Question

Sheldon Company manufactures only one product and uses a standard cost system. During the past month, the manufacturing operations had the following variances: Direct labor rate variance = $29,000 Favorable. Direct labor efficiency variance = $48,000 Unfavorable. Sheldon allows 4.60 standard direct labor hours per unit produced, and its standard direct labor hourly rate is $46. During the month, the company used 23.00% more direct labor hours than the standard allowed. What was the standard labor cost of units produced for the month? $48,000 $29,000 $227,696 $256,696 $208,696 Ventura uses a just-in-time (JIT) manufacturing system for all of its materials, components, and products. The master budget of the company for June called for use of 10,400 square feet of materials, while the flexible budget for the actual output of the month had 10,000 square feet of materials at a standard cost of 59.10 per square foot. Company records show that the actual price paid for the materials used in June was $9.08 per square foot, and that the direct materials purchase-price variance for the month was $980. The materials flexible budegt variance for June was $354,420 unfavorable 353,920 unfavorable 354,900 unfavorable 5355,400 unfavorable $980 favorable

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution 1:

Standard rate of labor = $46 per hour

Let standard hours allowed = X hours

Actual direct labor hours = X * 123% = 1.23 X hours

Direct labor efficiency variance = $48,000 U

(SH - AH) * SR = -$48,000

(X - 1.23X) * $46 = -$48,000

X = 4536.86 hours

Standard direct labor cost = Standard hours allowed * standard rate = 4536.86 * $46 = $208,696

Hence last option is correct.

Solution 2:

Material purchase price variance = $980 F

(SP - AP) * AQ = $980

($9.10 - $9.08) * AQ = $980

AQ = 49000 Square foot

SQ for actual output = 10000 square feet

Material quantity variance = (SQ - AQ) * SR

= (10000 - 49000) * $9.10 = $354,900 U

Material flexible budget variance = Material price variance + Material quantity variance

= $980 F + $354,900 U = $353,920 U

Hence 2nd option is correct.

Add a comment
Know the answer?
Add Answer to:
Sheldon Company manufactures only one product and uses a standard cost system. During the past month,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Sheldon Company manufactures only one product and uses a standard cost system. During the past month,...

    Sheldon Company manufactures only one product and uses a standard cost system. During the past month, manufacturing operations for the company had the following variances: direct labor rate variance = $30,000 favorable; direct labor efficiency variance = $50,000 unfavorable. Sheldon allows 5 standard direct labor hours per unit produced, and its standard direct labor hourly pay rate is $50. During the month, the company used 25% more direct labor hours than the standard allowed for the output achieved. What was...

  • Best Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 145,000...

    Best Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 145,000 square feet of extruded vinyl purchased at $1.15 per square foot. Production required 460 direct labor hours that cost $13.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.20 per square foot. The labor standard was 0.025 direct labor hour per fender, at a standard cost of $12.50 per hour. Read the requirement....

  • All-Star Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 146,000...

    All-Star Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 146,000 square feet of extruded vinyl purchased at $1.10 per square foot. Production required 440 direct labor hours that cost $13.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.15 per square foot. The labor standard was 0.027 direct labor hour per fender, at a standard cost of $12.50 per hour. Read the requirement...

  • Deluxe Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 142,000...

    Deluxe Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 142,000 square feet of extruded vinyl purchased at $1.55 per square foot. Production required 440 direct labor hours that cost $16.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.60 per square foot. The labor standard was 0.025 direct labor hour per fender, at a standard cost of $15.50 per hour. Read the requirement....

  • Superior Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2016, using 143,000...

    Superior Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2016, using 143,000 square feet of extruded vinyl purchased at $1.30 per square foot. Production required 460 direct labor hours that cost $14.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.35 per square foot. The labor standard was 0.028 direct labor hour per fender, at a standard cost of $13.50 per hour. Compute the cost...

  • Best Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 145,000...

    Best Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 145,000 square feet of extruded vinyl purchased at $1.15 per square foot. Production required 460 direct labor hours that cost $13.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.20 per square foot. The labor standard was 0.025 direct labor hour per fender, at a standard cost of $12.50 per hour. Read the requirement....

  • Best Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 145,000...

    Best Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 145,000 square feet of extruded vinyl purchased at $1.15 per square foot. Production required 460 direct labor hours that cost $13.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.20 per square foot. The labor standard was 0.025 direct labor hour per fender, at a standard cost of $12.50 per hour. Read the requirement....

  • Pro Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 142,000...

    Pro Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 142,000 square feet of extruded vinyl purchased at $1.55 per square foot. Production required 440 direct labor hours that cost $12.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.60 per square foot. The labor standard was 0.024 direct labor hour per fender, at a standard cost of $11.50 per hour. boat fenders during...

  • Smith Recliners manufactures leather recliners and uses flexible budgeting and a standard cost system. Smith allocates...

    Smith Recliners manufactures leather recliners and uses flexible budgeting and a standard cost system. Smith allocates overhead based on yards of direct materials. The company's performance report includes the following selected data: (Click the icon to view the selected data.) Read the requirements Requirement 1. Prepare a flexible budget based on the actual number of recliners sold. (Round budget amounts per unit to the nearest cent.) 980 Smith Recliners Flexible Budget Budget Amounts per Unit Actual Units (Recliners) Sales Revenue...

  • Ander's Clothing manufactures embroidered jackets. The company uses a standard cost system to control manufacturing costs....

    Ander's Clothing manufactures embroidered jackets. The company uses a standard cost system to control manufacturing costs. The following data represent the standard unit cost of a​ jacket:   i Data Table $4.15 per sq. ft.) Direct materials 3.0 sq. ft x 12.45 Direct labor $9.70 per hour) ( 2,0 hours x 19.40 Manufacturing overhead: Variable 2.0 hours x $0.68 per hour) 1.36 4.40 5.76 2.0 hours x $2.20 per hour) Fixed 37.61 Total standard cost per jacket Fixed overhead in total...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT