1. Increasing the capacity just before a bottleneck operation will improve the output of the process.
True or false
2. Increasing the capacity of the bottleneck resource always increases the capacity of process.
True or false
3. If the process has an average inventory of 5 units and the flow time is 1 hr, than the actual cycle time is 12 minutes.
True or false
Answer 1 : False
Explanation : To improve the output of the process one must know and identify the value added activities, communicate changes effectively, map existing process etc.
Answer 2 : True
Explanation : When the capacity of the WIP in bottleneck is been increased the outcome and the capacity changes.
Answer 3 : True
Explanation : To calculate cycle time, use the formula : cycle time = 1 / throughput rate, where throughput rate = units produced/ time, hence : Throughput time = 5 / 60 min ( 1 hr = 60 minutes) = 0.0833
Now, cycle time = 1 / 0.08333 = 12 minutes.
1. Increasing the capacity just before a bottleneck operation will improve the output of the process....
What is the process time of the system? b) What is the bottleneck time of this work cell? c)What is the process cycle time? d) If the firm operates 10 hours per day, 5 days per week, what is the weekly capacity of this work cell? The three-station work cell illustrated in the figure below has a product that must go through one of the two machines at station 1 (they are parallel) before proceeding to station 2. o Capacity:...
Which one of the following statements is true? Throughput contribution is not increased when non-bottleneck output is increased. a. The elimination of defects always increases productivity. b. Non-bottleneck operations should be refined for high efficiency before starting on bottleneck improvement because non-bottleneck operations are generally easier to correct and improve. С. d. Quality and time are seldom related in service industries. The elimination of defects always decreases revenues. е.
A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). Q 2.5 units.hr 1.8 units/hr Assembly a Sawing 0.8 units/hr Sanding Welding 5 units/hr Assembly 0.8 units/hr Driling 5 units.hr Assembly 0.8 units/hr a) Sanding is the bottleneck b) The bottleneck...
A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). Q 2.5 units/hr Sawing 2.1 units/he Sanding Assembly 0.8 unitsthe Welding 6 units.hr Assembly 0.8 units Drilling 5 unitshe Assembly 0.8 untui is the bottleneck 0.7 units/hr a) Drilling is the...
2. Four Step Process with Rework and Scrap - from module 5 slides Consider the following four step assembly operation with quality problems. All resources are staffed with one operator. The first resource has a processing time of 4 minutes per unit The second resource has a processing time of 3 minutes per unit. This process suffers from a high yield loss and 50% of all products have to be scrapped after this step. The third resource also suffers from...
PA 3-3 Consider a process consisting of three... Consider a process consisting of three resources. Assume there exists unlimited demand for the product. Resource 1 has a processing time of 2 minutes per unit. Resource 2 has a processing time of 6 minutes per unit. Resource 3 has a processing time of 4 minutes per unit. Resource 1 Resource2 Resource 3 All three resources are staffed by one worker. The flow diagram is shown above. Round "Capacity of resource" to...
1 . Product A has a unit profit of $40 and takes 10 minutes on the bottleneck; Product B has unit profit of $60 and takes 30 minutes on the bottleneck. Non-bottleneck operations have infinite capacity because capacity can be added at no cost. The bottleneck has a capacity of 24 hours in a day. Should I maximize feasible production of: a. Product A b. Product B 2In terms of setting up a safety program, Heinrich’s Safety Triangle states the...
1. The bottleneck time of the system is - ??? minutes per unit (enter your response as a whole number). 2. Which Station (1, 2, or 3) is the bottle neck station? 3. The throughput time is - ?????? 4. If the firm operates 11 hours per? day, 5 days per? week, the weekly capacity of this work cell is?....... units? (enter your response as a whole? number). The three-station work cell illustrated in the figure below has a product...
PART I: Multiple Choice Write all answers to the following questions. No partial credit available. Consumption utility is composed of price and convenience. True or False? A firm reduces inefficiencies by making trade-offs. True or False? A firm can increase its profitability by: A. increasing costs and reducing price. B. moving away from the efficient frontier. C. increasing inefficiencies. D. reducing inefficiencies. Operations comes from the Latin word "opus," which means: A. activity. B. helping people. C. improvement. D. work....
Matching supply with Demand (3rd Edition) - Question 10.2 (Process with Rework) Consider the following three-stage production process of glass ceramics, which is operated as a worker-paced line. Q10.2 Components 6 min./unit 5 min./unit min. /unit Finished Units Rework The process is experiencing severe quality problems related to insufficiently trained work- ers. Specifically, 20 percent of the parts going through operation 1 are badly processed by the operator. Rather than scrapping the unit, it is moved to a highly skilled...