Question

Inputs for the plan cost management process include(s). O project charter O expert judgement O data analysis all of the above
When estimating activity duration factors to consider include(s) a. number of resources Ob.advances in technology O c. motiva
0 0
Add a comment Improve this question Transcribed image text
Answer #1

a- project charter

Plan cost management process doesn't include data analysis, expert judgement but it includes project charter, project management plan, organizational process assets and enterprise environmental factors.

a. Number of resources

It includes estimation of work periods required for completing with number of resources.

Add a comment
Know the answer?
Add Answer to:
Inputs for the plan cost management process include(s). O project charter O expert judgement O data...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT