Question
please show working
approxma 02, supplemented with overtime.) 16. MT makes small camping and snowmobile trailers. The demand for camping trailers
ing and Master Scheduling Assume temporary workers wa ity are the same as permanent worke temporary workers work only during

the question is complete. 16 a) b)c)d)
approxma 02, supplemented with overtime.) 16. MT makes small camping and snowmobile trailers. The demand for camping trailers occurs between January and June (mostly in April and May). MT makes camping trail- ers from January to June, shuts down in July and then makes snowmobile trailers from August to November. Suppose now is the end of December. For simplicity, we consider every two months as a period. The forecasts for camping trailers during each of the next three periods (six months) are Lo2 Period 3 Period2 Period 1 869 1,730 1,374 MT employs 40 permanent workers who are paid an average of $20 per hour (including fringe benefits) and work approximately 320 hours a period (two months). They make approximately 1,000 camping trailers per period during regular time. They can also work up to 50 percent more as overtime (i.e., up to 12 hours a day vs. the regular 8 hours a day) and will be paid 1.5 times the regular wage rate. Alternatively, MT can hire up to 40 additional temporary workers to work during a sec- ond shift. Hiring cost is $3,000 per temporary worker.
ing and Master Scheduling Assume temporary workers' wa ity are the same as permanent worke temporary workers work only during rate and productiv. :. Also assume reezers, and that temporary workers work onlyd (no overtime) and are kept for whole two months or four months). Inventoue, for per camping trailer per period is S180, ad to average inventory level during each period. c there are no camping trailers on hand, and the en inventory at the end of period 3 is zero small positive number is also acceptable). MT to meet the total demand, but shortage durine wishes (except last) is acceptable, in w is assumed to be back ordered at the cost of sorage camping trailer per period. a. Calculate all the relevant unit costs. b. Suppose MT uses permanent workers during regular time and overtime. Determine the minimum cost plan in this case. (Hint: Use overtime in each de ion planner regular time ods (i.e., nt manager each quar- 3: 35,000 in Janu- , is.$180, and ischarged r of next ance in sirable. (althouc d that e are a period hich case the s per p to per ime our ry rs period.) c. Suppose MT hires temporary workers, but decides not to use permanent workers during overtime (just regu- lar time). Determine the minimum cost plan in this case. (Hint: Hire 15 temps for two periods and nine temps for one period starting in period 2.) d. Would overtime production by permanent workers and regular time production by temporary workers simul- taneously result in a lower total cost? Do a trade-of analysis. What is the overall minimum cost plan? 02 17. Mity-Lite (ML) is a manufout
0 0
Add a comment Improve this question Transcribed image text
Answer #1

SOLUTION:-

Forecas ts Period 2 Period 3 Period 1 869 1730 1,374 Permanent Workers 40 Regular Working Hours/ worker in a period (2 month)forward to meet the demand in next period. In the next period, extra production requirement is (1730-1000+131) 599. Regular p# IF YOU HAVE SATISFIED MY WORK PLEASE THUMBS UP AND IF YOU HAVE ANY DOUBT PLEASE COMMENT IT.

Add a comment
Know the answer?
Add Answer to:
please show working the question is complete. 16 a) b)c)d) approxma 02, supplemented with overtime.) 16. MT makes...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 1 (Aggregate planning): Martin Trailers (MT) is a manufacturer of small camping and snowmobile trailers...

    Problem 1 (Aggregate planning): Martin Trailers (MT) is a manufacturer of small camping and snowmobile trailers in Ontario (lvey case #9A82D006). The demand for the camping trailers occurs between Jan and Jun of each year (mostly in Apr and May). Aggregate demand (in units) is: Jan 450 Feb 525 Mar 675 Apr 1005 May 1,125 Jun. 600 MT employs 40 permanent workers who are paid $20 per hour and each worker works 150 hours per month. Together they make approx....

  • Whether to Work Overtime or Hire Additional Employees The Fair Labor Standards Act requires employers to...

    Whether to Work Overtime or Hire Additional Employees The Fair Labor Standards Act requires employers to pay nonexempt status employees an overtime rate at least equal to 1.5 times the normal hourly wage for each hour worked beyond the 40​-hour workweek period. ACME manufacturing has just signed a lucrative contract to produce the casings for flashlights. The contract spans five years. During this​ time, ACME must increase its total manufacturing output by 25 percent. To meet this added​ demand, the​...

  • please showing working.. formulas 10. A company produces sofas. The manager wants to prepare a 0. am for the next si...

    please showing working.. formulas 10. A company produces sofas. The manager wants to prepare a 0. am for the next six months using the following information: plan Month 2 3 456 160 150 160 180 170 140 recast demand For Cost Per Unit Regular time $100 Overtime $150 Part-time $120 Inventory, per month $10 Back order, per month $50 There are five workers, each making 30 sofas a month. The maximum number of sofas produced during overtime is 30 per...

  • Develop a production plan and calculate the annual cost for a firm whose demand forecast is...

    Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 11,000; winter, 7,700; spring, 6,700; summer, 13,000. Inventory at the beginning of fall is 550 units. At the beginning of fall you currently have 30 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular workforce on...

  • This is a Construction Management class, so will you please be able to provide a step...

    This is a Construction Management class, so will you please be able to provide a step wise solution of how you were able to calculate the answer. Case Problem WORKFORCE SCHEDULING Davis Instruments has two manufacturing plants located in Atlanta, Georgia. Product de mand varies considerably from month to month, causing Davis extreme difficulty in work force scheduling. Recently Davis started hiring temporary workers supplied by WorkForce Unlimited, a company that specializes in providing temporary employees for firms in the...

  • Here is an operations planning case analysis. You are expected to do the following questions and...

    Here is an operations planning case analysis. You are expected to do the following questions and submit them for marking at the end of the semester via utsonline and in hard copy to your tutor in week 10. A company has the following demand forecast next year, expressed in six bimonthly periods: Forecast Demand: Period 1 = 4,500 units Period 4 = 6,500 units Period 2 = 3,000 units Period 5 = 5,100 units Period 3 = 4,800 units Period...

  • Problem 8-7 Develop a production plan and calculate the annual cost for a firm whose demand...

    Problem 8-7 Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 10,700; winter, 8,300; spring, 6,900; summer, 12,700. Inventory at the beginning of fall is 535 units. At the beginning of fall you currently have 35 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular...

  • 02 Consuelo Chua, Inc., is a disk drive manufacturer in need of an aggregate plan for...

    02 Consuelo Chua, Inc., is a disk drive manufacturer in need of an aggregate plan for July through December. The com- pany has gathered the following data: COSTS Holding cost $8/disk/month Subcontracting 580/disk Regular-time labor $12 hour Overtime labor $18 hour for hours above 8 hours/workerday Hiring cost $4000/ worker Layoff cost $8000/worker DEMAND Note: In this problem (and Q3) the production cost should be computed based on the labor cost OTHER DATA Current worden 8 people Labor hours disk...

  • Forrester and Cohen is a small accounting​ firm, managed by Joseph Cohen since the retirement in ...

    Forrester and Cohen is a small accounting​ firm, managed by Joseph Cohen since the retirement in December of his partner Brad Forrester. Cohen and his 33 CPAs together bill 620 hours per month. When Cohen or another accountant bills more than 155 hours per​ month, he or she gets an additional​ "overtime" pay of​ $63.20 for each of the extra​ hours: this is above and beyond the 4,900 salary each draws during the month.​ (Cohen draws the same base pay...

  • Please answer questions using Microsoft excel, and please show formulas. Thank you. School of Business BUS...

    Please answer questions using Microsoft excel, and please show formulas. Thank you. School of Business BUS 476-Operations Management Dr. Enrique G. Zapatero, Professor Homework #8-Aggregate Planning Instructions: Use MS Excel to produce the computations to support your answers to ProblemsI, and I. Problem I: A production manager needs to develop a production schedule to meet the following demand Period Demand 600 600 800 1000 1200 600 2 Productions costs are as follows: (a) regular time: $3 per unit. (b) over-time:...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT