Question

project management

sad.png

A project contains the following activities and relations.

a) Construct the associated project network.

b) Find earliest and latest occurence time of each activity.

c) Find the critical path of the project.

d) Construct time schedule of the project.

e) Compute total floats and free floats for the noncritical activities of the network and

discuss their use in finalizing a schedule for the project (give at least one example).

0 0

> very urgent please solve the questions one by one

sasha195456. Sat, Apr 24, 2021 8:36 AM

> please do not upload old answer

sasha195456. Sat, Apr 24, 2021 8:42 AM

Add a comment Improve this question Transcribed image text
Answer #1

Answer [A] Project Network

1 受日) o) 2.

Answer [C]

Critical Path = A-C-D-F-G-H-J-L-N-S-T

Project Duration = 38

Answer [B]

Free float = subtracting the early finish (EF) of the activity from the early start (ES) of the successor activity.

Total Float = Late finish - Early finish Or Early finish - early start

Activity time

Early Start

Early Finish

Late Start

Late Finish

Total Float

Free Float

A

1

0

1

0

1

0

0

B

2

0

2

10

12

10

0

C

1

1

2

1

2

0

0

D

2

2

4

2

4

0

0

E

6

2

8

12

18

10

10

F

10

4

14

4

14

0

0

G

3

14

17

14

17

0

0

H

1

17

18

17

18

0

0

I

1

14

15

27

28

13

0

J

5

18

23

18

23

0

0

K

2

15

17

36

38

21

0

L

1

23

24

23

24

0

0

M

2

14

16

22

24

8

8

N

4

24

28

24

28

0

0

O

2

23

25

27

29

4

0

P

2

25

27

29

31

4

0

Q

1

27

28

37

38

10

0

R

7

27

34

31

38

4

0

S

7

28

35

28

35

0

0

T

3

35

38

35

38

0

0

Answer [D]: Time Schedule

2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 Time

Add a comment
Know the answer?
Add Answer to:
project management
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • F: The activities in the following table describe the construction of a new house. Activity Predecessor(s)...

    F: The activities in the following table describe the construction of a new house. Activity Predecessor(s) Duration(days) A: Clear site B: Bring utilities to site Excavate D: Pour foundation E: Outside plumbing B, C Frame house D G: Do electric wiring H: Lay floor Lay roof F Inside plumbing E, H K: Shingling Outside sheathing insulation F.J M: Install windows and outside doors F Do brick work L, M 0: Insulate walls and ceiling GJ Cover walls and ceiling 0...

  • for each problem I have this setup so far. I need help on each part and im not too sure if I am on the right track for each question on the picture. this chapter is on project management for statisti...

    for each problem I have this setup so far. I need help on each part and im not too sure if I am on the right track for each question on the picture. this chapter is on project management for statistics 1. A project is shown by the following network. The durations of activities (in weeks) are indicated on the arrows. a. Identify all of the paths, compute the length of each, identify the critical path and the b. Determine...

  • 1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 20...

    1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 200 | 1200 | 500 | 700 | 1200 | 800 | 1800 | 1500 | 400 (a) Construct the activity-on-node (AoN) network for the relations among the activities in the (b) Using the activity-on-node (Ao) network developed in part (a), determine the critical path and the minimum time required to complete the project. Develop the earliest start and finish times, the latest finish...

  • The following is a table of activities associated with a project at Rafay​ Ishfaq's software firm...

    The following is a table of activities associated with a project at Rafay​ Ishfaq's software firm in​ Chicago, their durations and what activities each must​ precede: Activity Duration​ (weeks) Precedes A​ (start) 2 ​B, C B 2 E C 6 F E 3 F F​ (end) 4 — This exercise contains only parts​ b, c, and d. ​b) Define the critical​ path, listing all critical activities in chronological order. Critical path activities are the activities that lie on the longest...

  • .8-6. A project consists of 12 activities, represented by the project network below, where number by each arc repres...

    .8-6. A project consists of 12 activities, represented by the project network below, where number by each arc represents the duration (in days) of the associated activity 4 12 4 12 10 a) Find the earliest time, latest time, and slack for each event as well as the slack for each activity. Also identify the critical path. (b) The project has been scheduled to be completed in the minimum possible time.If all previous activities have begun as early as possible...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • 1. The activities needed for a new project your company is undertaking are listed in the...

    1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...

  • 11. In CPM/PERT, an activity that is on the critical path A. has equal values for...

    11. In CPM/PERT, an activity that is on the critical path A. has equal values for "Latest Start" and "Earliest Start" ( LS = ES ) B. has equal values for "Latest Finish" and "Earliest Finish" ( LF = EF ) C. is used in calculating total project duration D. has slack equal to zero E. all of the above 12. In CPM/PERT, the critical path through the network A. will require the most time of any path B. will...

  • Given is a PERT project network diagram as shown below: Start End ctivity |StarA KEnd 15...

    Given is a PERT project network diagram as shown below: Start End ctivity |StarA KEnd 15 me 10 13 12 20 a) The Project Completion time = b) The Earliest Start time, ES, of Activity F- c) The Earliest Start time, ES, of Activity K = d) The Latest Start time, LS, of Activity. E = e) The non-critical activities are comma, no space) (ex. type in critical activities as ABCD, no

  • 2) The following tasks been assigned for a project following the steps needed to develop a...

    2) The following tasks been assigned for a project following the steps needed to develop a project network. Show al necessary steps and graphical representations. Find: 1 Critical Path for this project 2) Total free slack times for each activity 3) Total completion Time 4) The latest time that the activity D must be started to complete the project by day 54 Activity Predecessor Activity Time A |None None M,L.K 3) How would you calculate the duration of an activity...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT