Question

Your stockroom manager, Mehmet Altag, arrived at your desk just after you had completed the net requirements plan for product
Complete a new net requirements pian, based on the actual inventory (as reportea) and the new schedule (enter your responses
0 0
Add a comment Improve this question Transcribed image text
Answer #1

ANSWER :

Calculare requriements :

1.Net Requirement = Gross Requirement – On hand inventory

2.If Lead time is one week, so place order one week before the net requirement week.

Week 1 3 3 Gross Requirements On Hand Net requirement Planned order receipt Planned order release 100 1 2 3 4 5 10 11 12 13 1

Add a comment
Know the answer?
Add Answer to:
Your stockroom manager, Mehmet Altag, arrived at your desk just after you had completed the net...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Your stockroom manager, Yamil Bermudez, arrived at your desk just after you had completed the net requirements plan for...

    Your stockroom manager, Yamil Bermudez, arrived at your desk just after you had completed the net requirements plan for product A (use data given below), exclaiming that the cycle counter should be fired. It seems that the cycle counter was wrong. There are three As available now, not zero, as the original data showed. Moreover, five Es are also available. About then, your boss, Sam Melnyk, who overheard the discussion, says, "You might as well extend the net requirements plan...

  • You need to schedule 10 units of product Alpha for delivery in 6 weeks. Three units...

    You need to schedule 10 units of product Alpha for delivery in 6 weeks. Three units of D and 2 units of F are required for each Alpha. The lead time for Alpha is 1 week. Lead time for D is 1 week, and lead time for F is 2 weeks. Click the icon to view the product structure Click the icon to view the time-phased product structure. i More Info Construct a net material requirements plan if there are...

  • OPMGT301 Homework Assignment 5: MRP You MUST show all your work, including tables for all the...

    OPMGT301 Homework Assignment 5: MRP You MUST show all your work, including tables for all the necessary parts, to get full credit. If you plan to type your answers in a word processor, you may find the following table useful (you can copy-and-paste it for convenience) End Product Week Gross Requirements from Gross Requirements from Gross Requirements Scheduled Receipts Projected On-hand Net Requirements Planned-order Receipts Planned-order Releases 12345678 Product B 12 345 Week Gross Requirements from Gross Requirements from Gross...

  • Assume that you are the manager of a shop that assembles power tools. You have just...

    Assume that you are the manager of a shop that assembles power tools. You have just received an order for 51 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Lead Time (weeks) On Hand Item Saw Components A(2), B(1), C(4) E(3), D(1) D(2), F(3) E(2), D(2) Mowu Develop the material requirements plan for component Eusing lot-for-lot ordering. (Leave no cells blank - be certain to enter "0" wherever required.)...

  • calculate the MRP Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled...

    calculate the MRP Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled receipts are shown. Click the icon to view the MRP record. Complete the material requirements plan (enter your responses as whole numbers). Week .A2* LT(weeks) 3 2 6 1 Gross requirements Scheduled receipts Projected ending inventory: 360 350 100 50 100 220 0 Net requirements Min. order 1 Planned receipts Planned orders ulo iMore Info Week 2 4 5 6 3 A2** Gross requirements...

  • Assume that you are the manager of a shop that assembles power tools. You have just...

    Assume that you are the manager of a shop that assembles power tools. You have just received an order for 53 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand Components Saw 2 15 A(2), B(1), C(4) A 1 10 E(3), D(1) B 2 5 D(2), F(3) C 2 65 E(2), D(2) D 1 20 E 1 10 F 2 30    Develop the material...

  • The demand for subassembly S is 80 units in week 7. Each unit of S requires...

    The demand for subassembly S is 80 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 2 units of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U,...

  • provide step by step explanation of calculation. thanks

    Case #2 MGT2315  There are two (2) Parts to this case.  The First part (Part 1) requires you to use the information to:1.    Build a Bill of Material (BOM) form the given information2.    Determine the Master Production Schedule (MPS) and3.    Complete the MRP for all parts including the product.   The Second Part (Part 2) will require you to use an indexed BOM to 1.    Create the correct MPS from the provided information2.    create the MRP for the unit and all of...

  • Recently, Phil Harris, the production control manager at Brunswick, read an article on time phased requirements...

    Recently, Phil Harris, the production control manager at Brunswick, read an article on time phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine...

  • The demand for subassembly S is 120 units in week 7. Each unit of S requires...

    The demand for subassembly S is 120 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 1 unit of V, 1 unit of W. and 1 unit of X. Finally, each unit of U requires 1 unit of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S. 1 week to make T. 2 weeks to make U....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT