Question

If the value added time for a process is 40 minutes per 8 hour shift, what...

If the value added time for a process is 40 minutes per 8 hour shift, what is the process cycle efficiency expressed as a percentage?

5.00%
1.50%
6.24%
8.33%
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Process cycle efficiency = Value Added Time x 100 Total shift time n = 40 x 100 480 Total shift time = 8x60 min = 480 min 1 =I have solved the question neatly so that you can understand the solution easily. I have written the formula for process cycle efficiency so that you can use it for future reference.

Hope you like the solution. Thank you.

Add a comment
Know the answer?
Add Answer to:
If the value added time for a process is 40 minutes per 8 hour shift, what...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Compute the takt time for a system where the total time per shift is 480 minutes,...

    Compute the takt time for a system where the total time per shift is 480 minutes, there are two shifts, and workers on each shift are given two 15-minute breaks and 45 minutes for lunch. Daily demand is 650 units. What cycle time would match capacity and demand if demand is 120 units a day, there are two shifts of 480 minutes each, and workers are given two half-hour breaks during each shift, one of which is for lunch or...

  • The following information is from a manufacturing company. Process time Inspection time Move time Wait time...

    The following information is from a manufacturing company. Process time Inspection time Move time Wait time 20.0 minutes 3.0 minutes 8.6 minutes 42.6 minutes Required: a. Compute manufacturing cycle time b. Compute manufacturing cycle efficiency Complete this question by entering your answers in the tabs below. Required A Required B Compute manufacturing cycle time. (Round your answers to 1 decimal place.) Manufacturing cycle time Time Manufacturing cycle time The following information is from a manufacturing company. Process time Inspection time...

  • The following information is from a manufacturing company. Process time Inspection time Move time wait time...

    The following information is from a manufacturing company. Process time Inspection time Move time wait time 19.0 minutes 2.0 minutes 6.6 minutes 43.8 minutes Required: a. Compute manufacturing cycle time - b. Compute manufacturing cycle efficiency Complete this question by entering your answers in the tabs below. Required A Required B Compute manufacturing cycle time. (Round your answers to 1 decimal place) Manufacturing cycle time Time Manufacturing cycle time Required B > Complete this question by entering your answers in...

  • The following information is from a manufacturing company. Process time Inspection time Move time Wait time 17.0 minute...

    The following information is from a manufacturing company. Process time Inspection time Move time Wait time 17.0 minutes 2.0 minutes 7.0 minutes 41.4 minutes Required: a. Compute manufacturing cycle time b. Compute manufacturing cycle efficiency Complete this question by entering your answers in the tabs below. Required A Required B Compute manufacturing cycle time. (Round your answers to 1 decimal place.) Manufacturing cycle time Time Manufacturing cycle time 0.0 Required: a. Compute manufacturing cycle time b. Compute manufacturing cycle efficiency...

  • 38. Calculate the pieces per hour and the hours per unit for the following: Hours per 1,000 Piece...

    38. Calculate the pieces per hour and the hours per unit for the following: Hours per 1,000 Pieces Time StandardPieces per Hours per Piece Pieces per 8 Hours Minute 1.000 0.500 0.167 2.500 0.650 0.050 Hour Page 8 of 13 39. For the following data calculate the takt time. Length of shift: 8.5 hours, production requirements: 3,300 units, overall efficiency is 85%, non-production time: breaks 20 minutes; clean-up 10minutes; meeting 10 minutes, and lunch 30 minutes. 38. Calculate the pieces...

  • Problem 3: [14 points) During an 8-hour shift, the proportion of time Y that a sheet-...

    Problem 3: [14 points) During an 8-hour shift, the proportion of time Y that a sheet- metal stamping machine is being serviced for repairs has the following distribution: f(y) | 2(1 – y), if 0<y<1, elsewhere. 0, (a) Find the probability that the machine repair-time is between 25 minutes and 40 minutes during the 8-hour shift. [3] (b) Derive the c.d.f of Y and use it to find the 25th percentile of Y. [5] (c) Find E(Y) and E(Y2) (2,2]...

  • A machine has a cycle time of 0.485 seconds. What are the productions pieces per hour...

    A machine has a cycle time of 0.485 seconds. What are the productions pieces per hour at 100% and 85% efficiency? The floor-to-floor time (meaning a complete productive cycle) is 21 seconds. Find the gross units per hour at 100% and 95% efficiency.

  • The production facility run on one 7.5 hour shift. There is a 15 minute meeting planned at the beginning of the shift an...

    The production facility run on one 7.5 hour shift. There is a 15 minute meeting planned at the beginning of the shift and 30 total minutes of setup time each day. 15 minutes of unscheduled equipment failure usually occurs. 380 good parts and 20 defective parts were produced with a standard cycle time of 60 parts per hour. What is the Overall Equipment Effectiveness (OEE)? A) 93.51% B) 78.56% C) 85.17% D) 72.34%

  • Check my w Inspection time Wait time (from order to start of production) Process time Move...

    Check my w Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.5 days 15.4 days 3.2 days 0.9 days 4.3 days Required: 1. Compute the throughput time. (Round your answer to 1 decimal place.) 2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.) 3. What percentage of the throughput time was spent in non-value-added activities? (Round your percentage answer to nearest whole percent.)...

  • MCE Craig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 100 units (per hour) Move time: 18 minutes Inspection time: 13 minu...

    MCE Craig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 100 units (per hour) Move time: 18 minutes Inspection time: 13 minutes Rework time: 15 minutes Required: 1. Calculate MCE. If required, round your answer to two decimal places. 2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times. If required, round your answers to two decimal places. Theoretical cycle time minutes Actual cycle time...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT