Question

A company is considering a project that will cost $100,000. To determine market potential, the company paid $5000 to a firm t
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Calculating IRR,

105,000 = 15,000/(1+IRR)* + 25,000/(1+I RR)* +20,000/(1+ IRR)5

IRR = 5.09%

The IRR is less than hurdle rate, so the project should be rejected.

Add a comment
Know the answer?
Add Answer to:
A company is considering a project that will cost $100,000. To determine market potential, the company...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Unanswered A company is considering a project that will cost $100,000. To determine market potential, the...

    Unanswered A company is considering a project that will cost $100,000. To determine market potential, the company paid $5000 to a firm to perform market research. The firm estimates that the project will produce $15,000 in the first 2 years and $25,000 in the remaining 3 years. At the end of the project the company can sell the assets for $20,000. The hurdle rate is 6.5%. What is the project's IRR? (Convert to a percent. Enter only numbers in your...

  • Unanswered A company is considering a project that will cost $100,000. To determine market potential, the...

    Unanswered A company is considering a project that will cost $100,000. To determine market potential, the company paid $5000 to a firm to perform market research. The firm estimates that the project will produce $15,000 in the first 2 years and $25,000 in the remaining 3 years. At the end of the project the company can sell the assets for $20,000 after taxes. The hurdle rate is 6.5%. Which of the following is true about the cost of the market...

  • An all-equity firm is considering the following projects: Project Beta IRR W .64     9.5 % X...

    An all-equity firm is considering the following projects: Project Beta IRR W .64     9.5 % X .75     10.6 Y 1.31     14.1 Z 1.42     17.2 The T-bill rate is 5.2 percent, and the expected return on the market is 12.2 percent. a. Which projects have a higher/lower expected return than the firm’s 12.2 percent cost of capital? b. Which projects should be accepted? c. Which projects will be incorrectly accepted/rejected or correctly accepted/rejected if the firm's overall cost of capital were...

  • An all-equity firm is considering the following projects: Project Beta .89 76 141 IRR 10.3% 108...

    An all-equity firm is considering the following projects: Project Beta .89 76 141 IRR 10.3% 108 143 173 1.52 The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. a. Which projects have a higher/lower expected return than the firm's 12.3 percent cost of capital? expected return, Project X has a expected return, Project Y has a Project W has a expected return, and Project Z has a expected return b. Which projects should...

  • An all-equity firm is considering the following projects: Project Beta 80 90 1.10 1.35 IRR 9.3%...

    An all-equity firm is considering the following projects: Project Beta 80 90 1.10 1.35 IRR 9.3% 11.4 12.1 15.1 The T-bill rate is 4 percent, and the expected return on the market is 12 percent. a. Which projects have a higher expected return than the firm's 12 percent cost of capital? expected retum, Project X has a Project W has a expected return, and Project Z has a expected return, Project Y has a expected return. b. Which projects should...

  • n all-equity firm is considering the following projects: Project W Beta IRR .80 9.3% х .90...

    n all-equity firm is considering the following projects: Project W Beta IRR .80 9.3% х .90 11.4 Y 1.10 12.1 Z 1.35 15.1 he T-bill rate is 4 percent, and the expected return on the market is 12 percent. . Which projects have a higher expected return than the firm's 12 percent cost of capital? expected return, Project X has a Project W has a expected return, Project Y has a expected return expected return, and Project Z has a...

  • 17. SML and WACC [LO1] An all-equity firm is considering the following projects: Project Beta IRR...

    17. SML and WACC [LO1] An all-equity firm is considering the following projects: Project Beta IRR W 8.9% X .85 .92 1.09 1.35 10.8 12.8 < 13.3 N The T-bill rate is 4 percent, and the expected return on the market is 11 percent. a. Which projects have a higher expected return than the firm's 11 percent cost of capital? b. Which projects should be accepted? c. Which projects would be incorrectly accepted or rejected if the firm's overall cost...

  • An all-equity firm is considering the following projects: Project Beta IRR W .58 9% X .87...

    An all-equity firm is considering the following projects: Project Beta IRR W .58 9% X .87 9.7% Y 1.13 12.1% Z 1.47 15.2% The T-bill rate is 4.2 percent, and the expected return on the market is 11.2 percent. Compared with the firm's 11.2 percent cost of capital, Project W has a _____(answer 1) (lower or Higher)____ expected return, Project X has a _____(answer 2) (lower or Higher)____ expected return, Project Y has a _____(answer 3) (lower or Higher)____ expected...

  • (5 points) An all equity firm is considering the following projects: 2. Project Beta 0.8 1.2...

    (5 points) An all equity firm is considering the following projects: 2. Project Beta 0.8 1.2 IRR 10% 12% The risk-free rate is 3% and the expected market rate premium is 8%. The firm has a beta equal to 1 (1 point) What is the firm's cost of capital? a. b. (2 points) Which projects should be accepted? Explain (2 point) Which projects will be incorrectly accepted or rejected if the firm's overall cost of capital were used to as...

  • An all-equity firm is considering the following projects: Project Beta IRR W .65       10.0 %...

    An all-equity firm is considering the following projects: Project Beta IRR W .65       10.0 % X .90       10.5 Y 1.20       14.0 Z 1.80       17.0 The T-bill rate is 5 percent, and the expected return on the market is 12 percent. Required: (a) Which projects have a higher expected return than the firm’s 12 percent cost of capital? Project W has a (Click to select)lowerhigher expected return, Project X has a (Click to select)lowerhigher expected return, Project...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT