Question
please answer


3. In a pure construction management approach the construction manager usually guarantees the overall price of the project _T
0 0
Add a comment Improve this question Transcribed image text
Answer #1

3) Solution: False

Explanation: In a pure construction management approach, the selected subcontractor would be signing the contract with the owner

 

4) Solution: True

Explanation: The costs over the guaranteed maximum price will be borne by the contractor

 

5) Solution: True

Explanation: The unit-price contract gives an owner with price competition and also permits for a rise or falls in actual versus estimated quantities

 

6) Solution: True

Explanation: While assessing the risks associated to a project, it must consider the owner organization and the way making of decision occurs

As per policy we have to answer first four parts

Add a comment
Know the answer?
Add Answer to:
please answer 3. In a pure construction management approach the construction manager usually guarantees the overall...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 4. The Owner's ability to influence design and cost is highest at the construction phase. a....

    4. The Owner's ability to influence design and cost is highest at the construction phase. a. True b. False 5. The conceptual estimate is useful in the schematic design phase when design details are not available. a. True b. False 6. A Cost-Plus contract is considered a reimbursable type of contract. c. True d. False 7. An advantage of a Lump Sum Contract is that the owner assumes the risk of construction cost. e. True f. False 8. A Design-Bid-Build...

  • 7 In the work breakdown structure for a construction project: A. The different levels of detail...

    7 In the work breakdown structure for a construction project: A. The different levels of detail represents the logical hierarchical decomposition of the B. The smallest element in the WBS is the activity C. The project elements at various levels of the WBS relate to the contractor's project organizational structure, which defines the different responsibility levels D. All the above Negotiated cost-plus type of contracts is best used when: A. The risk is high B. No variations are expected C....

  • Match the type of schedule listed with the description following. Schedule types may be used more than once a. Activity on arrow (AOA) b. Activity on node (AON) C. Matrix d. Bar chart 40 Grap...

    Match the type of schedule listed with the description following. Schedule types may be used more than once a. Activity on arrow (AOA) b. Activity on node (AON) C. Matrix d. Bar chart 40 Graphically the simplest Graphic style makes it adaptable to high-rise construction 42.Utilizes i-j notation 43 Could also be termed precedent notation Would be used for a summary report to the owner Questions 45-49 Match the terms listed with their description. Terms may be used only once...

  • I am in my Construction Management and trying to figure out some questions. Pretty much all...

    I am in my Construction Management and trying to figure out some questions. Pretty much all of them. Midler EA POCOU CIVL 142 Construction Specifications Page 8 49. The term "Bidder" is best defined as a. A Contractor who is interested in doing the work b. A Contractor who is qualified to do the work c. The individual or entity who submits a Bid directly to the Owner d. An individual who is awarded a contract e. All of the...

  • I am in my Construction Management and trying to figure out some questions. Pretty much all...

    I am in my Construction Management and trying to figure out some questions. Pretty much all of them. 2. The purpose of the "Advertisement for Bids" is to a. Inform prospective bidders b. Supplement the Bid Form c. Determine contract responsibilities d. Obtain adequate competition e. a&d 3. Which of the following IS NOT a way a third party may acquire rights under a contract a Assignment b. Succession in office c. Receivership d. Inheritance e Arbitrary allocation 4. Which...

  • Dear Sir/Madam, could you answer all the question below. I appreciate if u can answer all....

    Dear Sir/Madam, could you answer all the question below. I appreciate if u can answer all. Thank You :) A (Bad?) Day in the Life of a Project Manager Frank Mills is a Site Agent for McMurray Concrete Ltd which specialises in building concrete structures on industrial sites. His present site is a large chemical plant, Agrochem Ltd that manufactures farm fertilisers. The project he is currently working on is part of a large contract being managed by Design Solutions...

  • Please help writing a well structured document using the below Agile Runbook - Our Overall Delivery Process How do we initiate a Project? Any project is a response to a pain point or desire expresse...

    Please help writing a well structured document using the below Agile Runbook - Our Overall Delivery Process How do we initiate a Project? Any project is a response to a pain point or desire expressed by either customers, internal stakeholders, employees, or regulatory authorities. In short, a project is a time bound and specific goal oriented task-system that is born out of an ask from any stakeholder. Project initiation is laying down a new project by defining its goals, objectives,...

  • TSR Silding! 5. Consider a farmer who must sale an extensive pasture of 100 acres (the...

    TSR Silding! 5. Consider a farmer who must sale an extensive pasture of 100 acres (the "Owner"). The pasture is currently covered by cedars and it is impossible to be sure of the productivity. The soil of the pasture is likely poor quality and can only support 10 cows, making it worth $50,000. But there is a 20 percent chance that it is high quality, meaning it can support 40 cows with a value of $200,000 a. After the pasture...

  • Guri Dam Project Management Brings Reliable Power and Growth To Remote Venezuelan Region Commonly known as...

    Guri Dam Project Management Brings Reliable Power and Growth To Remote Venezuelan Region Commonly known as Guri Dam, the Central Hidroeléctrica Raúl Leoni (Raul Leoni Hydroelectric Center) is one of the largest operating hydroelectric projects in the world. It is located in the Bolívar State in Venezuela’s Guayana region, and was built over a 23-year period using a phased construction concept. This design minimized the project’s initial investment and matched power supply to the growth in demand on Venezuela’s electrical...

  • TORENTO CONSTRUCTION: ETHICAL CONTRACTING On December 27, 2010, Cary Holmes, manager of the Supply Chain Management...

    TORENTO CONSTRUCTION: ETHICAL CONTRACTING On December 27, 2010, Cary Holmes, manager of the Supply Chain Management (SCM) group at Torento Construction Inc. (NCG), was in his office in Torento, Ontario, trying to organize the thoughts running through his head as a result of a recent bidding to save operating costs at NCG. There was no problem in terms of the final outcome; in fact, the bid was going to result in cost savings of 25 per cent, which was exactly...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT