Planning values |
|||
Starting inventory: |
1000 |
||
Starting and ending workforce: |
100 |
||
Hours worked per month per worker: |
160 |
||
Hours per unit: |
40 |
||
Hiring cost per worker: |
$5,000 |
||
Layoff cost per worker: |
$2,000 |
||
Monthly per-unit holding cost: |
$8 |
What would actual production be for December if the December forecast was for 1200 units, and we used a level production that involves staffing 350 workers in December?
Production = 350 workers x 160 hours per worker x 1 / (40 hours per unit)
= (350 x 160 / 40) units
= 1,400 units
Planning values Starting inventory: 1000 Starting and ending workforce: 100 Hours worked per month per worker:...
Complete the level production plan, using the following information. The only costs you need to consider here are layoff, hiring, and inventory costs. If you complete the plan correctly, your hiring, layoff, and inventory costs should match those given here. E: Click the icon to view the costs table. Click the icon to view the forecasted sales. Fill in the production plan table below (enter your responses rounded to the nearest whole number). Month Forecasted sales Sales in worker hours...
Develop a production schedule to produce the exact production requirements by varying the workforce size for the following problem The monthly forecasts for Product X for January February, and March 1010, 1510 and 1180 respectively. Safety stock policy recommends that half of the forecast for that month be defined as safety stock. There are 22 working days in January, 19 in February, and 21 in March. Beginning inventory is 530 units Manufacturing cost is $180 por unit, storage cost is...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...
A company believes that its demand for the next six months is as follows ota ont eman The output per worker per month is 100 units. The per worker hiring and lay off costs are $1,500 and $3,500, respectively. There is no beginning inventory, and the starting workforce is 135. It cost the company $25 to carry an item in inventory each month, and the stockout costs is estimated to be $25 per unit. Develop a level sales and operations...
AGGREGATE PLANNING Garden Hub makes a single product, a garden tool that sells for $40. Garden Hub starts with 1000 of these tools in inventory and is expected to end with at least 500 in stock. Garden Hub can temporarily backlog demand for a cost, but at the end of the time horizon, they require their backlog to be zero – This is an important constraint to remember- if we forget it, we will get strange results . Production costs...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...
Plan B: Vary the workforce to produce the prior month's demand. The firm produced 1,300 units in June. The cost of hiring additional workers is $35 per unit produced. The cost of layoffs is $60 per unit cut back. (Enter all responses as whole numbers.) Note: Both hiring and layoff costs are incurred in the month of the change (i.e., going from production of 1,300 in July to 1200 in August requires a layoff (and related costs) of 100 units...
Problem 8-8 Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply,...
Problem 8-14 (Algo) Develop a production schedule to produce the exact production requirements by varying the workforce size for the following problem. The monthly forecasts for Product X for January, February, and March are 1,010, 1,540, and 1,180, respectively. Safety stock policy recommends that half of the forecast for that month be defined as safety stock. There are 22 working days in January, 19 in February and 21 in March. Beginning inventory is 530 units. Manufacturing cost is $180 per...
Check my wa will have 400 mowers in inventory at the beginning of the month and desires to maintain at least that number at the end of each month. Assume hiring and layoff/firing, if necessary, occur at the beginning of the quarter. Below is other critical data: Production cost per unit = $230 Inventory carrying cost per month per unit = $50 (based on ending month inventory) Hiring cost per worker = $420 Firing cost per worker = $540 Beginning...