Question

1) You are about to develop a Heijunka schedule for four products which are processed through...

1) You are about to develop a Heijunka schedule for four products which are processed through four operations in a flow line fashion. The necessary information about processing times, setup times, resource time availability and demand is given below.

Processing times table

Process 1

Process 2

Process 3

Process 4

Part A

10

15

7

9

Part B

12

8

6

12

Part C

13

            9

5

3

Part D

1

7

6

9

Setup times table

Process 1

Process 2

Process 3

Process 4

Part A

25

15

17

9

Part B

12

8

26

12

Part C

13

           19

5

23

Part D

15

7

6

9

Demand table

Part

Demand

A

40

B

120

C

82

D

238

Available processing time table

Process

Available time

Process 1

4550

Process 2

4800

Process 3

4250

Process 4

4650

  1. Find out the minimum batch sizes that will be feasible for each product.
  2. What is the length of this Heijunka cycle?
  3. What will be the best sequence of batches on this schedule?


0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
1) You are about to develop a Heijunka schedule for four products which are processed through...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A company makes four products: Product A sells for $50 but needs $10 of materials; Product...

    A company makes four products: Product A sells for $50 but needs $10 of materials; Product B sells for $75 but needs $30 of materials; Product C sells for $100 but needs $50 of materials; Product D sells for $150 but needs $75 of materials. The labor cost is $15/hr. The processing requirements for each product on each of the four machines are shown in the table. Table 6 Work Center Processing Time (min/unit) A B C D W 3...

  • 1. Suppose you have four jobs that must be processed, with the following table giving their...

    1. Suppose you have four jobs that must be processed, with the following table giving their charac- teristics(all times in hours): Each job can be processed on any of three identical machines; to be Job 1 23 4 Processing time 21.524 | 2 | 0 | 0.5 | 1 Release time Processing time 5346 finished, a job must be processed for its entire processing time, but this processing time can be interrupted and even moved to a different machine if...

  • You have prepared the following schedule for a project in which the key resource is a...

    You have prepared the following schedule for a project in which the key resource is a backhoe. This schedule is contingent on having four backhoes. You receive a call from your partner, Brooker, who desperately needs one of your backhoes. You tell Brooker you are willing to let him have the backhoe if you are still able to complete your project in 13 months. Develop a resource schedule to see if it is possible to complete the project in 13...

  • Problem #1 Five jobs are to be processed through a single machine. The processing times and...

    Problem #1 Five jobs are to be processed through a single machine. The processing times and due dates are given here. Assume all released dates are zero. Job 1 2 3 4 5 Processing time 3 6 5 4 2 Due date 4 8 12 21 15 In each of the following cases determine the sequence in which she should perform and compute Mean Flow Time, Average Tardiness and the number of tardy jobs. A) Shortest Processing Time B) Early...

  • Question 1: You are the lead production engineer for a manufacture that produces four large components...

    Question 1: You are the lead production engineer for a manufacture that produces four large components for the aerospace industry, referred to as components 3, 6, 7, and 9. Given the size and unique nature of these components, you only can produce four parts a day. Your job is to schedule each day’s production. How many different schedules (the sequence of the schedule is important, see example schedules below) are possible that result in components 6 and 7 both being...

  • Six jobs are to be processed through a​ two-step operation. The first operation involves​ sanding, and...

    Six jobs are to be processed through a​ two-step operation. The first operation involves​ sanding, and the second involves painting. Processing times are as​ follows: JOB OPERATION 1 (HOURS) OPERATION 2 (HOURS) A 4 8 B 10 5 C 3 11 D 14 14 E 6 1 F 7 12 a. Using​ Johnson's rule for​ 2-machine scheduling, the sequence​ is: Scheduled Order Job 1 ? 2 ? 3 ? 4 ? 5 ? 6 ? b. For the schedule developed...

  • Question 17 3 pts Refer to Table 4-1. c D E 1 2 3 A Price...

    Question 17 3 pts Refer to Table 4-1. c D E 1 2 3 A Price $12 $10 $8 $6 $4 $2 B D 5 8 11 13 16 18 S 19 17 15 13 11 9 4 S2 14 12 10 8 9 12 15 18 21 24 5 6 7 4 Table 4-1 Suppose that D1 and S1 are the prevailing demand and supply curves for a product. If the demand schedule changes from D1 to D2, then:...

  • please answer this ABC's machine shop is considering the use of priority scheduling rule in the...

    please answer this ABC's machine shop is considering the use of priority scheduling rule in the fabrication shop and must decide whether to use: a. Critical ratio (CR) Earliest due date (EDD) C. Shortest operation next (SON)/Shortest processing time 9SPT) d. Order Slack Order No. Total Remaining Time Remaining Current operation Manufacturing until Due Date Processing time Time (days) (days) (days) А 12 15 10 14 D 18 15 19 Using the four sequencing rules, compute the scheduling priority for...

  • Five processes arrive to run on a CPU. The scheduler puts them in its data structure....

    Five processes arrive to run on a CPU. The scheduler puts them in its data structure. The table below lists the processes, how much CPU time each will need, and the priority of each process. One(1) is the highest priority and 4 is the lowest priority. Process CPU time needed Priority P1 P2 P3 NNW-W a. The scheduler uses First Come First Serve to schedule the jobs. Fill in the time line below showing at what time each process starts...

  • Table Workstation 1 has five jobs waiting to be processed. It is now time 0, and...

    Table Workstation 1 has five jobs waiting to be processed. It is now time 0, and times are expressed in terms of hours. All pertinent data are given in the following table. Job Time Since Job Arrived Processing Time Due Date A 8 3 10 B 7 6 14 C 6 3 2 D 4 2 6 E 1 5 16 Using the information in the Table and the SPT rule, what is the average flow time? Fewer than or...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT