Question

Problem 5-12 1 1 The following table represents a plan for a project: PREDECESSOR TIMES (DAYS) JOB NO. JOB(S) m b 1 1 3 8 2 3
e. What is the probability that the project will take more than 35 days to complete? (Round your answer to 2 decimal places.)
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1-4-7-10-11

33

No

No

No

0.23

Activity Optimistic Likely Pessimistic Mean Std dev Variance
A 1 3 8 3.5 1.166667 1.361111
B 3 3 6 3.5 0.5 0.25
C 3 6 12 6.5 1.5 2.25
D 5 7 12 7.5 1.166667 1.361111
E 3 6 12 6.5 1.5 2.25
F 1 2 3 2 0.333333 0.111111
G 2 9 10 8 1.333333 1.777778
H 2 4 6 4 0.666667 0.444444
I 2 4 12 5 1.666667 2.777778
J 4 4 7 4.5 0.5 0.25
K 2 11 11 9.5 1.5 2.25
Precedences
Activity Time Pred 1 Pred 2
A 3.5
B 3.5 A
C 6.5 A
D 7.5 A
E 6.5 B
F 2 C
G 8 D
H 4 E F
I 5 H
J 4.5 G
K 9.5 I J
Results
Activity Early Start Early Finish Late Start Late Finish Slack Variance Critical Variance
A 0 3.5 0 3.5 0 1 1.361111 1.361111
B 3.5 7 4.5 8 1 2 0.25
C 3.5 10 6 12.5 2.5 3 2.25
D 3.5 11 3.5 11 0 4 1.361111 1.361111
E 7 13.5 8 14.5 1 5 2.25
F 10 12 12.5 14.5 2.5 6 0.111111
G 11 19 11 19 0 7 1.777778 1.777778
H 13.5 17.5 14.5 18.5 1 8 0.444444
I 17.5 22.5 18.5 23.5 1 9 2.777778
J 19 23.5 19 23.5 0 10
Know the answer?
Add Answer to:
Problem 5-12 1 1 The following table represents a plan for a project: PREDECESSOR TIMES (DAYS)...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT