Predecessors below Worst Duration 10 Index Tasks Best Duration Most Likely Duration Market Research Cost Analysis...
Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m b Time (t) o 2 3 2 1 B с D NWN mlm A 1 A,B 2 4 1 6 7 9 F 1 с с DE F,G 4 2 5 3 G 4 12 H 2 4 From the table above find the flowing answers. 1. Construct the project Network 2. Find the expected duration and Variance of each activity 3. Find the...
please help!! The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assu that the activity times are independent. Time (weeks) Immediate Time (weeks) Immediate Activity a bPredecessor(s)Activitya bPredecessor(s) 12 10 12 8 17 This exercise contains only parts a, b, c, d, and e a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response...
It was determined on the following project that the duration for the tasks contained some uncertainty. After more research, the optimistic and pessimistic values were determined. 1. a. Calculate the expected time and variance (using the 95 percent level of confidence) for each activity. b. Determine the critical path and time for completion c. Calculate the probably that the project will finish in 30 days. Calculate the probably of completing the project in 27 days. Other than the critical path,...
2. Using the information in Table 1, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible: Table 1: Project description Task Description Predecessor/s Duration (working days) 5 15 25 15 A B A B с D E F G H Requirement Analysis Systems Design Programming Telecoms Hardware Installation Integration System Testing Training/Support Handover and Go-Live B B 30 CD E, F 10...
Q1. (10 marks) Construct an activity on arrow network based on the activity descriptions below. Show all your work. Label activities in the network by their activity letters and node numbers. Remove any redundant dependencies and label dummy activities DUMMY1, DUMMY2, etc. • Activities H, R2, T1 start the project. • Activity T2 can start when Activities H, E1 and S are completed. • Activity E1 also depends on Activity R2. • Activity X follows Activity H and precedes Activity...
Use a PERT network to establish the expected duration for the project described in the table below: (SHOW the PERT NETWORK) Activity Predecessors Duration a m b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400 600 D B, C 4 6 8 200 600 E B, C 6 9 12 400 300 F C 4 6 14...
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Time (weeks) Immediate Time (weeks) Immediate Activity a m b Predecessor(s) Activity a m b Predecessor(s) A 6 8 10 — G 3 3 5 C, E B 2 9 23 A H 1 1 1 F C 8 12 18 A I 7 7 7 F D 4 7 10 A J 4 7 14 D, G,...
PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building ne a b 2 5 1 Activity А B С D E F 1 Time (weeks) a m b 6 8 10 2 9 23 9 12 16 5 6 10 1 3 4 5 9 20 Immediate Predecessor(s) Activity G A H А А B к CE Time (weeks) m 3 1 7 7 3 Immediate Predecessor(s) CE F...
2. Given the table below (10 pts): A. Draw the project network B. Calculate the expected time to complete each activity as well as the variance (or standard deviation) associated with that time C. Determine the time associated with each potential path and denote the critical path D. Given the calculated data, what is the probability of completing the project in 30 days? 35 days? E. If you were to try to improve your performance (in terms of time), what...