Question

A PERT network consists of 60 activities, and 20 of these are critical activities. The length...

A PERT network consists of 60 activities, and 20 of these are critical activities. The length of the critical path is 120 days. The sum of all activity variances is 64; while the sum of the variances along the critical path is 36.

The probability that this project can be completed within 108 and 120 days is:

  1. More than 0.4675 but less than or equal to 0.4695
  2. More than 0.4695 but less than or equal to 0.4700
  3. More than 0.4700 but less than or equal to 0.4775
  4. More than 0.4775 but less than or equal to 0.4780
  5. None of the above.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:
Given in the question
Length of critical path or Expected time of project completion (\mu) = 120
Variance of Critical path = 36
Standard deviation (\sigma) = sqrt(Variance) = sqrt(36) = 6
We need to calculate probability that this project can be completed within 108 and 120 days, which can be calculated as
P(108<X<120) = P(X<120) - P(X<108)
Here we will use standard normal distribution, First we will calculate Z-score which can be calculated as
Z-score = (X-\mu)/\sigma = (120-120)/6 = 0
Z = (108-120)/6 = -2
From Z table we found p-value
P(108<X<120) = P(X<120) - P(X<108) = 0.5 - 0.0228 = 0.4772
So there is 47.72% probability that this project can be completed within 108 and 120 days.
0.4772 220 on 120 x-108

answered by: ANURANJAN SARSAM
Add a comment
Know the answer?
Add Answer to:
A PERT network consists of 60 activities, and 20 of these are critical activities. The length...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following info is available for drawing a PERT network using AOA. *(More than one answer...

    The following info is available for drawing a PERT network using AOA. *(More than one answer may be selected)* Activity Immediate Predecessors Activity Duration (days) A -- 10 B -- 13 C A 12 D B 15 E A 13 F C 16 G D,E 10 H G,F 5 a. the critical path includes: B, D, G, and H. b. the slack on activity G is not 11 days. c. there is one critical path. d. the total duration to...

  • 1. When finding the approximate probability of project duration, it is necessary to know which of...

    1. When finding the approximate probability of project duration, it is necessary to know which of following? a. The mean and variance of each activity b. The mean of each activity on the CP c. The sd of only the activities on the CP d. Each activity's probability of completion e. The distribution of activity times 2. The sd of a path is computed as: a. the sum of the sd of all activities on the path b. the square...

  • 11. In CPM/PERT, an activity that is on the critical path A. has equal values for...

    11. In CPM/PERT, an activity that is on the critical path A. has equal values for "Latest Start" and "Earliest Start" ( LS = ES ) B. has equal values for "Latest Finish" and "Earliest Finish" ( LF = EF ) C. is used in calculating total project duration D. has slack equal to zero E. all of the above 12. In CPM/PERT, the critical path through the network A. will require the most time of any path B. will...

  • .8-6. A project consists of 12 activities, represented by the project network below, where number by each arc repres...

    .8-6. A project consists of 12 activities, represented by the project network below, where number by each arc represents the duration (in days) of the associated activity 4 12 4 12 10 a) Find the earliest time, latest time, and slack for each event as well as the slack for each activity. Also identify the critical path. (b) The project has been scheduled to be completed in the minimum possible time.If all previous activities have begun as early as possible...

  • 5-9 answer only, 10 please tell me how to get the answer. mal limits (keep three...

    5-9 answer only, 10 please tell me how to get the answer. mal limits (keep three deci 5 What are the upper and lower control chart limits using 3-sigma I places if necessary and select the closest one) (d) (6.583, 33.416] () [17,23] (d) I6.583, 33.41 (o) [o.o96, 0.105) (e) (0.037,0.163] (b) 10.099, 0.101) 6. Is the process in control? (a) Yes (b) No 7. If the parking office didn't count how many vehicle every day, is the process s...

  • Please show work 5) A project being analyzed by PERT has 40 activities, 18 of which...

    Please show work 5) A project being analyzed by PERT has 40 activities, 18 of which are on the critical path. If the estimated time along the critical path is 107 days with a project variance of 25, what is the probability that the project will take 112 days or less? A) Near zero B) 0.0126 C) 0.8411 D) 0.1587 E) 2.14

  • NETWORK: PERT 4 - Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES tml - 2...

    NETWORK: PERT 4 - Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES tml - 2 (days) tp c D, E 1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.) 2) By using ES, EF, LF, LS, find the slack of each activity and the critical path. 3) Find the completion time (x) and the standard deviation (6) for the project-...

  • The following table represents the set of activities required to complete a project, along with their...

    The following table represents the set of activities required to complete a project, along with their time estimates for PERT calculations. a. Using the data in the table, calculate the expected time (ET) and variance for each activity. Job Predecessor mi expected variance number Job(s) time (ET) --- 468 B A 3 4 5 CIA 234|| D C 34 11 E B, C 13 5 D, E 2 46 F b. [Sketch the network diagram for the project on a...

  • For the activities given in the table: Draw the AOA network diagram Find the critical activities...

    For the activities given in the table: Draw the AOA network diagram Find the critical activities Find the critical path Find the project completion time Time (days) Predecessors Activity Description Initial Paperwork A 3 Build Body B A 3 C Build Frame A 2 Finish Body 3 D E Finish Frame C Final Paperwork B,C 3 G Mount Body to Frame D,E 6 Install Skirt on Frame C 2 H A FLO For the activities given in the table: Draw...

  • Given is a PERT project network diagram as shown below. Start D Activity Start ABCDEFGH End...

    Given is a PERT project network diagram as shown below. Start D Activity Start ABCDEFGH End Time 0 1.35 3.65 4.327 .36 8.25 1.394 .68 3.250 a) The Project Completion time = (in 2 decimal places) b) The Earliest Start time, Es, of Activity G- (in 2 decimal places) c) The Latest Finish time, LF, of Acitivity C (in 2 decimal places) d) The critical activities are (ex. type in critical activities as ABCD no comma, no space)

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT