Question 2 Draw the following network using Line Of Balance "LOB" method and find project duration...
The following table illustrates the activities of a small project Duration Days) Activity Depends orn 7 7 9 2 419 A a. Calculate the mean Project duration; b. Write and Highlight the Critical Path; c. Find the probability to finish this project at 15 days; d. Find the probability to finish this project at 19 days; e. Find the project duration that satisfies probability equal to 8 %; f. Find the project duration that satisfies probability equal to 92 %.
Draw the following network and calculate all dates (all activities are contiguous): Activity Duration IPA Type Rel Lag ES EF LS LF TF FF A 4 - B 3 - C 8 A D 7 A,B E 6 D SS 3 F 3 D FF G 5 F SS 2 2 F FF please do not copy from others, they are wrong
Assignment for week 5Given the following information, draw the project network. Compute the early, late and slack times for the project network. which activities are on the critical path have only the start or finish of the activity on the critical path?ID duration finish to start finish to start additional lag lag predecessor lag Relationship A 2 none 0 none 0B 4 A 0 none 0C 6 A 0 finish-finish C to F 7D 8 A 0 none 0E 18...
QUESTION 1 Please use the information below to draw and solve the network on a piece of paper by: Complete the forward and backward pass Identify the critical path Fill in the requested information (Example: ESA Early Start of Activity A; LFA Late Finish of Activity A, etc) Relationship Activity Contract sign Predecessor Activity ID Duration 3 А Survey В 2 А Target market C Data В,С D 7 collection Presentation 2 FS Lag 3 E В Analyze F 2...
Q1. a) Draw a project network using (AOA) method, b) and calculate (EST, EFT, LFT, LST) for each activity, c) and define the critical path. Activity Symbol A B C Predecessor Activity D E F G Duration (Weeks) Nil Nil Nil 5 9 4 B 7 AC C 8 7 D F
Given the following information, Construct the PDM network and use the information given in the following table, calculate ES, EF, LS, LF and the critical activities. Project Data: 1-U and R can be performed concurrently and both begin on the start of the project. 2-Activity X is independent of both activities Q and K 3-E must start before work on activity K can begin. 4-Neither activity F nor activity G can start before activity R start. However, activities F and...
2. For the following project draw a node network and a bar chart. Then perform resource leveling trying to reduce the daily resources needed to no more than 8 laborers per day. If you cannot get it down to 8, manually shift resources so that the project starts low and gradually increases towards the middle and gradually decreases toward the end of the project Duration (days) laborers Activity IPA А 6 2 В 2 C 8 3 5 А, В...
2) The following tasks been assigned for a project following the steps needed to develop a project network. Show al necessary steps and graphical representations. Find: 1 Critical Path for this project 2) Total free slack times for each activity 3) Total completion Time 4) The latest time that the activity D must be started to complete the project by day 54 Activity Predecessor Activity Time A |None None M,L.K 3) How would you calculate the duration of an activity...
QUESTION 2 Given the following information, you are to determine the following Project network. Early, late and slack activity times. Project duration. Critical path Task Predecessor Duration A None 8 B A 5 C A 10 D A 15 E A 10 F B 12 G C, D 12 H E, 7 I G, H 7 J F,G,I 10 K J 12
I need help Software Project Management question Q1. For the following table of information: a) Draw a network diagram (Activity on Arrow) b) List down all the network paths c) Determine the critical path(s) Activity Predecessor Duration A Start 5 days B A 2 days C A 3 days D B 4 days E C 6 days F C 3 days G D, E 4 days H F 2 days I G 3 days J H 1...