Question

The following type of buffer does not add time to a schedule: (A) milestone (B) feeding...

The following type of buffer does not add time to a schedule:

(A) milestone

(B) feeding

(C) project

(D) resource

(E) none of the above

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The correct answer is D.

Project buffer helps in protecting the project deadline so a single project buffer is added at the end of the project network between the last activity and project deadline. So, a resource when added does not add time to a schedule.

Add a comment
Know the answer?
Add Answer to:
The following type of buffer does not add time to a schedule: (A) milestone (B) feeding...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • post the answers for the following Mcq's. NOTE: FYI - 17th question has 4 option in...

    post the answers for the following Mcq's. NOTE: FYI - 17th question has 4 option in the pic option A and B is there. option C ) Environmental D ) Mandatory. 2. If you are compressing the project schedule by using a technique that generally does not increase project costs, which of the following techniques are you using? A. Fast tracking B. Crashing C. Resource optimization D. Resource leveling 3. The amount of time a successor activity must wait after...

  • Match the type of schedule listed with the description following. Schedule types may be used more than once a. Activity on arrow (AOA) b. Activity on node (AON) C. Matrix d. Bar chart 40 Grap...

    Match the type of schedule listed with the description following. Schedule types may be used more than once a. Activity on arrow (AOA) b. Activity on node (AON) C. Matrix d. Bar chart 40 Graphically the simplest Graphic style makes it adaptable to high-rise construction 42.Utilizes i-j notation 43 Could also be termed precedent notation Would be used for a summary report to the owner Questions 45-49 Match the terms listed with their description. Terms may be used only once...

  • Warblers feeding on similar foods in the same trees have demonstrated A. allopatry B. symbiosis C....

    Warblers feeding on similar foods in the same trees have demonstrated A. allopatry B. symbiosis C. intense competition between species D. resource partitioning Competition A. is a type of symbiotic relationship B. always negatively effects both competing species C. is also referred to as commensalism D. has the same outcome as a parasite-host relationship

  • 17. The types of float in a CPM schedule are a. free Float b. negative Float...

    17. The types of float in a CPM schedule are a. free Float b. negative Float c. total Float d. independent Float e. all of the above 18. A loop in the schedule means a. circular logic between two activities b. two paths with the same logic c. duplicate activities d. negative float e. a and d 19. Constraints can be define as a. imposed restrictions applied to activities to reflect project requirements that cannot be built into the logic....

  • From this schedule of activities: Activity Immediate Predecessor Activity Time A --- 4 B A 2...

    From this schedule of activities: Activity Immediate Predecessor Activity Time A --- 4 B A 2 C B 3 D B 5 E A 1 F C, D 3 G E, F 2 a. Draw the PERT/CPM network b. Complete the forward and backward pass c. Determine the critical path d. Determine the total duration of the project.

  • 1- Which of the following is NOT a basic type of fire detection system? A Photoelectric...

    1- Which of the following is NOT a basic type of fire detection system? A Photoelectric detection sensors B Fixed-temperature C Rate-of-rise sensors D Thermal detection 2 .-Which of the following delivers documented instructions to the individuals who are executing the implementation phase? A resources B project plan C project scope D milestone

  • ***Choose ANY 6 vaccines as long as there is one of each type of the following:...

    ***Choose ANY 6 vaccines as long as there is one of each type of the following: toxoid vaccine, attenuated virus vaccine, killed virus vaccine, subunit vaccine, conjugate vaccine; DNA vaccine and then fill out the questions below.*** Find an example of each of the types of vaccines (toxoid vaccine, attenuated virus vaccine, killed virus vaccine, subunit vaccine, conjugate vaccine and DNA vaccine) and answer the following questions. VACCINE #1: _________________________________ a. Describe the disease agent, disease transmission, and disease symptoms:...

  • Schedule the following activities using CPM: Table 2 ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A                    — 8...

    Schedule the following activities using CPM: Table 2 ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A                    — 8 B                    A 4 C                    A 4 D                    C 8 E                    B, D 2 F                    D 6 G                    E, F 2 Question 25 (1 point) What is the critical path? (Show your diagram and calculations) Question 25 options: A-C-D-E-G A-B-E-G A-B-D-E-G A-C-D-F-G A-B-D-F-G How many weeks will it take to complete the project? What is B slack time?

  • Compute b) Describe the type of information that an as-built schedule can provide to a firm...

    Compute b) Describe the type of information that an as-built schedule can provide to a firm that might n. otherwise be obtained as puut ncclule shows things that man caured delay previously that can now he avided" c) What is the role of as-built schedules in litigation involving delays? shows when and where vanaus actuhe where ac performed. 3) a) What is the difference between a recovery schedule and an updated schedule? recany schedule prgects substantial completion byether t -...

  • 1 Which of the following is true regarding the code of accounts? a It allows one...

    1 Which of the following is true regarding the code of accounts? a It allows one to easily identify the breakdown level of the item in the resource structure. b It describes the coding structure used by the performing organization to report financial information in its general ledger. c It is the collection of unique identifiers generally assigned to WBS items. d It defines ethical behavior in the project and the responsibilities to the customer and the profession. 2 You...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT