Question

Please use the following information to answer question 27-30 Activity Preceding activity Optimistic Pessimistic Most likely

what is the earliest time to finish thr project ?

A. 18.7
B. 20
C. 21.7
D. 22.5
E. 26.2

what is the expected activity time for activityD?
2
3
4
5
6
what is the latest start time fir activity G without delaying the project ?
5.3
10.7
13.3
14.9
18.5

what is the late finish time for activity A
0
2.5
4.7
5.7
8
0 0
Add a comment Improve this question Transcribed image text
Answer #1

IVIT Predecessor 14.67 ho souous Hoolt 1919 Joom 3.83 4 8 | 5:33 a= optimistic time b = Pessimistic time . m = Most likely ti[201 Page No. ( Date: B. Bla1 Gl9 小站 SYM 的 6 501中 98 |Fu」 . % HE IFE | FG 54 官 6f181 EW- || 刊318ca) Earliest time to finish project - 22.5 (b) ke Expected Activity time fos Activity D (c) Latest start time for G 13.17 (d)

All the parts have been done as shown.

Add a comment
Know the answer?
Add Answer to:
what is the earliest time to finish thr project ? A. 18.7 B. 20 C. 21.7...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT