000 February $200,000 March $300,000 April $350,000 May $450,000 Using a two month moving average, what are the expected sales for June? Using a three month moving average, what are the expected sales for June? Ed Rogers owns an appliance store. Sales data on a particular model of a DVD player for the past six months are shown below, along with the results of two different...
The operations manager of an instruments company is balancing an assembly line. The company needs to build 96 instruments per 24-hour day. The assembly line activities are: a. Draw the precedence diagram. b. If the daily (24-hour) production rate is 96 units, what is the greatest possible cycle time? c. If the cycle time after allowances is given as 10 minutes, what is the daily (24-hour) production rate? d. With a 10-minute cycle time, what is the theoretical minimum number...
1. [Layout Strategy-Line Balancing] The call center department of Jax-steel company needs to service 3,000 calls per 40-hour workweek. The process of servicing calls can be broken down into the six stations listed above. The precedence and time requirements for each element are as follows in the table below. The manager wants a new operational analyst to draw and label a precedence diagram for the service process. Finally, the manager needs to balance the line, calculate the efficiency of the...
The following is the data of recent refrigerator sales at a local Home Depot store. Month 1 2 3 4 5 Actual Sales 95 100 80 90 ??? Inputs will be exact numbers. What is the forecasted sales in month 5 using naive approach. Please use a 2-month simple moving average method to forecast sales in month 5. Please use a weighted moving average method, with weights of 0.6 one period ago, 0.3 two periods ago, and 0.1 three periods...
Hello, I need to see the solution, how they got these numbers? Will appreciate help. The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,600 units per 40-hour workweek: Predecessors Task A B С D E F Performance Time (seconds) 22 27 14 15 10 28 А A А B, C DE This exercise only contains parts b, c, d, e, and...
4.22 The table below lists the work elements in minutes to be performed on assembly line with precedence requirements. Annual demand is 60000 units. The line will operate on shift (2000 hr/yr). Line efficiency is expected 95% and repositioning time is 6 sec. The table below defines the precedence relationships and element times for a new model toy. (a) Construct the precedence diagram for this job. (b) If the ideal cycle time = 1.1 min. repositioning time = 0.1 min,...
2. Use the data provided to answer the following questions. Data for Last Week: Values LY POS Sales TY POS Sales LY POS Qty TY POS Qty LY Next Week Sales LY Next Week QTY LY Next 13 QTY $60,000 $56,250 11,625 10,901 $58,824 11,400 140,500 a. What is the average price for last year (LY), this year (TY)? b. What are the percent changes year-over-year (YOY) in sales and quantity? C. What would you suggest should be an expected...
CAN YOU PLEASE HELP ME?The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,800 units per 40-hour workweek:Questions;1) Draw a precedence diagram of this operation.2) In Question 1, given the demand, what is the cycle time for this operation? Write the formula, and show your calculations.3) For Question 1, what is the theoretical minimum number of workstations? Write the formula, and show your calculations.4) For, Question 1, assign tasks to workstations. 5) For Question 1,...