OVERWORKED INC has 3 resources (Resource A, Resource B and Resource C) in its production process....

OVERWORKED INC has 3 resources (Resource A, Resource B and Resource C) in its production process. The production process involves 3 products (Product A, Product B and Product C) being processed through these 3 resources. Currently, there is demand for 800 units of Product A, 1,200 units of Product B and 200 units of Product C per day. The processing times for each product at different resource levels is given in the table below:

Product A

Product B

Product C

Resource A

0.72 minutes

0.72 minutes

Resource B

1.584 minutes

1.584 minutes

Resource C

1.584 minutes

1.584 minutes

Product C is not processed at Resource A. Product B is not processed at Resource B and Resource C.

Assume that each work day has 24 hours.

a) Find the implied utilization for Resource A.

b) Find the implied utilization for Resource B.

c) Find the implied utilization for Resource C.

d) What is the highest implied utilization.

e) Find the maximum daily flow rate of Product A

f) Find the maximum daily flow rate of Product B

g) Find the maximum daily flow rate of Product C

h) Find the actual daily flow rate of Product A

i) Find the actual daily flow rate of Product B

j) Find the actual daily flow rate of Product C

k) Find the daily process capacity

Assuming that demand for each of the 3 products (Product A, Product B and Product C) changes to 100 units per day, answer the following questions:

l) Find the maximum daily flow rate of Product A

m) Find the maximum daily flow rate of Product B

n) Find the maximum daily flow rate of Product C

o) Find the actual daily flow rate of Product A

p) Find the actual daily flow rate of Product B

q) Find the actual daily flow rate of Product C


0 0
Add a comment Improve this question Transcribed image text
Answer #1

(Note: As per an organizational policy of Chegg for the subject matter experts, for the questions involving multiple subparts, we can answer only up to the maximum of the first four subparts (Here, a to d) out of the multiple subparts, unless the user has specified particular subpart/s to be answered. Kindly, do not down-vote for not answering the remaining subparts.)

Solution:

We will find the implied utilization rates (%) for all of the five resources as mentioned in the below table:

(Rounded to 2 decimal places)

Calculation Steps:

Step 1: Col 6 = Available Time (Min / Day) = Col 1 X Col 2

Step 2: Col 7 = Capacity Required for Product A (Min / Day) = Demand (A) X Col 3 = 800 X Col 3

Step 3: Col 8 = Capacity Required for Product B (Min / Day) = Demand (B) X Col 4 = 1200 X Col 4

Step 4: Col 9 = Capacity Required for Product C (Min / Day) = Demand (C) X Col 5 = 200 X Col 5

Step 5: Col 10 = Workload (Min) = Col 7 + Col 8 + Col 9

Step 6: Col 11 = Implied Utilization (%) = ( Col 10 / Col 6 ) X 100

Thus,

Answer a: The implied utilization for Resource A = 100 %

Answer b: The implied utilization for Resource B = 110 %

Answer c: The implied utilization for Resource C = 110 %

Answer d: As per the above calculations, we conclude that the highest implied utilization = 110 %

(Kindly raise an upvote for this answer, if you found it useful)

Add a comment
Know the answer?
Add Answer to:
OVERWORKED INC has 3 resources (Resource A, Resource B and Resource C) in its production process....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • HEAVYLOAD INC has 3 resources (Resource A, Resource B and Resource C) in its production process....

    HEAVYLOAD INC has 3 resources (Resource A, Resource B and Resource C) in its production process. The production process involves 3 products (Product A, Product B and Product C) being processed through these 3 resources. Currently, there is demand for 700 units of Product A, 1,200 units of Product B and 200 units of Product C per hour. The following bullets provide information about each resource: At Resource A, the processing time for Product A is 14.112 seconds and for...

  • Consider a process consisting of five resources that are operated eight hours per day. The process...

    Consider a process consisting of five resources that are operated eight hours per day. The process works on three different products, A, B, and C; Resource Number of Workers Processing Time for A (Min./Unit) Processing Time for B (Min./Unit) Processing Time for C (Min./Unit) 1 2 5 5 5 2 2 3 4 5 3 1 15 0 0 4 1 0 3 3 5 2 6 6 6 Demand for the three different products is as follows: product A,...

  • PA 3-3 Consider a process consisting of three... Consider a process consisting of three resources. Assume...

    PA 3-3 Consider a process consisting of three... Consider a process consisting of three resources. Assume there exists unlimited demand for the product. Resource 1 has a processing time of 2 minutes per unit. Resource 2 has a processing time of 6 minutes per unit. Resource 3 has a processing time of 4 minutes per unit. Resource 1 Resource2 Resource 3 All three resources are staffed by one worker. The flow diagram is shown above. Round "Capacity of resource" to...

  • A production process consists of two resources. One resource consists of one machine that is used...

    A production process consists of two resources. One resource consists of one machine that is used to make 3 different parts. Those parts are needed to make the one product. The parts are labeled, A, B and C. To make a product requires 3 A parts, 2 B parts and 1 C part. Switching production from one type of part to another requires 2.5 minutes. Once setup to make a part, the machine works at the rate of 8 A...

  • An architectural firm has three types of clients: "G" = "green/new": "EC" = experienced with a...

    An architectural firm has three types of clients: "G" = "green/new": "EC" = experienced with a complex project, and "ES" = experienced with a simple project. The process flow for these types of projects and the staffing of each of the stages are provided below in the diagram: G- Needs assessment: 2 planners Design: 5 architects Structural engineering: 2 engineers The processing times for the different types of jobs (in days) are listed in the following table. Processing time (days)...

  • (Process with Rework) Consider the following three-stage production process of glass ceramics, wh...

    Matching supply with Demand (3rd Edition) - Question 10.2 (Process with Rework) Consider the following three-stage production process of glass ceramics, which is operated as a worker-paced line. Q10.2 Components 6 min./unit 5 min./unit min. /unit Finished Units Rework The process is experiencing severe quality problems related to insufficiently trained work- ers. Specifically, 20 percent of the parts going through operation 1 are badly processed by the operator. Rather than scrapping the unit, it is moved to a highly skilled...

  • 2. Four Step Process with Rework and Scrap - from module 5 slides Consider the following...

    2. Four Step Process with Rework and Scrap - from module 5 slides Consider the following four step assembly operation with quality problems. All resources are staffed with one operator. The first resource has a processing time of 4 minutes per unit The second resource has a processing time of 3 minutes per unit. This process suffers from a high yield loss and 50% of all products have to be scrapped after this step. The third resource also suffers from...

  • 1. What may a resource calendar not provide? a. Duration of resource availability b. Which resources...

    1. What may a resource calendar not provide? a. Duration of resource availability b. Which resources are available during a planned activity c. Estimation of resource expenses d. Capabilities and skills of human resources 2. Which analysis can result in preparing contingency and response plans to overcome or mitigate the impact of an unexpected situation? a. Critical Chain Method b. What if Analysis c. Critical Path Method d. Fast Tracking 3. The Control Schedule process involves the following, except? a....

  • c. What will be the new bottleneck in the process? d . How many customers a day will not be served? Which customers are...

    c. What will be the new bottleneck in the process? d . How many customers a day will not be served? Which customers are going to wait? Explain your reasoning!    (Car Wash Supply Process) CC Car Wash specializes in car cleaning services. The ser- vices offered by the company, the exact service time, and the resources needed for each of them are described in the table following: Resource Used Service Description Processing Time A. Wash Exterior car washing and drying...

  • CSUCI Company produces and sells four products; A, B, C, D. The following data relate to...

    CSUCI Company produces and sells four products; A, B, C, D. The following data relate to its four products: A B D 180 120 90 150 $70 $50 Daily demand in units Selling price per unit Variable costs per unit Direct material cost per unit Labor time in minutes per unit $26 $30 $10 $80 $36 $16 $100 $49 $14 $12 N 5 4 3 There are a total of 1,022 minutes available per day. Total fixed costs are $3,200...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT