The formula is as below:
EAC = Initial cost (A/P, interest rate, number of years) + Annual maintenance cost + Annual cleaning cost
= 90,000 (A/P, 6%, 15) + 700 + 10,000
Now the “compound interest table” as per 6% rate for 15 years gives A/P factor as 0.1030. This is to be inserted in the above formula.
EAC = 90,000 × 0.1030 + 700 + 10,000
= 9,270 + 700 + 10,000
= 19,970 (Answer)
A short concrete canal can be constructed as part of a flood control project. The cost...
2. In a proposed flood control project, there are two possible sites, A and B, for a dam and storage reservoir. One or the other of these sites may be used but not both. Certain channel improvement is also considered; this will increase the capacity of the stream to carry flood discharge. Estimated first costs, lives, and annual operation and maintenance costs are as follows: Site A Site B Channel Improvement First cost $6,000,000 $8,000,000 $1,000,000 Life 75 years 75...
Question 6 A flood control project at Pleasant Valley dam is projected to cost $2,130,000 today, have annual maintenance costs of $40,000, and have major inspection and upkeep after each 3-year interval costing $220,000. If the interest rate is 9%/year Click here to access the TVM Pactor Table Calculator Determine the total capitalized cost. $ Round entry to o decimal places. The tolerance is t12. LINK TO TEXT LINK TO VIDEO Attempts: 0 of 3 used SAVE FOR LATER SUBMIT...
Question 6 A flood control project at Pleasant Valley dam is projected to cost $2,300,000 today, have annual maintenance costs of $50,000, and have major inspection and upkeep after each 9-year interval costing $280,000. If the interest rate is 12%/year. Click here to access the TVM Factor Table Calculator x Your answer is incorrect. Try again. Determine the total capitalized cost. $. 1713845. Round entry to o decimal places. The tolerance is 24. Click if you would like to Show...
The Capitalized cost (CC) of the project is
The property appraisal district for Marin County has just installed new software to track residential market values for property tax computations. The manager wants to know the total equivalent cost of all future costs incurred when the three county judges agreed to purchase the software system. If the new system will be used for the indefinite future, find the equivalent value (a) now and (b) for each year hereafter. The system has...
1) Johnson Jets is considering two mutually exclusive projects. Project A has an up-front cost of $122,000 (CF0 = -122,000), and produces positive after-tax cash inflows of $30,000 a year at the end of each of the next six years. Project B has an up-front cost of $60,000(CF0 = -60,000) and produces after-tax cash inflows of $20,000 a year at the end of the next four years. Assuming the cost of capital is 10.5%, 1. Compute the equivalent annual...
The answer is shown in the
picture, i want to know how they got it, please show all your work
and if you are using excel please show your formulas, Thank You and
good luck.
Toll lanes on a section of the 1-40 freeway are being considered in order to reduce traffic congestion and travel times Since this is a government project, the B-C ratio method must be applied in the evaluation. Construction costs of the project are estimated to...
An area on the Colorado River is subject to periodic flood damage that occurs, on the average, every two years (i.e., probability of flooding in any year is 0.5) and results in a $2,200,000 loss. It has been proposed that the river channel be improved by straightening and deepening it at a cost of$2,400,000, to reduce the annual probability of flooding to 0.364 during a period of 18 years before it would have to be deepened again. This procedure would...
In a proposed flood control project, there are two possible sites for a dam and storage reservoir, designated as the Willow and Cottonwood sites. One or the other of these sites may be used but not both. A small hydroelectric power development may be added at the Willow site. Certain channel improvements are also considered. Seven alternate projects are set up for analysis and average annual damages due to floods under each plan estimate as follows: Plan Damages A) Willow...
Toll lanes on a section of the l-40 freeway are being considered in order to reduce traffic congestion and travel times. Since this is a government project, the B-C ratio method must be applied in the evaluation. Construction costs of the project are estimated to be $18,600,000, and $321,000 per year in operating and maintenance costs are anticipated. In addition, the lanes must be resurfaced every fourth year of their 20-year projected life at a cost of $1,110,000 per occurrence...
Cost Analysis: The Purchase of Health Care Equipment Team Project An equipment acquisition proposal is being considered by a large healthcare organization, XYZ Health Care. The array machine will enable the hospital to perform autoimmunity tests (for immunoglobulins G, M, and A and complements C3 and C4) in-house rather than sending them to a reference laboratory. Test turnaround time is expected to decrease by 2 days. The array machine costs $50,000, with a useful life of 5 years. The depreciation...