The MRP of items is developed in order as per their level in the product structure. So MRP of parent items is created first and child items later. The gross requirements is computed on the basis of MRP of parent items.
MRP of all the items are developed as below:
Your stockroom manager, Yamil Bermudez, arrived at your desk just after you had completed the net requirements plan for...
Your stockroom manager, Mehmet Altag, arrived at your desk just after you had completed the net requirements plan for product A (use data given below), exclaiming that the cycle counter should be fired. It seems that the cycle counter was wrong. There are three As available now, not zero, as the original data showed. Moreover, five Es are also available. About then, your boss, Joe Orlicky, who overheard the discussion, says, "You might as well extend the net requirements plan...
You need to schedule 10 units of product Alpha for delivery in 6 weeks. Three units of D and 2 units of F are required for each Alpha. The lead time for Alpha is 1 week. Lead time for D is 1 week, and lead time for F is 2 weeks. Click the icon to view the product structure Click the icon to view the time-phased product structure. i More Info Construct a net material requirements plan if there are...
Assume that you are the manager of a shop that assembles power tools. You have just received an order for 53 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Lead Time (weeks) On Hand Components Saw 2 15 A(2), B(1), C(4) A 1 10 E(3), D(1) B 2 5 D(2), F(3) C 2 65 E(2), D(2) D 1 20 E 1 10 F 2 30 Develop the material...
The demand for subassembly S is 80 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 2 units of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U,...
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) 1 0 34 WEEK NUMBER 2 3 4 47 ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 5 71 - 4 Item J LT = 1 Q = L4L Period Gross...
Assume that you are the manager of a shop that assembles power tools. You have just received an order for 51 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Lead Time (weeks) On Hand Item Saw Components A(2), B(1), C(4) E(3), D(1) D(2), F(3) E(2), D(2) Mowu Develop the material requirements plan for component Eusing lot-for-lot ordering. (Leave no cells blank - be certain to enter "0" wherever required.)...
Problem 12-18 Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the start of week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are in production and will be completed by the start of week 2. (Leave no cells...
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 73 55 74 On hand 43 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J LT = 1...
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 75 50 70 On hand 40 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J OH = 40...
Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...