Question

QUESTION 32 Using the table and network below, how many paths are there in the network? Activity Predecessor Time OAO - LOE 9

QUESTION 33 Using the table and network below, what is the critical path of the project?! Activity Predecessor Time «Խլ bhi c

QUESTION 34 Given the table and problem below, choose the correct value for the duration of the project. Activity Predecessor

QUESTION 35 Using the POM Time Schedule and the network below, specify the critical path for the project. Activity time ES EF

0 0
Add a comment Improve this question Transcribed image text
Answer #1

9 (32) No. of Path = a-d-J a-e-h-s b-Di-d- J b-Di-e-n- b-f-h- J b-Dz-g-i-] b-Dz - D3-h- C- g- i-J c-b3-h-J. ] 33) Longest pat

Add a comment
Know the answer?
Add Answer to:
QUESTION 32 Using the table and network below, how many paths are there in the network?...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT