Solution:
Computation of % of completion and revenue recognition | |||||
Year | Km Completed during the year | Total Kms | % of completion | Contract Price (In millions) | Revenue Recognition for the year (In millions) |
20X0 | 51 | 170 | 30.0% | $160.00 | $48.00 |
20X1 | 85 | 170 | 50.0% | $160.00 | $80.00 |
20X2 | 34 | 170 | 20.0% | $160.00 | $32.00 |
CCS is a construction company that builds roads in the Northwest Territories (NWT). CCS uses the...
Hamilton Construction Company uses the percentage-of-completion method of accounting. In 2020, Hamilton began work on the construction of a hospital, which provides for a contract price of $2,195,000. Other details follow: 20XO 20X1 Costs incurred during the year 637,600 1,000,000 Total estimated cost 1,594,000 1,637,600 Billings during the year 427,000 2,195,000 Collections during the year 343,000 1,509,000 What portion of the total contract price would be recognized as revenue in 20x0? 2,195,000 878,000 1,097,500 427,000 343,000
In 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
Westgate recognizes revenue over time according to percentage of
completion.
Calculate the amount of revenue and gross profit (loss) to be
recognized in each of the three years assuming the following costs
incurred and costs to complete information. (Do not round
intermediate calculations and round your...
Nailed It! Construction (Nailed It! or the “Company”), an SEC registrant, is a construction company that manufactures commercial and residential buildings. On March 1, 20X1, the Company entered into an agreement with a customer, Village Apartments, to construct a residential apartment building for a fixed price of $1.5 million. The Company estimates that it will incur costs of $1 million to complete construction of the apartment building. The apartment building will only transfer to Village Apartments once the construction of...
MULTIPLE-CHOICE questions E1-1.ABC Engineering use cost method to cart engineering use cost method to calculate the stage of completion of its construction act. Total estimated contract costs of their contract are $100 million. In the first year of their contract, ABC Engineering has incurred the following costs: Cost of purchase of raw materials worth $10 million ($5 million of which are unused by the year end) 2. Payment of salaries and wages of $5 million ($1 million of accrued salaries...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 2,110,000 3,736,000 4,154,000 Cash collections during the year 1,855,000 3,500,000 4,645,000 Westgate...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $2,550,000 $4,250,000 $ 1,870,000 Estimated costs to complete as of year-end 5,950,000 1,700,000 0 Billings during the year 2,050,000 4,750,000 3,200,000 Cash collections during the year 1,825,000 4,100,000 4,075,000 Westgate recognizes revenue over time according to percentage of...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,926,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000 1,840,000 2022 $2,300,000 2,660,000 2,860,000 2,800,000 5,060,000 5,360,000 Westgate recognizes revenue over time according to percentage of completion. Problem...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000 3,900,000 4,285,000 Westgate recognizes revenue over time according to...
In 2018, the West $10,000,000. gate Construction Company entered into a contract to construct a road for Santa Clara County for The road was completed in 2020. Information related to the contract is as follows: 2020 2018 2,542,000 $3,772,000 $2,074,600 5, 658,000 1,886,000 2,020,000 4,294,000 3,686,000 1,810,000 3,800,000 4,390,000 2019 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of...
Case 18-3 rev. Nailed It! Construction Nailed It! Construction (Nailed It! or the “Company"), an SEC registrant, is a construction company that manufactures commercial and residential buildings. On March 1, 20X1, the Company entered into an agreement with a customer, Village Apartments, to construct a residential apartment building for a fixed price of $1.5 million. The Company estimates that it will incur costs of $1 million to complete construction of the apartment building. The apartment building will only transfer to...