A flood control study for a urban river has developed three alternatives. The initial costs are...

A flood control study for a urban river has developed three alternatives. The initial costs are $5,000,000, $8,000,000, and $10,000,000 for alternatives A, B, and C, respectively. The annual maintenance costs are $200,000, $350,000, and $600,000 for alternatives A, B, and C, respectively. Once flooding occurs, the damage is $1,000,000. If alternatives A, B, and C can prevent 30%, 70%, and 80% of annual probability of occurrence, respectively, which alternative should be selected? The life span of the project is 30 years and the annual interest rate is 6 %.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

Alternative B should be selected.

Alternative B is least cost option.

Workings:

Add a comment
Know the answer?
Add Answer to:
A flood control study for a urban river has developed three alternatives. The initial costs are...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Three sites (A, B & C) are being considered for flood control dams. The three construction...

    Three sites (A, B & C) are being considered for flood control dams. The three construction costs are $10 million, $12 million and $20 million; and the annual maintenance costs are expected to be $15,000, $20,000 and $23,000 respectively for sites A, B and C. In addition, a $75,000 refurbishing expenditure will be required every 10 years at each site. Every year without the dams, $2 million in flood damage occurs. It is projected that dam A, by itself, would...

  • An area on the Colorado River is subject to periodic flood damage that​ occurs, on the​ average, every two years​ (i.e., probability of flooding in any year is​ 0.5) and results in a $2,200,000 loss....

    An area on the Colorado River is subject to periodic flood damage that​ occurs, on the​ average, every two years​ (i.e., probability of flooding in any year is​ 0.5) and results in a $2,200,000 loss. It has been proposed that the river channel be improved by straightening and deepening it at a cost of$2,400,000​, to reduce the annual probability of flooding to 0.364  during a period of 18 years before it would have to be deepened again. This procedure would...

  • One of two alternatives will be selected to reduce flood damage in a rural community in...

    One of two alternatives will be selected to reduce flood damage in a rural community in central Arizona. The estimates associated with each alternative are available. Use B/C analysis at a discount rate of 7% per year over a 20-year study period to determine which alternative should be selected. For analysis purposes only, assume the flood damage would be prevented in years 3, 13, and 18 of the study period. Retention Pond Channel Initial Cost, $ 960,000 2,900,000 Annual Maintenance...

  • One of two alternatives will be selected to reduce flood damage in a rural community in...

    One of two alternatives will be selected to reduce flood damage in a rural community in central Arizona. The estimates associated with each alternative are available. Use B/C analysis at a discount rate of 7% per year over a 20 year study period to determine which alternative should be selected. For analysis purposes only, assume that the benefits of reduced flood damage are available in years 3, 8, and 18 of the study period. 33 Retention Pond Channel Initial Cost,...

  • Problem 09.029 Two Alternative Comparison One of two alternatives will be selected to reduce flood damage in a rural co...

    Problem 09.029 Two Alternative Comparison One of two alternatives will be selected to reduce flood damage in a rural community in central Arizona. The estimates associated with each alternative are available. Use B/C analysis at a discount rate of 9% per year over a 20-year study period to determine which alternative should be selected. For analysis purposes only, assume that the benefits of reduced flood damage are available in years 4, 8, and 18 of the study period. Retention Pond...

  • please show all work. Recent flooding on the Big Bad River at Goodtown has motivated the...

    please show all work. Recent flooding on the Big Bad River at Goodtown has motivated the community to reconsider building a flood levee. A nearby stream gage on the river has a 60-year record. The ranked sample of annual maximum peak discharges are: Rank Peak Discharge (cfs) 1 5850 2 4120 4020 3 58 59 60 410 390 200 The 3rd largest flood (shown above) occurred in the past year. What is the estimated return period for the 3rd largest...

  • 2. In a proposed flood control project, there are two possible sites, A and B, for...

    2. In a proposed flood control project, there are two possible sites, A and B, for a dam and storage reservoir. One or the other of these sites may be used but not both. Certain channel improvement is also considered; this will increase the capacity of the stream to carry flood discharge. Estimated first costs, lives, and annual operation and maintenance costs are as follows: Site A Site B Channel Improvement First cost $6,000,000 $8,000,000 $1,000,000 Life 75 years 75...

  • Written solution please 5- The Nile Basin countries are considering three flood control projects in Ethiopia....

    Written solution please 5- The Nile Basin countries are considering three flood control projects in Ethiopia. Project A is a dam. The dam will have recreation and irrigation benefits as well as the flood control benefits. Projects B and C consist of permanent dikes along the river. Facts about the three projects are shown in the following table. Each project has a life of 25 years. The MARR is 10%. Use (a) BCR & (b) IRR method to choose the...

  • A city council considers to construct a new toll bridge across the river. Investment cost of...

    A city council considers to construct a new toll bridge across the river. Investment cost of the bridge is estimated to be $7,000,000 with an annual operating and maintenance costs of $130,000 per year. In addition, the bridge must go through a comprehensive maintenance in every fifth year of its 30-year expected life at a cost of $500,000 per occurrence (no cost in year 30). It is expected 200,000 vehicles per year to cross the bridge. The city plans to...

  • 1. Alaa works for a pharmaceutical company that has developed a new drug. The patent on...

    1. Alaa works for a pharmaceutical company that has developed a new drug. The patent on the drug will last 17 years. She expects that the drug’s profits will be $2 million in its first year and that this amount will grow at a rate of 5% per year for the next 17 years. Once the patent expires, other pharmaceutical companies will be able to produce the same drug and competition will likely drive profits to zero. What is the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT