Question 10 Blossom Construction Company uses the percentage-of-completion method. During 2018, the company entered into a...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
On February 1, 2018, Arrow Construction Company entered into a
three-year construction contract to build a bridge for a price of
$8,060,000. During 2018, costs of $2,020,000 were incurred with
estimated costs of $4,020,000 yet to be incurred. Billings of
$2,520,000 were sent, and cash collected was $2,270,000.
In 2019, costs incurred were $2,520,000 with remaining costs
estimated to be $3,630,000. 2019 billings were $2,770,000 and
$2,495,000 cash was collected. The project was completed in 2020
after additional costs of...
Sheffield Construction Company has entered into a contract beginning January 1, 2012, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. 2019 $608,000 Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $294,000 306,000 268,000 238,000 2018 $432,000 168,000 547,000 497,000...
Cheyenne Construction Company has entered into a contract
beginning January 1, 2017, to build a parking complex. It has been
estimated that the complex will cost $596,000 and will take 3 years
to construct. The complex will be billed to the purchasing company
at $895,000. The following data pertain to the construction
period.
2017
2018
2019
Costs to date
$268,200
$482,760
$605,000
Estimated costs to
complete
327,800
113,240
–0–
Progress billings to
date
267,000
552,000
895,000
Cash collected to date...
Swifty Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2019 Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $266,640 339,360 270,000 240,000 2018 $412,080 193,920 545,000 495,000 $617,000...
Ayayai Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $246,000 354,000 270,000 240,000 2018 $432,000 168,000 546,000 496,000 2019 $612,000...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $390 million. The expected completion date is April 1, 2020. lust in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2018 2019 2020 $ 60 $130 $70...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 S 30 140 $40...
it says it's incomplete, please help
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,600,000. During 2018, costs of $2,200,000 were incurred with estimated costs of $4,200,000 yet to be incurred. Billings of $2,700,000 were sent, and cash collected was $2,450,000. In 2019, costs incurred were $2,700,000 with remaining costs estimated to be $3,900,000. 2019 billings were $2,950,000 and $2,675,000 cash was collected. The project was completed...
Riverbed Construction Company uses the percentage-of-completion
method of accounting. In 2017, Riverbed began work under contract
#E2-D2, which provided for a contract price of $2,195,000. Other
details follow:
2017
2018
Costs incurred during the year
$695,310
$1,404,000
Estimated costs to complete, as of December 31
921,690
–0–
Billings to date
426,000
2,195,000
Collections during the year
352,000
1,475,000
What portion of the total contract price would be recognized as
revenue in 2017? In 2018?
Revenue recognized in 2017
$
Revenue...