Question

Saved 7 Dolls are the flow unit in a process with two resources. The capacities of the resources are 15 and 0.99 dolls per mi
Dinners are the flow unit in a process with two sequential resources. The processing times for the resources are 0 22 and 0.1
Saved Lenses are assembled in a process with two resources. The processing times for the resources are 2 and 3.3 hours. Instr
0 0
Add a comment Improve this question Transcribed image text
Answer #1

7. Utilization percentage of second resource = 0.99 dolls / 1.1 dolls

= 90%

Therefore utilization percentage or second resource in meeting the demand of dolls per minute is 90%

8. Utilization percentage of first resource = (0.22 + 0.16) * 3.4 / 3.4

= 38%

9. Time taken for 15 lenses to be assembled on a work paced line is

( 2 hours + 3.3 hours ) * 15 lenses = 79.5 hours.

Add a comment
Know the answer?
Add Answer to:
Saved 7 Dolls are the flow unit in a process with two resources. The capacities of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Lenses are assembled in a process with two resources. The processing times for the resources are...

    Lenses are assembled in a process with two resources. The processing times for the resources are 0.91 and 0.45 hours. o Instruction: Assume the process starts empty and round your answer to two decimal places How long does it take 16 lenses to be assembled on a machine-paced line (in hours)? hours 03.10 Patients are treated in a process with two resources. The processing times for the resources are 0.91 and 0.63 hours. Instruction Assume the process starts empty and...

  • PA 3-3 Consider a process consisting of three... Consider a process consisting of three resources. Assume...

    PA 3-3 Consider a process consisting of three... Consider a process consisting of three resources. Assume there exists unlimited demand for the product. Resource 1 has a processing time of 2 minutes per unit. Resource 2 has a processing time of 6 minutes per unit. Resource 3 has a processing time of 4 minutes per unit. Resource 1 Resource2 Resource 3 All three resources are staffed by one worker. The flow diagram is shown above. Round "Capacity of resource" to...

  • OVERWORKED INC has 3 resources (Resource A, Resource B and Resource C) in its production process....

    OVERWORKED INC has 3 resources (Resource A, Resource B and Resource C) in its production process. The production process involves 3 products (Product A, Product B and Product C) being processed through these 3 resources. Currently, there is demand for 800 units of Product A, 1,200 units of Product B and 200 units of Product C per day. The processing times for each product at different resource levels is given in the table below: Product A Product B Product C...

  • Consider a process consisting of five resources that are operated eight hours per day. The process...

    Consider a process consisting of five resources that are operated eight hours per day. The process works on three different products, A, B, and C; Resource Number of Workers Processing Time for A (Min./Unit) Processing Time for B (Min./Unit) Processing Time for C (Min./Unit) 1 2 5 5 5 2 2 3 4 5 3 1 15 0 0 4 1 0 3 3 5 2 6 6 6 Demand for the three different products is as follows: product A,...

  • A production process consists of two resources. One resource consists of one machine that is used...

    A production process consists of two resources. One resource consists of one machine that is used to make 3 different parts. Those parts are needed to make the one product. The parts are labeled, A, B and C. To make a product requires 3 A parts, 2 B parts and 1 C part. Switching production from one type of part to another requires 2.5 minutes. Once setup to make a part, the machine works at the rate of 8 A...

  • An architectural firm has three types of clients: "G" = "green/new": "EC" = experienced with a...

    An architectural firm has three types of clients: "G" = "green/new": "EC" = experienced with a complex project, and "ES" = experienced with a simple project. The process flow for these types of projects and the staffing of each of the stages are provided below in the diagram: G- Needs assessment: 2 planners Design: 5 architects Structural engineering: 2 engineers The processing times for the different types of jobs (in days) are listed in the following table. Processing time (days)...

  • 1. The process is performed by several resources. 2. Resources are shared across assembly lines (i.e.,...

    1. The process is performed by several resources. 2. Resources are shared across assembly lines (i.e., workers must multitask and perform multiple activities for every flow unit.) 3. The resource that limits hourly production is not the same resource that limits the process lead-time. From 2002 to 2009, Honda’s 1800cc cruiser-style motorcycle, the VTX1800, was assembled in Marysville, Ohio from four major subassemblies. The following is a simplified explanation of the assembly process. All resources are indicated in bold.   •...

  • Consider the following production process for manufacturing biscuits. The first step of the process is mixing...

    Consider the following production process for manufacturing biscuits. The first step of the process is mixing where all of the ingredients are combined in the correct proportion to form dough. In the next step of the process, the dough is formed into sheets and cut into pieces in preparation for baking. The cut dough is then baked into biscuits and subsequently must be cooled. The final step of the process is packaging the biscuits for the consumer. The following table...

  • PART I: Multiple Choice Write all answers to the following questions. No partial credit available. Consumption...

    PART I: Multiple Choice Write all answers to the following questions. No partial credit available. Consumption utility is composed of price and convenience. True or False? A firm reduces inefficiencies by making trade-offs. True or False? A firm can increase its profitability by: A. increasing costs and reducing price. B. moving away from the efficient frontier. C. increasing inefficiencies. D. reducing inefficiencies. Operations comes from the Latin word "opus," which means: A. activity. B. helping people. C. improvement. D. work....

  • Two-step Process Utilization: A two- used to finish a product: painting and drying. There are 5 workers and each one ta...

    Two-step Process Utilization: A two- used to finish a product: painting and drying. There are 5 workers and each one takes an average of 60 minutes to paint each unit. Drying takes place in an oven that can hold up to 100 units and it takes 5 minutes to load each unit. Once all the units are loaded into the oven, it takes 6 hours to dry each load. Assume that the process is capacity constrained (so the demand rate...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT