Question

Your stockroom manager, Yamil Bermudez, arrived at your desk just after you had completed the net requirements plan for produtem C 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Week Gross requirement 10 7 10 10 On hand 10 10 10 10 10 Net requirement 10 10 P

Your stockroom manager, Yamil Bermudez, arrived at your desk just after you had completed the net requirements plan for product A (use data given below), exclaiming that the cycle counter should be fired. It seems that the cycle counter was wrong. There are three As available now, not zero, as the original data showed. Moreover, five Es are also available. About then, your boss, Sam Melnyk, who overheard the discussion, says, "You might as well extend the net requirements plan out to 16 weeks, because we just received an order for 10 more As in week 12 and 5 more in week 15. Additionally, count on the fleld service department wanting 3 more Bs in week 16, as well as those 10 units of B and F in week 6. 囲 Click the icon to view the completed net requirements plan for product A. 囲Click the icon to view the inventory on hand for each product. Click the icon to view the structure tree Complete a new net requirements plan, based on the actual inventory (as reported) and the new schedule (enter your responses as whofe numbers) Item A Weck 1 23 4 56 78 9 10 11 12 13 14 15 16 0 10 10 On hand 10 Net requirement Planned order receipt 10 10 0 Planned order release Item B Week 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 10 0 Gross requirement 10 7 On hand 2 2 2 22 2 O 10 0 Net requirement 10 0 Planned order receipt Planned order release 10
tem C 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Week Gross requirement 10 7 10 10 On hand 10 10 10 10 10 Net requirement 10 10 Planned order receipt 10 10 5.3 Planned order release 1010 Answe.
1 0
Add a comment Improve this question Transcribed image text
Answer #1

Steps to create the MRP 1) Enter the gross requirement as per Master Planning Schedule (MPS). Gross requirement of components

Projected available balance: scheduled receipts plus available inventory from last period. Planned order receipts: the quanti

The MRP of items is developed in order as per their level in the product structure. So MRP of parent items is created first and child items later. The gross requirements is computed on the basis of MRP of parent items.

MRP of all the items are developed as below:

16 15 14 12 13 10 11 MRP 10 Item 10 Gross Requirement 10 Proiected on Hand ss = 10 Net Requirement 10 1 Planned Order Receipt

15 16 14 11 12 13 Item 10 Gross Requirement Proiected on Hand 10 Net Requirement 10 4Planned Order Receipt 10 Planned Order R

Add a comment
Know the answer?
Add Answer to:
Your stockroom manager, Yamil Bermudez, arrived at your desk just after you had completed the net requirements plan for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Your stockroom manager, Mehmet Altag, arrived at your desk just after you had completed the net...

    Your stockroom manager, Mehmet Altag, arrived at your desk just after you had completed the net requirements plan for product A (use data given below), exclaiming that the cycle counter should be fired. It seems that the cycle counter was wrong. There are three As available now, not zero, as the original data showed. Moreover, five Es are also available. About then, your boss, Joe Orlicky, who overheard the discussion, says, "You might as well extend the net requirements plan...

  • You need to schedule 10 units of product Alpha for delivery in 6 weeks. Three units...

    You need to schedule 10 units of product Alpha for delivery in 6 weeks. Three units of D and 2 units of F are required for each Alpha. The lead time for Alpha is 1 week. Lead time for D is 1 week, and lead time for F is 2 weeks. Click the icon to view the product structure Click the icon to view the time-phased product structure. i More Info Construct a net material requirements plan if there are...

  • Assume that you are the manager of a shop that assembles power tools. You have just...

    Assume that you are the manager of a shop that assembles power tools. You have just received an order for 53 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand Components Saw 2 15 A(2), B(1), C(4) A 1 10 E(3), D(1) B 2 5 D(2), F(3) C 2 65 E(2), D(2) D 1 20 E 1 10 F 2 30    Develop the material...

  • The demand for subassembly S is 80 units in week 7. Each unit of S requires...

    The demand for subassembly S is 80 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 2 units of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U,...

  • In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order...

    In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) 1 0 34 WEEK NUMBER 2 3 4 47 ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 5 71 - 4 Item J LT = 1 Q = L4L Period Gross...

  • Assume that you are the manager of a shop that assembles power tools. You have just...

    Assume that you are the manager of a shop that assembles power tools. You have just received an order for 51 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Lead Time (weeks) On Hand Item Saw Components A(2), B(1), C(4) E(3), D(1) D(2), F(3) E(2), D(2) Mowu Develop the material requirements plan for component Eusing lot-for-lot ordering. (Leave no cells blank - be certain to enter "0" wherever required.)...

  • Problem 12-18 Develop a material requirements plan for component H. Lead times for the end item a...

    Problem 12-18 Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the start of week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are in production and will be completed by the start of week 2. (Leave no cells...

  • In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order...

    In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 73 55 74 On hand 43 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J LT = 1...

  • In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order...

    In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 75 50 70 On hand 40 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J OH = 40...

  • Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for...

    Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT