Correct Answer:
Week 7
Working note:
D-A-P = 3+2+1 = 6 weeks
K-A-P = 2+2+1 = 5 weeks
K-B-P = 2+ 1+ 1 = 4 weeks
K-C-P = 2+ 3+ 1 = 6 weeks
Here, the longest time is 6 week and it is the critical time. So, it will take 6 week to complete the order. Since, the shipment will start from week 13.
So, latest time = 13-6 = week 7
Question 7 071 pts Using the following information, lead times are one week for items P...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 8 B(2), J(3) C 3 12 G(2), B(2) K 3 17 H(4), B(2) B 2 32 J 3 27 G 3 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. ts Direct C End rded B(2), 3(3) G(2), B(2) H(4), B(2) 12 21 32 103 a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan.) 405 0 Additional units b. An order for the end item is scheduled to be shipped...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand L12), c(1),x(3) B(2), 33) G(2), 8(2) H(4), B(2) 13 16 21 29 a. f 43 unts of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan) Additional units b. An order for the end item is scheduled to be shipped at the start of week...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand on Hand Iten End Direct Components L(2), C(1), K(3) B(2), (3) G(2), B(2) H(4), B(2) a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan.) Additional units C b. An order for the end item is scheduled to be shipped at...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 12 B(2), J(3) C 4 15 G(2), B(2) K 4 21 H(4), B(2) B 3 32 J 4 27 G 4 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item End B C D E F G H LT (wk) 2 2 1 1 1 2 1 2 Amount on hand 0 11 8 26 12 30 7 0 A. If 21 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.)...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. E Item LT (wk) Amount on hand End 2 0 B 2 11 C 3 8 D 3 26 1 F 2. 31 G 1 3 INO 12 End Item B (2) с D (3) E (2) F(3) G (2) E (2) H (4) E (2) a. If 19 units of the end item are to be assembled, how many additional units...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. G Item LT (wk) Amount on hand End 2 0 B 2 11 C 1 8 D 1 26 E 1 12 F 2 30 1 H 2 0 7 End Item B (2) C D (3) E (2) F(3) G (2) E (2) H (4) E (2) a. If 21 units of the end item are to be assembled, how many...
The following table lists the components needed to assemble an
end item, lead times, and quantities on hand.
Item
End
B
C
D
E
F
G
H
LT (wk)
2
2
2
2
1
2
1
2
Amount on hand
0
11
8
26
12
28
6
0
a. If 20 units of the end item are to be
assembled, how many additional units of E are needed?
(Hint: You don't need to develop an MRP plan to determine
this.)...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. End H Item LT (W) Amount on hand 1 B 3 10 с 4 9 D 4 25 E 2 11 F 1 26 G 2 7 1 0 o End Item B12) с D (3) E (2) F (3) G 21 E (2) H14) E (2) a. If 24 units of the end item are to be assembled, how many additional...