Question

Question 20 June 3390 What does the hiring and training cost mean in the table below? (CL03) (3 marks) month Jan Feb Mar Ap
→ Moving to another question will save this response. Question 21 May 6788 17 June 3390 24 What does Lay off costs mean in
my w anoner question will save this response. Question 22 What does labor hours required mean in the table below? (CL03] (3
0 0
Add a comment Improve this question Transcribed image text
Answer #1

20) Hiring and training cost refers to the cost for hiring a worker and provide training for him for the job. Hence the answer is option 6- it means that the cost for hiring and training one worker is 210$.

21) Lay off cost refers to the cost incurred for ending the service of a worker. Hence the answer is option 3- it means that the cost to end the services of one worker is 150$.

22) The answer is option 1- it means: How long it requires for each worker to spend to produce one unit. Labour hours required is the hours of labour required to produce one unit of a good.

Add a comment
Know the answer?
Add Answer to:
Question 20 June 3390 What does the "hiring and training cost" mean in the table below?...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • $75 $15 1 $20 Materials = Holding costs = Marginal cost of backorder = Hiring and...

    $75 $15 1 $20 Materials = Holding costs = Marginal cost of backorder = Hiring and training cost = Layoff costs = Straight time labor cost/hr. $250 $300 Beginning Workers Beginning inventory = Productive hours/worker/day = Paid straight hrs/day = Working days per month = Units per worker per month El ng Inventory goal (December) 110 2200 7.25 8 20 100 1000 $18 Question 8 1 pts Given the following production plan, use a level production strategy to compute the...

  • Develop a production schedule to produce the exact production requirements by varying the workforce size for...

    Develop a production schedule to produce the exact production requirements by varying the workforce size for the following problem The monthly forecasts for Product X for January February, and March 1010, 1510 and 1180 respectively. Safety stock policy recommends that half of the forecast for that month be defined as safety stock. There are 22 working days in January, 19 in February, and 21 in March. Beginning inventory is 530 units Manufacturing cost is $180 por unit, storage cost is...

  • Problem 8-14 (Algo) Develop a production schedule to produce the exact production requirements by varying the...

    Problem 8-14 (Algo) Develop a production schedule to produce the exact production requirements by varying the workforce size for the following problem. The monthly forecasts for Product X for January, February, and March are 1,010, 1,540, and 1,180, respectively. Safety stock policy recommends that half of the forecast for that month be defined as safety stock. There are 22 working days in January, 19 in February and 21 in March. Beginning inventory is 530 units. Manufacturing cost is $180 per...

  • Plan production for a four-month period: February through May. For February and March, you should produce...

    Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...

  • The total subcontracting costequals=​$ ???? ​(Enter your response as a whole​ number.) Total cost with plan...

    The total subcontracting costequals=​$ ???? ​(Enter your response as a whole​ number.) Total cost with plan 5​ = ???? Juarez has yet a sixth plan. A constant workforce of 7 is​ selected, with the remainder of demand filled by subcontracting. Evaluate this plan.The production rate per day equals= ???? A Juarez, Mexico, manufacturer of roofing supplies has developed monthly forecasts for a family of products. Data for the 6-month period January to June are presented in the table below. There...

  • Plan production for a four-month period: February through May. For February and March, you should produce...

    Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...

  • Need help filling the empty slots above in. What is Plan A's cost = ___?(enter response...

    Need help filling the empty slots above in. What is Plan A's cost = ___?(enter response as a whole number) Refrigeration Corp. needs an aggregate plan for January through June for its refrigerator production. The company has developed the following data: B Click the icon to view the company's data. Consider the two following strategies. a) Plan A: Vary the workforce so that production meets the forecasted demand (maintain inventory at 250 units). Bell had eight employees on staff in...

  • Problem 8-8 Plan production for a four-month period: February through May. For February and March, you...

    Problem 8-8 Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply,...

  • Please help me fill those in and also what is Plan B's cost = ____$? (enter...

    Please help me fill those in and also what is Plan B's cost = ____$? (enter your response as a whole number) Refrigeration Corp. needs an aggregate plan for January through June for its refrigerator production. The company has developed the following data: Click the icon to view the company's data. Consider the two following strategies. a) Plan A: Vary the workforce so that production meets the forecasted demand (maintain inventory at 250 units). Bell had eight employees on staff...

  • The Austin, Texas plant of Computer Products produces disk units for personal and small business computers....

    The Austin, Texas plant of Computer Products produces disk units for personal and small business computers. Gerald Knox, the plant’s production planning director, is looking over next year’s sales forecasts for these products and will be developing an aggregate capacity plan for the plant. The quarterly sales forecasts for the disk units are as follows: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 2,310 1,980 1,980 2,340 Ample machine capacity exists to produce the forecast. Each disk unit takes an...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT