Question

Consider a project to produce custom door moldings for GMC Acadia? cross-over vehicles, described in the...

Consider a project to produce custom door moldings for GMC Acadia? cross-over vehicles, described in the following table.

???????????????????????????????????????????????????????????????????

Activity

Activity Time

?(weeks)

Immediate? Predecessor(s)

START

0

minus?

A

2

START

B

6

START

C

4

B

D

2

A

E

7

?A, B

F

8

?D, E

G

4

?C, E

FINISH

0

?F, G

a. If you start the project? immediately, when will it be? finished?

The critical path is path B?E?Fand the project duration is 21 weeks.

b. You are interested in completing your project as soon as possible. You have only one option. Suppose you could assign Employee? A, currently assigned to Activity? G, to help Employee? B, currently assigned to Activity F. Each week that Employee A helps Employee B will result in Activity G increasing its time by one week and Activity F reducing its time by one week. How many weeks should Employee A work on Activity? F?

Employee A should work ? weeks on Activity F and the? project's duration will be reduced to ? weeks. (Enter your responses as integers.?)

* The ? is where the answer should go.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

AON:

Path and Duration:

ADF                      12
AEF                      17
AEG                      13
BEF                      21
BEG                      17
BCG                      14

Project time = 21 weeks (BEF)

b) Time for F is 8 weeks and time for G is 4 weeks, in order to have equal time of 6 weeks for both F & G, A will have to work for 2 week. The impact will be:

Old   New
ADF                      12                  10
AEF                      17                  15
AEG                      13                  15
BEF                      21                  19
BEG                      17                  19
BCG                      14                  16

So, new time for project completion will reduce to 19 weeks

So, A should work for 2 weeks and project's duration will be reduced to 19 weeks

Add a comment
Know the answer?
Add Answer to:
Consider a project to produce custom door moldings for GMC Acadia? cross-over vehicles, described in the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A project manager discovers that his team has neglected tocomplete the network diagram for the...

    A project manager discovers that his team has neglected to complete the network diagram for the project. the network diagram is shown below. however the project manager has some information available, specifically that each activity a-g, has a different duration between one and seven weeks. also the slack time for each of the activity is known as shown belowDuration (weeks): 1,2,3,4,5,6,7 Slack time (weeks): 0,0,0,1,1,3,7 A D E G B FINISH START C F Using the clues provided below, determine...

  • 1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 20...

    1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 200 | 1200 | 500 | 700 | 1200 | 800 | 1800 | 1500 | 400 (a) Construct the activity-on-node (AoN) network for the relations among the activities in the (b) Using the activity-on-node (Ao) network developed in part (a), determine the critical path and the minimum time required to complete the project. Develop the earliest start and finish times, the latest finish...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • A Question 11 The following table provides a list of activities in a project, along with...

    A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...

  • PLEASE ANSWER IN 30 MINUTES PM.53 Sun Oracle is launching a new computer component. The team...

    PLEASE ANSWER IN 30 MINUTES PM.53 Sun Oracle is launching a new computer component. The team has broken the project down into activities, with the following durations: Activity     Duration (weeks)     Immediate Predecessor(s)   A 20 - B 12 - C 15 A D 5 B E 6 D F 14 A,E G 5 F H 3 C,G What is the duration of the project?    weeks What is the latest start week for activity C?     What is the slack time for...

  • Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity...

    Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity on Node (AON) diagram to reflect the flow of these activities. Calculate the Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity. Calculate the slack for each activity. Identify all activities on the Critical Path. Use the data to calculate the probability the project will finish in 20 weeks (Hint: z-score). Activity A 8 с D E...

  • Question 13 The following table provides a list of activities in a project, along with their...

    Question 13 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 B 3 с 2 D A,B 5 E CD F D 4 G E 2 1 Determine the duration of the project. a. 13 weeks b. 12 weeks OC. 11 weeks d. 10 weeks e. 9 weeks Question 14 Assume that activity F has the following times: Early start time (ES) =...

  • Use a PERT network to establish the expected duration for the project described in the table...

    Use a PERT network to establish the expected duration for the project described in the table below:    (SHOW the PERT NETWORK) Activity Predecessors Duration a        m       b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400         600 D B, C 4 6 8 200                             600 E B, C 6 9 12 400 300 F C 4 6 14...

  • The following is a table of activities associated with a project at Rafay​ Ishfaq's software firm...

    The following is a table of activities associated with a project at Rafay​ Ishfaq's software firm in​ Chicago, their durations and what activities each must​ precede: Activity Duration​ (weeks) Precedes A​ (start) 2 ​B, C B 2 E C 6 F E 3 F F​ (end) 4 — This exercise contains only parts​ b, c, and d. ​b) Define the critical​ path, listing all critical activities in chronological order. Critical path activities are the activities that lie on the longest...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 nar Case Study A Table 1 below contains activities associated with a...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT