Answer: E. 5-4-3-2-1
Explanation:
As per Johnson's rule, the job with shortest processing time (SPT) need to be scheduled first. If SPT is for Machine 1(A) then it should be scheduled as early as possible. If SPT is for Machine 2 (B) then it should be scheduled as late as possible.
Job 5 - Processing time 1 for Machine A so it should be scheduled first - Sequence Order 1
Job 1 - Processing time 2 for Machine B so it should be scheduled last - Sequence Order 5
Job 4 - Processing time 2 for Machine B so it should be scheduled Second - Sequence Order 2
Job 3 - Processing time 3 for Machine A so it should be scheduled third - Sequence Order 3
Job 2 is the last job to be scheduled - Sequence Order 4
Sequence Order: 5 - 4 - 3 - 2 - 1
7. Five jobs must be scheduled. Each of the jobs must be processed on two machines...
1. Suppose you have four jobs that must be processed, with the following table giving their charac- teristics(all times in hours): Each job can be processed on any of three identical machines; to be Job 1 23 4 Processing time 21.524 | 2 | 0 | 0.5 | 1 Release time Processing time 5346 finished, a job must be processed for its entire processing time, but this processing time can be interrupted and even moved to a different machine if...
1. Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the longest processing time dispatching rule, in which order should the jobs be processed? All dates are specified as days from today. Job Processing Time (days) 4 Job due date (days) 7 A B 7 4 11 с 3 D 8 5 E 5 8 A) D, B, E, A, C B) C, A, E, B, D C) B, D, E, A,C...
ABC Enterprises has five jobs that must be scheduled for production at a work center. Below are the processing times and due dates for each job. Job Processing Time (in days) Due Date (days from today) 1 7 14 2 5 21 3 3 10 4 2 7 5 6 9 Schedule the jobs by sequencing them using the Earliest Due Date (EDD) priority rule. What is the average flow time? Show your Work and round your...
Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows: JOB OPERATION 1 (HOURS) OPERATION 2 (HOURS) A 4 8 B 10 5 C 3 11 D 14 14 E 6 1 F 7 12 a. Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job 1 ? 2 ? 3 ? 4 ? 5 ? 6 ? b. For the schedule developed...
Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the shortest processing time dispatching rule, in which order should the jobs be processed? Processing Time (days) Job due date (days) Job A B 4 C 11 D 8 5 8 O A. D, A, E, B, C О в. D. В. Е. А. С О С. С. А, Е, в.р O D. C, E, A, B, D O E. B, D, A,...
Suppose we have five jobs to be processed on a single machine. The processing times and the due dates of the jobs are shown below Job 2 3 4 Processing Time 2 6 5 4 Due Date 10 11 15 4 13 Find a schedule that minimizes the number of tardy jobs
Problem #1 Five jobs are to be processed through a single machine. The processing times and due dates are given here. Assume all released dates are zero. Job 1 2 3 4 5 Processing time 3 6 5 4 2 Due date 4 8 12 21 15 In each of the following cases determine the sequence in which she should perform and compute Mean Flow Time, Average Tardiness and the number of tardy jobs. A) Shortest Processing Time B) Early...
Determine the processing sequence for the five jobs to be processed on the two work centers shown below using Johnson's Rule. What is the total throughput time. Show your work. Job Center1 Center2 A 6 7 B 10 9 C 12 8 D 5 11 E 13 4
n 10 The following set of jobs must be processed ed serially through a two-step system. The times at out of each process are in hours. If Johnson's Rule is used to sequence the jobs then Job A would complete processing on operation 2 at Job Process Process 2 A 12 9 B 11 C 7 6 D 10 14 E 5 8 Select one: A. hour 38. LO A 12 8 11 C 7 6 D 10 14 E...
3. Consider the following seven-job problem. Each job must be processed by two ma chines A and B, first on machine A and then machine B. The operation processing times at machine A and B are as follows: Job i 1 2 3 5 6 Processing time on machine A (a9 8 5 10 6 8 5 Processing time on machine B (b) 6 5 7912 11 4 a. Suppose jobs arrived in their natural order (i.e, job before job...