A machine has a cycle time of 0.485 seconds. What are the productions pieces per hour at 100% and 85% efficiency? The floor-to-floor time (meaning a complete productive cycle) is 21 seconds. Find the gross units per hour at 100% and 95% efficiency.
A machine has a cycle time of 0.485 seconds. What are the productions pieces per hour...
38. Calculate the pieces per hour and the hours per unit for the following: Hours per 1,000 Pieces Time StandardPieces per Hours per Piece Pieces per 8 Hours Minute 1.000 0.500 0.167 2.500 0.650 0.050 Hour Page 8 of 13 39. For the following data calculate the takt time. Length of shift: 8.5 hours, production requirements: 3,300 units, overall efficiency is 85%, non-production time: breaks 20 minutes; clean-up 10minutes; meeting 10 minutes, and lunch 30 minutes. 38. Calculate the pieces...
Cycle Time and Velocity Norton Company has the following data for one of its production departments: Theoretical velocity: 180 units per hour Productive minutes available per year: 62,000,000 Annual conversion costs: $372,000,000 Actual velocity: 72 units per hour Required: 1. Calculate the actual conversion cost per unit using actual cycle time and the standard cost per minute. Round your actual cycle time answer to three decimal places and your cost per unit answer to the nearest cent. Actual cycle time...
Determine the maximum output of a manufacturing system that operations 60 minutes per hour, has a calculated total task time of all operations equal 220 seconds, and a bottleneck cycle time of 30 seconds per unit. The maximum output rate of this system is: __________ units per hour.
If the value added time for a process is 40 minutes per 8 hour shift, what is the process cycle efficiency expressed as a percentage? 5.00% 1.50% 6.24% 8.33%
(10 points) The normal time for a repetit h atduces two work per ce min. The plant uses a PFD allowance factor of 15 Determine the standard meet and (b) how many work units are produced in an hour tandard performance 4. (10 points) The normal time of the work cycle in a worker-machine system is 5.50 min. The operator-controlled portion of the cycle is 0.70 min. One work unit is produced each cycle. The machine cycle time is constant....
MCE Craig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 100 units (per hour) Move time: 18 minutes Inspection time: 13 minutes Rework time: 15 minutes Required: 1. Calculate MCE. If required, round your answer to two decimal places. 2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times. If required, round your answers to two decimal places. Theoretical cycle time minutes Actual cycle time...
A production process has two machines. The first machine has a capacity of 500 units per hour and the second machine has a capacity of 350 units per hour. Demand for the process is 100 units per hour. (a) In a push process, what would be the utilization of the first machine? Utilization of the first machine is ___%? (b) How would the situation change with a pull system? The utilization would drop to ___%?
Cycle Time and velocity, MCE Computador has a manufacturing plant in Des Moines that has the theoretical capability to produce 260,000 laptops per quarter but currently produces 78,000 units. The conversion cost per quarter is $8,190,000. There are 65,000 produ the processing minutes per unit used, the production of the laptops uses 9 minutes of move time, 21 minutes of wait time, and 6 minutes of rework time. (All work is done by cell workers.) Required: 1. Compute the theoretical...
What is a Therblig? Please specify and give exampie. 3) A time study was conducted on a job that contains four elements. The observed times and performance ratings for six cycles are shown in the following table. Note that all units are in minutes 15 Element Performance 1 13 4 6 rating 85% 100% 110% 95% 0.5 258* 0.89 1.14 0.46 1.52 0.8 0.44 1.5 0.84 1.1 0.43 1.47 0.48 1.49 0.85 0.45 1.51 0.83 1.081.21.161.26 4 * Machine broke...
Craig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 100 units (per hour) Move time: 20 minutes Inspection time: 14 minutes Rework time: 13 minutes Required: 1. Calculate MCE. If required, round your answer to two decimal places. 2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times. If required, round your answers to two decimal places. Theoretical cycle time minutes Actual cycle time minutes...