Question

2. Table below shows the original time and cost estimate for Activity A and the probability and impacts of 2 identified risks

0 0
Add a comment Improve this question Transcribed image text
Answer #1


Activity Estimating Form Activity A Work Package XYZ Time in days Cost in $ Initial estimate (before risk analysis) 50 640000Expected monetary va etony valves I cost Time Probability of doº 80% Impact Time ) Cost 30 180000 adox 180000 100 36,000 15New Rating Rial - Risk Response pleuning : EMN Timel cost I probability Impact of a day days) e 18 TO ni 8000 do 160000 20000

Add a comment
Know the answer?
Add Answer to:
2. Table below shows the original time and cost estimate for Activity A and the probability...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A watch list is an output of which risk management process? Perform Quantitative Risk Analysis Implement...

    A watch list is an output of which risk management process? Perform Quantitative Risk Analysis Implement Risk Responses Perform Qualitative Risk Analysis Plan Risk Responses A project has the following risks: 20 percent probability of a 14-day delay in the receipt of customer requirements; 10 percent probability of a 21 -day delay in the procurement process; 50 percent probability the integration will take 14 days longer than planned. What is the expected value of these events? 49 days Seven days...

  • QUESTION 42 The Perform Qualitative Risk Analysis process assesses the priority of identified risks using all of the following EXCEPT O Relative probability or likelihood of occurrence of identified...

    QUESTION 42 The Perform Qualitative Risk Analysis process assesses the priority of identified risks using all of the following EXCEPT O Relative probability or likelihood of occurrence of identified risks O Impact on project objectives if the identified risks occur OA mathematical technique, such as the expected monetary value (EMV), to create the impression of precision and accuracy O The organization's risk tolerance associated with the project constraints of cost, schedule, scope, and quality QUESTION 42 The Perform Qualitative Risk...

  • B. Risk strategy C. Respanses to individual risks D. Risk categories. 192. The Perform Qualitative Risk Analysis process assesses the priority of identified risks using all af the following EXCEPT A....

    B. Risk strategy C. Respanses to individual risks D. Risk categories. 192. The Perform Qualitative Risk Analysis process assesses the priority of identified risks using all af the following EXCEPT A. B. C. Relative probability or likelihoad of occurrence of identified risks. Impact an praject abjectives if the identified risks accur A mathematical technique, such as the expected monetary value (EMV), to create the impression of precision and accuracy. The organization's risk tolerance assaciated with the praject constraints of cast,...

  • Qualitative risks are typically categorized by a group of experts to determine the probability and the...

    Qualitative risks are typically categorized by a group of experts to determine the probability and the impact to project objectives. In the example below, consider the next steps that should be taken as project manager to assemble a group of experts to participate. Who would you select and why? Identifying risk is a critical part of project management. One of the main factors in a successful project execution is correctly identifying risk so that risks can be minimized or mitigated...

  • Problem 9-17 The Porsche Shop, founded in 1985 by Dale Jensen, specializes in the restoration of...

    Problem 9-17 The Porsche Shop, founded in 1985 by Dale Jensen, specializes in the restoration of vintage Porsche automobiles. One of Jensen's regular customers asked him to prepare an estimate for the restoration of a 1964 model 356SC Porsche. To estimate the time and cost to perform such a restoration, Jensen broke the restoration process into four separate activities: disassembly and initial preparation work (A), body restoration (B), engine restoration (C), and final assembly (D). Once activity A has been...

  • 1. When finding the approximate probability of project duration, it is necessary to know which of...

    1. When finding the approximate probability of project duration, it is necessary to know which of following? a. The mean and variance of each activity b. The mean of each activity on the CP c. The sd of only the activities on the CP d. Each activity's probability of completion e. The distribution of activity times 2. The sd of a path is computed as: a. the sum of the sd of all activities on the path b. the square...

  • question 3.12 Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in...

    question 3.12 Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in hours) Predecesur Planning Find location determine resource requirements Purchasing Requisition of lumber and sand Excavation Planning Dig and grade Sawing Planning Saw lumber inte appropriate sizes Placement Purchasing Position lumber in comect locations Sawing. c om Assembly Nail lamber together Placement Tafill Put sand in and under the equipment Ambly Outfill Put dirt a nd the equipment Assembly Decoration Put grass all over the...

  • Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days....

    Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days. Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash Cost A None 4 3 202 383 B A 5 3 303 601 C A 1 1 190 285 D B and C 5 4 509 543 E D 4 2 502 898 What is the total time of this project? Please give your answer in days What are the total normal cost of...

  • Consider the office renovation project data in the following table. A "zero" time estimate means that...

    Consider the office renovation project data in the following table. A "zero" time estimate means that the activity could take a very small amount of time and should be treated as a numeric zero in the analysis. a. Based on the critical path, find the probability of completing the office renovation project by 38 days. Refer to the standard normal table. (Make sure to round all intermediate calculations for te and variance to two decimal places.) Time Estimates (days) Activity...

  • Could you help with these questions please Activity Two: A Frequency Table Then Probability Table appliance...

    Could you help with these questions please Activity Two: A Frequency Table Then Probability Table appliance store owner is interested in the relationship between price (retail or sales) the customer's decision to purchase an extended warranty or not. The owner defines the following events: A Item is purchased at retail price; C Extended warranty is purchased; B-ltem is purchased at sale price; D-Extended warranty is not purchased hen examining 2000 invoices he determined the following: 420 purchases made at the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT