Question

er 11 End-of-Chapter Problems Question 2 of 4 Check My Work (1 remaining) Problem 11-11 Capital budgeting criteria: mutually
0 0
Add a comment Improve this question Transcribed image text
Answer #1

V.Project S, since NPV of s > NPV. of L.

working:

first let us know the present value of annuity factor relevant.

for 5 years @14%.

present value of annuity factor = [1-(1+r)^(-n)]/r

here,

r =14%=>0.14.

n=5

=>[1-(1.14)^(-5)]/0.14

=>3.43308071.

now,

project S project L
present value of cash inflows (4,500*3.43308071) (10,700*3.43308071) 15,448.86 36,733.96
less: cash outflows (11,000) (35,000)
NPV 4,448.86 1,733.96

since NPV of S is high, this project shall be selected.

Add a comment
Know the answer?
Add Answer to:
er 11 End-of-Chapter Problems Question 2 of 4 Check My Work (1 remaining) Problem 11-11 Capital...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • m Chapter 11 End-of-Chapter Problems signment: Brigham Chapter 11 End-of-Chapter Problems Assignment com 0.0096 Save Submit...

    m Chapter 11 End-of-Chapter Problems signment: Brigham Chapter 11 End-of-Chapter Problems Assignment com 0.0096 Save Submit Assignment for Grading uestions Question 1 of 4 Check My Work (1 remaining) Problem 11-11 Capital budgeting criteria: mutually exclusive projects and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L costs $30,500 and its expected cash flows would be $10,00 per year for 5 years. If both projects have a WACC of 149, which project would...

  • Problem 11-11 Capital budgeting criteria: mutually exclusive projects Project S costs $16,000 and its expected cash...

    Problem 11-11 Capital budgeting criteria: mutually exclusive projects Project S costs $16,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $35,500 and its expected cash flows would be $8,600 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. O I. Project S, since the NPVs > NPVL. O II. Both Projects S and L, since both projects...

  • Problem 11-11 Capital budgeting criteria: mutually exclusive projects Project S costs $15,000 and its expected cash...

    Problem 11-11 Capital budgeting criteria: mutually exclusive projects Project S costs $15,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $30,000 and its expected cash flows would be $9,600 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. O I. Project S, since the NPVS > NPVL. II. Both Projects and L, since both projects have NPV's...

  • 11-2: Net Present Value (NPV) Capital budgeting criteria: mutually exclusive projects Project Scosts $13,000 and its ex...

    11-2: Net Present Value (NPV) Capital budgeting criteria: mutually exclusive projects Project Scosts $13,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $36,500 and its expected cash flows would be $8,100 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. O I. Both Projects S and L, since both projects have IRR's > 0. O II. Project...

  • CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would...

    CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $29,500 and its expected cash flows would be $9,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Neither Project S nor L, since each...

  • Capital budgeting criteria: mutually exclusive projects Project S costs $12,000 and its expected cash flows would...

    Capital budgeting criteria: mutually exclusive projects Project S costs $12,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $49,000 and its expected cash flows would be $12,900 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. I. Project L, since the NPVL > NPVS. II. Both Projects S and L, since both projects have NPV's > 0....

  • Project S costs $11,000 and its expected cash flows would be $4,500 per year for 5...

    Project S costs $11,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $27,000 and its expected cash flows would be $7,500 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. I. Neither S or L, since each project's NPV < 0. II. Project L, since the NPVL > NPVS. III. Both Projects S and L, since both...

  • 2. Project S costs $10,000 and its expected cash flows would be $5,500 per year for...

    2. Project S costs $10,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $45,000 and its expected cash flows would be $10,250 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Both Projects S and L, since both projects have IRR's > 0....

  • 1) A project has annual cash flows of $5,000 for the next 10 years and then...

    1) A project has annual cash flows of $5,000 for the next 10 years and then $6,500 each year for the following 10 years. The IRR of this 20-year project is 12%. If the firm's WACC is 11%, what is the project's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. 2) Project S costs $12,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $25,000 and...

  • Project S requires an initial outlay at t = 0 of $13,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $33,000, and its expected cash flows would be $8,750 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Project L,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT